2024.03.07_QL Specs.pdf

PDF 204 KB Posted

Attached to
QL Water Line Federal contract opportunity
Solicitation number
12970224Q0034
Issued by
Department of Agriculture Forest Service

About this file

This document is a set of technical specifications for the demolition and installation of a new water distribution system as part of a federal contract opportunity. The key details are:

The project involves abandoning the existing Queen Lily Campground water source and installing a new distribution system that ties into the North Fork Campground Water System. This will require demolishing existing hydrants and drain infrastructure, filling in valve boxes, capping the existing water distribution source, and installing new distribution line infrastructure. An optional item is to remove the existing Queen Lily water source above ground distribution lines. The solicitation number is 12970224Q0034 and it is being issued by the Department of Agriculture Forest Service. The document provides detailed technical specifications for the various construction activities, materials, installation requirements, testing, and project closeout procedures.

View the file

Other files for this federal contract opportunity

Other files attached to QL Water Line, newest first.
File Type Posted
Site Walk QandA.pdf PDF
12970224Q0034 A0001.pdf PDF
Rescheduling of Site Visit.pdf PDF
12970224Q0034.pdf PDF
QL Design_2024.03.04_JZTO_JH.pdf PDF
QL Water Line SOW.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Document Generated by MasterWorks: March 07, 2024

SECTION 024119 - SELECTIVE DEMOLITION

SECTION 312000 - EARTH MOVING

SECTION 321216 - ASPHALT PAVING

SECTION 331415 - SITE WATER DISTRIBUTION PIPING

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. The Work of this Section Includes:

1. Demolition and removal of selected portions of existing North Fork Water System.

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

1.3 CLOSEOUT SUBMITTALS

A. Inventory: Submit a list of items that have been removed in a daily report.

1.4 FIELD CONDITIONS

A. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.

B. Notify Owner of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

C. On-site sale of removed items or materials is not permitted.

PART 2 - EXECUTION

2.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs or video.

2.2 PREPARATION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent facilities to remain.

2.3 UTILITY SERVICES AND BUILDING SYSTEMS

A. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utilities and building systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated utilities when requested by Contractor.

2. Demolish and remove existing building systems, equipment, and components indicated on

Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material. Existing hydrants and associated drain infrastructure shall be removed to 12” below grade and filled in with native fill. Existing system drain pipe and valve boxes shall be removed and filled in with native fill.

3. Abandon existing building systems, equipment, and components indicated on Drawings to be abandoned in place.

a. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

2.4 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site and dispose of them via an approved method by authorities having jurisdiction.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

END OF SECTION 024119

SECTION 312000 - EARTH MOVING

TIPS:

To view non-printing Editor's Notes that provide guidance for editing, click on MasterWorks/Single-File

Formatting/Toggle/Editor's Notes.

To read detailed research, technical information about products and materials, and coordination checklists, click on MasterWorks/Supporting Information.

Content Requests:

<Double click here to submit questions, comments, or suggested edits to this Section.>

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Subbase course for asphalt paving.

2. Excavating and backfilling trenches for utilities and pits for buried utility structures.

1.2 DEFINITIONS

A. Backfill: Soil material used to fill an excavation.

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

2. Final Backfill: Backfill placed over initial backfill to fill a trench.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

C. Bedding Course: Aggregate layer placed over the excavated subgrade in a trench before laying pipe.

D. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.

E. Drainage Course: Aggregate layer at base of campground hydrant sump.

F. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.

1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Architect. Authorized additional excavation http://user.avitru.com/ContentContact.aspx?sect=312000&ver=06-01-21&format=SF&sid=16029&utm_source=MasterSpec&utm_medium=Word and replacement material will be paid for according to Contract provisions for changes in the Work.

2. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Architect. Unauthorized excavation, as well as remedial work directed by Architect, will be without additional compensation.

G. Fill: Soil materials used to raise existing grades.

H. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other fabricated stationary features constructed above or below the ground surface.

I. Subbase Course: Aggregate layer placed between the subgrade and base course for hot-mix asphalt pavement, or aggregate layer placed between the subgrade and a cement concrete pavement or a cement concrete or hot-mix asphalt walk.

J. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase, drainage fill, drainage course, or topsoil materials.

K. Utilities: On-site underground pipes, conduits, ducts, and cables as well as underground services within buildings.

1.3 INFORMATIONAL SUBMITTALS

A. Material test reports.

1.4 FIELD CONDITIONS

A. Utility Locator Service: Notify utility locator service for area where Project is located before beginning earth-moving operations.

PART 2 - PRODUCTS

2.1 SOIL MATERIALS

A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.

