Questions and Answers for BLDG 700 Carpet Replacement SSN Responses.xlsx
XLSX spreadsheet 11 KB Posted
- Solicitation number
- W911S026RA018
About this file
This is a Questions and Answers document for the Building 700 Carpet Replacement Project solicitation (W911S026RA018) issued by the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Eustis. The document addresses clarifications from potential offerors regarding project scope and specifications for carpet replacement in Building 700.
The project encompasses approximately 9,100 square feet of carpet replacement work to be completed during regular duty hours (8 a.m. to 4 p.m., Monday through Friday), with a pre-construction site visit requested post-award. The existing flooring varies by area as detailed in the attached Materials Key, installed over a concrete tile system with bolted, raised subflooring. The existing rubber base is 4 inches and will not be replaced per end-user request, as the current cove base is in good condition. No asbestos testing has been conducted on the existing materials, representing the first carpet replacement since the building's initial construction in 2011. A floor plan with marked areas indicating new flooring installation has been provided to offerors. This is an LPTA (Lowest Price Technically Acceptable) procurement, and all proposal responses should be submitted to the Contract Specialist via email to Mr. Jared Maunz (jared.b.maunz.civ@army.mil) and Mr. Curtis Arthur (curtis.m.arthur.civ@army.mil) by the stated closing deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Carpet Replacement RFP - Addendum to 52.212-1 and Addendum to 52.212-2 .docx | DOCX document | |
| B700 Carpet Finishes and Locations.pdf | ||
| PWS-B700 Carpet Replacement_clean.pdf | ||
| Solicitation - W911S026RA018.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question Number | Questions | Answers |
| 1 | Would you be able to provide a floor plan for this opprtunity or Approx Sq Ft? | Please see floor plan attachment and Approx 9100 SF. |
| 2 | What is the project working hours? | Regular duty hours (8-4; M-F); Pre-construction Site Visit requested post award/NTP. |
| 3 | What is the total QTY & if possible, could you please provide a floor plan with marked areas that are receiving new flooring? | Don’t understand the QTY component of this question. The floor plan with marked areas is attached. |
| 4 | What is the size of wall base 4" OR 4.5" OR 6"? | Base is rubber 4". End User is asking to not replace the cove base. The existing cove base is rubberized and in good condition. |
| 5 | What is the existing flooring installed? | See "Materials Key" in the attachment. |
| 6 | What is the sub-floor wood or concrete? | Concrete tile system; bolted, raised. |
| 7 | Has an asbestos testing been done if so could you please provide that? | Not to my knowledge. This is the first carpet replacement since initial construction in 2011. |