QL Water Line SOW.pdf
PDF 1 MB Posted
- Attached to
- QL Water Line Federal contract opportunity
- Solicitation number
- 12970224Q0034
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to abandon the existing Queen Lily Campground water source and install a new distribution system connected to the North Fork Campground Water System. The key tasks include demolishing existing hydrants and drain infrastructure, capping the existing water source, and installing new distribution lines and hydrants. An optional task is to remove the existing Queen Lily water system tank and associated infrastructure. The project is located in Plumas County, California, with a period of performance of 125 calendar days, occurring outside the campground operating season. The contractor is required to provide all personnel, equipment, materials, and services necessary to complete the work. The key deliverables include a proposed schedule, project plan, warranties, and weekly status reports. The contractor must provide an onsite representative and ensure key personnel performing heat fusion are certified to ASTM F3190 standards. Access to the campground will be coordinated with the Contracting Officer's Representative (COR).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Walk QandA.pdf | ||
| 12970224Q0034 A0001.pdf | ||
| Rescheduling of Site Visit.pdf | ||
| 12970224Q0034.pdf | ||
| QL Design_2024.03.04_JZTO_JH.pdf | ||
| 2024.03.07_QL Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Section C: SOW
Contents Project
General Information
Contractor Requirements
1.0 Technical Requirements / Tasks
2.0 Government Furnished
3.0 Deliverables / Schedule
4.0 Contractor’s Key Personnel
5.0 Security Requirements
Attachment
Project
Queen Lily CG Water Distribution Line
General Information
Scope o The goal of this project is to abandon the existing Queen Lily Campground water source and install a new distribution system with all components tied into the existing North Fork Campground Water System. This is to be accomplished by demolishing the existing hydrants and drain infrastructure, filling in existing valve boxes, capping the existing water distribution source, and installing new distribution line infrastructure. It is included as an option item to remove the existing Queen Lily water source above ground distribution lines.
Location o The Queen Lily Campground is located approximately 2.5 miles up Caribou Rd from Highway 70 in
Plumas County, California.
Period of Performance o The work shall commence after the Notice to Proceed (NTP) is issued. The NTP shall be issued within 10 days of the award.
o The period of performance is 125 Calendar days.
o Work shall occur outside of the campground operating season (May-October) unless coordinated and approved prior by COR.
Contractor Requirements
1.0 Technical Requirements / Tasks
The contractor shall furnish all personnel, equipment, tools, materials, supervision, and other items and services necessary to selectively demo the existing Queen Lily Water System and install a new distribution system with hydrants in the campground.
Existing Queen Lily Water System Tasks:
o Cap existing water source pipe at valve box located within the campground.
o Remove valve boxes and fill in with native fill.
o Remove existing drain surfaced drain pipe until it is covered by a minimum of 12” of soil.
o Demo existing hydrants and metal drain infrastructure to 12” below grade and fill with native fill.
o All other existing distribution lines can be abandoned in place.
o Option Item: Remove existing Queen Lily Water system tank and all associated infrastructure from tank to campground valve box including but not limited to: valves, above ground piping and above ground pipe supports.
New Queen Lily Water System Tasks:
o Furnish and install new water distribution system and hydrants and shown in drawing plans. Complete all commissioning activities as described in the specifications.
o Install new PRV inside restroom on existing piping.
All work shall be completed per specification requirements unless otherwise noted.
All work shall be installed to be ABA and FSORAG compliant.
2.0 Government Coordination
Protection of Existing Facilities o Contractor shall be responsible for protecting surrounding structures and landscaping from damage during the duration of the project. If damage occurs to government owned infrastructure and landscaping, the contractor will be responsible for all costs to fix.
Water and power will not be available at the campground for the Contractor’s use. Contractor is responsible to provide their own trash containers and restroom/handwashing facilities for employees.
Work shall be scheduled to avoid periods with forecasted precipitation in excess of 1/2”.
Camping may be permitted by contractor in the Queen Lily Campground only with COR approval. Please provide request for camping in project bid proposal.
3.0 Deliverables / Schedule
Tasks and Associated Deliverables: Timely submission of deliverables is essential to successful completion this project.
Schedules for deliverables are specified in Table 1 and project specifications.
Table 1: Key Deliverables
Item No. Deliverable Objective Due 1 Proposed Schedule Demonstrate project timeline to Government At time of bid submission 2 Proposed Project Plan
(shall be included in all proposals) & Product Data Sheets
Define the responsibilities, timeline, milestones of contract objectives and proposed material for the project
No later than ten (10) business days after contract award
3 Warranties and Maintenance/Operation Manuals
Document required paperwork to the Government No later than five (5) business days after field work completion
4 Weekly Status Report Report documenting tasks & issues weekly. Must include photos
Weekly, every Friday, by 1700 PST until the contract expires
4.0 Contractor’s Key Personnel
The Contractor shall provide an onsite contract representative who will oversee the performance of the work specified in this contract no later than five (5) business days after contract award. Designate in writing to CO, the name of the contract representative and an alternate who shall have the authority to act for the Contractor on all contract matters relating to daily operation of this contract. The CO/COR shall be notified at least 10 working days in advance of any subsequent personnel changes. Replacement personnel shall have the same level or better experience as the person being replaced.
Contractor’s key personnel performing heat fusion shall be certified to meet ASTM F3190 standards.
5.0 Security Requirements
The Queen Lily Campground has an entrance and exit gate. Access through these gates shall be coordinated with the COR prior to onsite activities starting.
Attachment
Attachment A – Queen Lily Water System Drawings
Attachment B – Queen Lily Water System Project Specifications
File details come from the government source that posted it. Updated .