B. Satisfactory Soils: Soil Classification Groups GW, GP, GM, SW, SP, and SM according to

ASTM D2487, or a combination of these groups; free of rock or gravel larger than 2 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.

C. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 90 percent passing a 1-

1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.

D. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 90 percent passing a 3/4-inch sieve and not more than 8 percent passing a No. 200 sieve.

E. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with 100 percent passing a No. 4 sieve and not more than 12 percent passing a No. 200 sieve.

F. Drainage Course: Narrowly graded mixture of washed or crushed stone, or crushed or uncrushed gravel; ASTM D448; coarse-aggregate grading Size 57; with 100 percent passing a 1/2-inch sieve and zero to 5 percent passing a No. 8 sieve.

2.2 ACCESSORIES

A. Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, 1-1/2” inches wide minimum, continuously inscribed with a description of the utility; colored to comply with local practice or requirements of authorities having jurisdiction.

B. Detectable Warning Wire: Provide a continuous bare copper or aluminum tracer wire not less than 0.10 inch in diameter in sufficient length over each separate run of nonmetallic pipe. Wire shall be easily detectable at the top of all valve box lids.

PART 3 - EXECUTION

3.1 PREPARATION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth-moving operations.

B. Protect and maintain erosion and sedimentation controls during earth-moving operations.

C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials.

3.2 EXCAVATION, GENERAL

A. Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.

1. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with satisfactory soil materials.

3.3 EXCAVATION FOR UTILITY TRENCHES

A. Excavate trenches to indicated gradients, lines, depths, and elevations.

B. Excavate trenches to uniform widths to provide the following clearance on each side of pipe or conduit. Excavate trench walls vertically from trench bottom to 12 inches higher than top of pipe or conduit unless otherwise indicated.

1. Clearance: 6 inches each side of pipe minimum.

C. Trench Bottoms: Excavate and shape trench bottoms to provide uniform bearing and support of pipes and conduit. Shape subgrade to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits. Remove projecting stones and sharp objects along trench subgrade.

1. Excavate trenches 6 inches deeper than elevation required in rock or other unyielding bearing material to allow for bedding course.

D. Trenches in Tree- and Plant-Protection Zones:

1. Hand-excavate to indicated lines, cross sections, elevations, and subgrades. Use narrow-tine spading forks to comb soil and expose roots. Do not break, tear, or chop exposed roots.

Do not use mechanical equipment that rips, tears, or pulls roots.

2. Do not cut main lateral roots or taproots; cut only smaller roots that interfere with installation of utilities.

3.4 STORAGE OF SOIL MATERIALS

A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing.

Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.

3.5 BACKFILL

A. Place and compact backfill in excavations promptly, but not before completing the following:

1. Construction below finish grade.

2. Surveying locations of underground utilities for Record Documents.

3. Testing and inspecting underground utilities.

4. Removing trash and debris.

5. Removing temporary shoring, bracing, and sheeting.

B. Place backfill on subgrades free of mud, frost, snow, or ice.

3.6 UTILITY TRENCH BACKFILL

A. Place backfill on subgrades free of mud, frost, snow, or ice.

B. Place and compact bedding course on trench bottoms and where indicated. Shape bedding course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits.

C. Initial Backfill: Place and compact initial backfill of subbase material to a height of 12 inches over the pipe or conduit.

1. Carefully compact initial subbase backfill under pipe haunches and compact evenly up on both sides and along the full length of piping or conduit to avoid damage or displacement of piping or conduit. Coordinate backfilling with utilities testing.

D. Final Backfill: Place and compact final backfill of satisfactory soil to final subgrade elevation.

E. Warning Tape: Install warning tape directly above utilities, 12 inches below finished grade, except 6 inches below subgrade under pavements and slabs.

3.7 SOIL FILL

A. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material.

B. Place and compact fill material in layers to required elevations as follows:

1. Under grass and planted areas, use satisfactory soil material.

2. Under walks and pavements, use satisfactory soil material.

3.8 SOIL MOISTURE CONTROL

A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before compaction to within 2 percent of optimum moisture content.

1. Do not place backfill or fill soil material on surfaces that are muddy, frozen, or contain frost or ice.

2. Remove and replace, or scarify and air dry, otherwise satisfactory soil material that exceeds optimum moisture content by 2 percent and is too wet to compact to specified dry unit weight.

3.9 COMPACTION OF SOIL BACKFILLS AND FILLS

A. Place backfill and fill soil materials in layers not more than 10 inches in loose depth for material compacted by heavy compaction equipment and not more than 4 inches in loose depth for material compacted by hand-operated tampers.

B. Place backfill and fill soil materials evenly on all sides of structures to required elevations and uniformly along the full length of each structure.

