This document contains questions and answers related to the John Day Ponds Dredging Project, ITB S-63500-00003680, issued by the Oregon Department of Fish and Wildlife. The project involves dredging two ponds in the John Day, Oregon area that have become filled with muck over the past 30 years. Key details include that the goal is to have uniform solids removal across the ponds, with the contractor responsible for fencing the work area and restoring the property to its original state upon completion. The contractor will be allowed to operate 7am-8pm, Monday-Friday, and will be compensated on a lump sum basis, not per cubic yard. Any debris removal required for the dredging will be paid through change orders, and the owner will provide the disposal site for the dredged material.

Regarding pricing, the owner will not currently consider changing the bid form from lump sum to per cubic yard. The owner will pay for any cubic yards in excess of 6,800 if the budget allows. The contractor will no longer be responsible for removal of the dewatered material. Certain environmental requirements, such as using environmentally safe polymers, must also be met.

View the file

Other files

File Type Posted
017-23 ITB for John Day Ponds Dredging OregonBuys 6929.pdf PDF
5622 NOTICE OF AWARD.pdf PDF
Pre bid attendees list.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and answers for S-63500-00003680 John Day Ponds Dredging Project

1. Will the Agency consider extending the bid due date one week?

0. Has been done thanks to Alan!

1. Page 3, Section 1.1, P#3: Please clarify the objective for solids removal, uniform across the ponds, or concentrated in areas depicted in the drawings?

1. This will depend on the bids that come in, but the goal would be uniformed across the pond. The pricing is what will dictate which way we will go.

1. Page 3, Section 1.1, P#3: Section 6: Will the owner pay for any cubic yards in excess of 6800, if authorized by owner?

2. Yes, if the budget will allow for it.

1. Page 46, attachment D Bid Proposal Form: Will the owner consider changing the bid unit rate from Lump Sum to per Cubic Yards?

3. Not currently.

1. Page 10, section 6, P#1: How does the owner propose to measure CYD for payment?

4. This is not relevant since it is a hard bid.

1. Page 10, Section 6, P#1: Please designate the specific location for Geotube laydown area at the 7th street pond.

5. The bags will have to be placed in the parking lot area adjacent to the pond.

1. Please clarify if an impervious liner would need to be installed if using the parking lot.

6. Yes, all excess water will have to be contained within the area provided and the pumped back into the pond.

1. Page 3, Section 1.1, P#4: Please provide a diagram, or description of area to be fenced.

7. Any location that work is taking place or equipment is being stored.

1. Page 3, Section 1.1, P#4: What restoration is required following fence removal and/or dredging?

8. Property must be returned to original state.

1. Page 10, Section 6, P#1: If polymer is needed to treat solids, is there a limitation on type (i.e. NSF)?

9. Must be environmentally safe and have documentation on this on what is being applied.

1. Page 3, Section 1.1, P#5: Please confirm that the contractor is responsible for the removal of the material dewatered from the 7th st pond.

10. Please clarify if there are any disposal restrictions (percent solids, stacking etc.) at the city’s designated disposal site.

10. Contractor will no longer be responsible for removal of material at either locations.

1. Page 3, Section 1.1, P#2: Please verify the elevation of the native bottoms of the ponds.

11. The exact details of this are unknown since there are no as-builts for either pond. They will have to do their own due diligence to determine this.

1. Page 10, Section 6, P#1: Regarding debris in the ponds, the ponds cannot be dredged without removal of trees at minimum. Please confirm that removal of debris necessary for dredging will be paid through change order.

12. Yes it will be, this was stated at the meeting.

12. If not, can the debris be dragged out, or do they need to be lifted out onto the bank.

12. Can the debris be left on the bank, or do they have to be placed back in the pond(s)?

12. No

12. If to be placed back, can the debris be dragged back or do they need to be lifted and placed?

12. Once again, both properties must be returned to original state after dredging has been completed.

1. Page 10, Section 6, P#1: Please confirm hours per day, and days per week contractor is allowed to operate.

13. 7am – 8pm, Monday – Friday