About this file
This is a Questions and Answers document for a painting services Request for Proposals (RFP) issued by the Nevada State Purchasing Division on behalf of the Department of Employment, Training, and Rehabilitation (DETR) for work at a Southern Nevada facility located at 2800 E St. Louis Ave. The scope encompasses approximately 50,000 square feet of exterior stucco pressure washing, preparation, patching, caulking, priming as needed, and latex stucco paint application to sun-faded areas including the main entry, elevator shaft, staff entries, walls, security yard, metal gates, structural steel, stairwells, bridges, doors, frames, curbs, fire hydrants, bollard lights, concrete bollards, graffiti-covered concrete walls, electrical boxes, and decorative fencing. The project must be completed by June 30, 2026, with preferred working hours Monday through Friday from 6:00 a.m. to 5:00 p.m. The State will provide full access to all areas requiring paint as well as water and electricity on-site. No pre-bid meeting will be held for this project. Responses were due March 30, 2026, at 5:00 p.m. Pacific Time, with the question submission deadline March 25, 2026, at 5:00 p.m. Pacific Time and answers posted by March 26, 2026.
A full primer coat is not required for all areas; primer will be applied only as needed based on surface condition. The State will pre-approve specific paint brands and colors before work begins, and contractors should not assume a particular brand preference when developing cost estimates. Water and electricity access will be provided at no cost to the contractor. If weekend work is scheduled, operations management will coordinate access to restricted areas such as the elevator shaft. The evaluation criteria are cost (30 percent), experience and qualifications (20 percent), project timeline (20 percent), and communication and customer service (30 percent). Nevada-based businesses receive a five percent preference. Required insurance includes Commercial General Liability with a $2,000,000 General Aggregate limit, $1,000,000 Products-Completed Operations Aggregate, $1,000,000 Personal and Advertising Injury, $1,000,000 Each Occurrence, Automobile Liability with a $1,000,000 Combined Single Limit, and Workers' Compensation at statutory limits.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Standard-form-contract~13.docx | DOCX document | |
| Terms-and-conditions-for-services~16.pdf | ||
| Copy of Cost Schedule.xlsx | XLSX spreadsheet | |
| Quote Instructions.pdf | ||
| Insurance Schedule - Standard~10.docx | DOCX document | |
| Painting Services Solicitation.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Questions and Answers for Solicitation 90DETR-S3789 | |||
| Question 1: Could you provide the approximate total square footage of the exterior stucco areas to be painted? Are there any site plans, drawings, or photos available showing the full scope? Is a full primer coat required for all areas, or only as needed based on surface condition? Are there specific paint brands required, or can the contractor propose equivalent systems? | Answer: Approximately 50,000 sqft. Digital prints are not available at request. Architectual prints are available at the site only. A full primer coat is not required for all areas. There will be a pre-approval from the Department regarding specific paint brand and color will be established beffore work is to be started. | ||
| Question 2: What is the expected project timeline and preferred working hours (weekdays vs. weekends)? Will the State provide full access coordination, or are there restricted zones with specific scheduling requirements? | Answer: This project must be completed before 6/30/2026. Preferred working hours will be Monday through Friday 6am-5pm. The state will provide full access to all of the areas that require paint. | ||
| Question 3: The solicitation specifies curb measurements, but could you provide the approximate total square footage for the exterior stucco areas? 2. Is a full primer coat required for all stucco, or only as needed for patched cracks and faded areas as mentioned in section 3? 3. Since the owner will select the paint, do you have a preferred brand or quality level we should use for our cost estimate? | Answer: See answer 1. | ||
| Question 4: | 1. Will the State provide access to water and electricity on-site for pressure washing and equipment, or should the contractor include these costs? 2. Regarding weekend work, is there a specific schedule or notice required to coordinate access to restricted areas like the elevator shaft? | Answer: Yes the contractor will have access to water and electricity. If weekend work is scheduled operations management will cordinate access to restricted areas while the work is being preformed. | |
| We would like to know if there will be a pre bid meeting for this project and if there is an estimated budget. | Answer: We will not be holding a pre-bid meeting for this project.DETR is focused on selecting the vendor that offers the best overall value based on the proposed solution and its ability to meet the requirements outlined in the RFP. We encourage vendors to submit proposed solutions that are both cost-effective and aligned with the scope outlined in the RFP. |
File details come from the government source that posted it. Updated .