3.10 GRADING

A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.

B. Site Rough Grading: Slope grades to direct water away from buildings and to prevent ponding.

Finish subgrades to elevations required to achieve indicated finish elevations, within the following subgrade tolerances:

3.11 SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS

A. Place subbase course and base course on subgrades free of mud, frost, snow, or ice.

B. On prepared subgrade, place subbase course and base course under pavements and walks as follows:

1. Shape subbase course and base course to required crown elevations and cross-slope grades.

3.12 PROTECTION

A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.

B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.

C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.

1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.

3.13 DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Remove surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and debris, and legally dispose of them off Owner's property.

END OF SECTION 312000

SECTION 321216 - ASPHALT PAVING

1.1 SUMMARY

A. Section Includes:

1. Hot-mix & Cold Mix asphalt patching.

B. Related Requirements:

1. Section 312000 "Earth Moving" for subgrade preparation, fill material, separation geotextiles, unbound-aggregate subbase and base courses, and aggregate pavement shoulders.

1.2 ACTION SUBMITTALS

A. Product Data

1.3 INFORMATIONAL SUBMITTALS

A. Material Certificates:

1. Aggregates.

2. Asphalt binder.

3. Tack coat.

1.4 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with materials, workmanship, and other applicable requirements of CalTrans for asphalt paving work.

PART 2 - PRODUCTS

2.1 AGGREGATES

A. Coarse Aggregate: ASTM D692/D692M, sound; angular crushed stone, crushed gravel, or cured, crushed blast-furnace slag.

B. Fine Aggregate: AASHTO M 29, sharp-edged natural sand or sand prepared from stone, gravel, cured blast-furnace slag, or combinations thereof.

C. Mineral Filler: AASHTO M 17, rock or slag dust, hydraulic cement, or other inert material.

2.2 ASPHALT MATERIALS

A. Asphalt Binder: AASHTO M 320 binder designation PG 58-22.

B. Asphalt Cement: ASTM D3381/D3381M for viscosity-graded material.

C. Tack Coat: AASHTO M 140 emulsified asphalt, or AASHTO M 208 cationic emulsified asphalt, slow setting, diluted in water, of suitable grade and consistency for application.

D. Cold Patch: COR approval required.

2.3 MIXES

A. Hot-Mix Asphalt: Dense-graded, hot-laid, hot-mix asphalt plant mixes approved by authorities having jurisdiction and complying with the following requirements:

1. Provide mixes with a history of satisfactory performance in geographical area where

Project is located.

PART 3 - EXECUTION

3.1 PATCHING

A. Asphalt Pavement: Saw cut perimeter of patch and excavate existing pavement section to sound base. Excavate rectangular or trapezoidal patches, extending 12 inches into perimeter of adjacent sound pavement, unless otherwise indicated. Cut excavation faces vertically. Remove excavated material. Recompact existing unbound-aggregate base course to form new subgrade.

B. Tack Coat for hot-mix only: Before placing patch material, apply tack coat uniformly to vertical asphalt surfaces abutting the patch. Apply at a rate of 0.05 to 0.15 gal./sq. yd..

1. Allow tack coat to cure undisturbed before applying hot-mix asphalt paving.

2. Avoid smearing or staining adjoining surfaces, appurtenances, and surroundings. Remove spillages and clean affected surfaces.

C. Placing Patch Material: Hot Mix- Fill excavated pavement areas with hot-mix asphalt base mix for full thickness of patch and, while still hot, compact flush with adjacent surface. Cold Patch –

Place material in 1” lifts and adequately compact. Compact final layer to be flush with adjacent surface.

3.2 FIELD QUALITY CONTROL

A. Replace and compact hot-mix asphalt where core tests were taken.

B. Remove and replace or install additional hot-mix asphalt where test results or measurements indicate that it does not comply with specified requirements.

3.3 WASTE HANDLING

A. General: Handle asphalt-paving waste in accordance with approved waste management plan required

END OF SECTION 321216

SECTION 331415 - SITE WATER DISTRIBUTION PIPING

1.1 SUMMARY

A. Section Includes:

1. Water-distribution piping and related components for domestic water service lines.

B. Related Requirements:

1. Section 312000 "Earth Moving"

2. Section 321216 "Asphalt Paving"

1.2 ACTION SUBMITTALS

A. Product Data.

B. Shop Drawings:

1. Detail precast concrete vault assemblies and indicate dimensions, method of field assembly, and components.

1.3 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: For piping and specialties including relation to other services in same area, drawn to scale. Show piping and specialty sizes and valves, meter and specialty locations, and elevations.

