QUALIFICATION_SUBMITTAL_FORM.pdf

PDF 78 KB Posted

Attached to
Pave Strawberry Parking Lot (PID 004570A) - St. Pete-Clearwater International Airport STEP 2
Solicitation number
23-0593-ITB-C STEP 2
Issued by
Pinellas County, Clewiston City, Florida

About this file

The Qualification Submittal Form is a document from the Florida Department of Transportation (FDOT) for contractors bidding on the Strawberry Parking Lot project at St. Pete-Clearwater International Airport. The form is designed for contractors who are not pre-qualified with FDOT and requires detailed documentation to demonstrate project eligibility. Contractors must provide information about four similar past projects, including project descriptions, owner and project manager contact details, project award and final amounts, design estimates, change orders, and scheduled and actual completion dates. The form also requires contractors to specify their qualified work types, which include categories such as bascule bridge, fixed bridge, roofing, bridge repair, building, mechanical, electrical, and various infrastructure-related work types.

The document mandates that non-pre-qualified contractors submit additional documentation, including a bonding letter, vendor information form, and at least three reference letters from companies where similar projects have been completed. Contractors must provide comprehensive vendor information, including firm details, street address, and officer/director information. The qualification process involves a background check and review, with a clear warning that failure to meet any of the specified conditions will result in disqualification from moving forward to Step Two of the bidding process. The form is part of a competitive procurement process that aims to ensure only qualified and experienced contractors are considered for the airport parking lot reconstruction and expansion project.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALIFICATION SUBMITTAL FORM

STEP 1

Part A

If you are currently a pre-qualified construction contractor with FDOT in the applicable work type, please check box and fill out Vendor Information Form and return with signed Part A pages below.

I am Pre-qualified with FDOT in one or more of the work class(s) as referenced in the Special Conditions Section.

Signature by Contractor for Part A Only: ___________________________________________________

If you are not pre-qualified with FDOT, please complete PART B and include all Qualification Forms.

Part B

Applicable only for contractors who are not pre-qualified with FDOT in in one or more of the work class(s) as referenced in the Special Conditions Section.

The invitation to bid for this Project requires that this qualification submittal be included with the proposal and completed in its entirety.

A component of the Pre-Qualification of Bidder process is background check and review. If you are not currently pre-qualified with FDOT please provide the following documentation and include with Qualification Submittal Forms by Step One due date referenced in the Notice Section.

1. Provide a bonding letter from surety or a letter of parent guarantee indicating at a minimum the maximum amount of the budget estimate referenced in the Notice Section.

2. Please complete and return the Vendor Information Form.

3. Confirm Project Work Type(s) (outlined below – check appropriate box(es)

4. Provide your experience on Qualification Submittal Forms below outlining projects of a similar size and scope.

5. Provide a minimum of three reference letters from companies that you have performed projects of a similar size and scope.

Work Types your company is qualified to perform - *Check all boxes that apply

Project Work Types

Bascule Bridge Fixed Bridge Roofing

Bridge Repair Marine Well Drilling

Building Mechanical Water and Sanitary Sewer

Electrical Road, Street, Storm Sewer

**If any of the above conditions are not met, your company will be disqualified from moving forward with Step Two.**

Applicable only for contractors who are not pre-qualified with FDOT. The invitation to bid for this Project requires that this qualification submittal be included with the proposal and completed in its entirety.

NOTE: BIDDER SHALL SUBMIT QUALIFICATION SUBMITTAL ON THE FORM PROVIDED HEREIN

TO PROVIDE THE QUALIFICATION REQUIREMENTS AS SPECIFIED IN

Company Name: Please include below

Project 1 (of similar type) Description

Owner of Project - Contact Information

Name

Address

Telephone Number and Email Address:

Project Manager - Contact Information

Address

Telephone Number and Email Address:

Project Award Amount: $

Final Project Total Amount: $

Design Professional/Engineer Estimate:

$ Change Orders $

Scheduled Completion Date

Actual Completion Date

QUALIFICATION SUBMITTAL FORM (continued)

Project 2 (of similar type) Description

Project Manager - Contact Information

Address

Telephone Number and Email Address:

Project Award Amount: $

Final Project Total Amount: $

Design Professional/Engineer

Project 3 (of similar type) Description

Project Manager- Contact Information

Address

Telephone Number and Email Address:

Project Award Amount: $

Final Project Total Amount: $

Design Professional/Engineer

Project 4 (of similar type) Description

Project Manager- Contact Information

Address

Telephone Number and Email Address:

Project Award Amount: $

Final Project Total Amount: $

Design Professional/Engineer

Applicable only for contractors who are not pre-qualified with FDOT

The invitation to bid for this Project requires that this qualification submittal be included with the proposal and completed in its entirety.

Vendor Information Firm Name:

Street Address:

City:

State:

ZIP:

Additional Info:

Officer/Director Information

Officer/Director/Member:

Title:

DOB:

SSN:

Notes:

Officer/Director/Member

Additional Information: (On Vendor or Contract Requirements)

File details come from the government source that posted it. Updated .