B. Field Quality-Control Submittals:

1. Field quality-control reports.

1.4 CLOSEOUT SUBMITTALS

A. Operation and maintenance data.

1.5 PROJECT CONDITIONS

A. Interruption of Existing Water-Distribution Service: Do not interrupt service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary water-distribution service in accordance with requirements indicated:

1. Notify Owner no fewer than 10 days in advance of proposed interruption of service.

2. Do not proceed with interruption of water-distribution service without Owner's written permission.

1.6 COORDINATION

A. Coordinate connection to existing North Fork water main with Owner.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Comply with standards of authorities having jurisdiction (Government) for domestic water-service piping, including materials, installation, testing, and disinfection.

B. Piping materials to bear label, stamp, or other markings of specified testing agency.

C. Comply with ASTM F645 for selection, design, and installation of thermoplastic water piping.

D. All piping and appurtenances intended to convey or dispense water for human consumption are to comply with the U.S. Safe Drinking Water Act (SDWA), with requirements of the Authority

Having Jurisdiction (AHJ), and with NSF 61/NSF 372 or are certified in compliance with

NSF 61/NSF 372 by an ANSI-accredited third-party certification body, that the weighted average lead content at wetted surfaces is less than or equal to 0.25 percent.

2.2 PIPING MATERIALS

A. Comply with requirements in section 3.2 "Piping Applications" Article for applications of pipe, tube, fitting materials, and joining methods for specific services, service locations, and service sizes.

B. Potable-water piping and components comply with NSF 14, NSF 61, and NSF 372.

2.3 PIPING JOINING MATERIALS

A. Piping shall be typically joined by thermos-fusing or as otherwise specifically authorized by the

Contracting Officer.

B. Plastic Pipe-Flange Gasket, Bolts, and Nuts: Type and material recommended by piping system manufacturer unless otherwise indicated.

2.4 PIPING SPECIALTIES

A. Transition Fittings: Manufactured fitting or coupling same size as, with pressure rating at least equal to and ends compatible with, piping to be joined.

2.5 GATE VALVES

A. Valves shall be a type and material recommended by piping system manufacturer unless otherwise indicated and compatible with adjoining pipe material.

2.6 CONCRETE VAULTS

A. Concrete Vault - Precast, Reinforced Concrete: Designed for A-8 load designation in accordance with ASTM C857 and made in accordance with ASTM C858.

a. ASTM A536, Grade 60-40-18, ductile-iron traffic frame and cover.

1) Dimension: 24-inch minimum diameter unless otherwise indicated.

PART 3 - EXECUTION

3.1 EARTHWORK

A. Comply with excavating, trenching, and backfilling requirements in Section 312000 "Earth

Moving."

3.2 PIPING APPLICATIONS

A. Transition couplings with pressure ratings at least equal to piping pressure rating may be used unless otherwise indicated.

B. Do not use flanges or unions for underground piping.

C. Flanges, unions, and grooved-end-pipe couplings may be used, instead of joints indicated, on aboveground piping and piping in vaults.

D. Underground water-service piping to be the following:

1. HDPE Pipe: PE 3408 SDR 11 or PE 4710 SDR 13.5 with a pressure rating of 100psi min.

3.3 VALVE APPLICATIONS

A. General Application: Use mechanical-joint-end valves for NPS 3 and larger underground installation. Use threaded- or flanged-end valves for installation in vaults. Use UL/FM Global, nonrising-stem gate valves for installation with indicator posts. Use corporation valves and curb valves with ends compatible with piping, for NPS 2 and smaller installation.

B. Drawings indicate valve types to be used.

3.4 PIPING SYSTEMS - COMMON REQUIREMENTS

A. Provide a continuous bare copper or aluminum tracer wire not less than 0.10 inch in diameter in sufficient length over each separate run of nonmetallic pipe.

3.5 INSTALLATION OF PIPING

A. Bury piping with depth of cover over top at least 30 inches, with top at least 12 inches below level of maximum frost penetration, and according to the following:

B. Install piping by tunneling or jacking, or combination of both, under streets and other obstructions that cannot be disturbed.

C. Extend water-service piping and connect to water-supply source and building water-piping systems at outside face of building wall in locations and pipe sizes indicated.

D. Install underground piping with restrained joints at horizontal and vertical changes in direction.

Use restrained-joint piping, thrust blocks, anchors, tie-rods and clamps, and other supports.

3.6 JOINT CONSTRUCTION

A. Make pipe joints according to the following:

1. Butt fused, flanged or Electrofusion (COR approval required)

2. All joints shall be made according to manufacturer recommendations and ASTM standards for material used.

B. All personnel performing thermal-fusing shall be certified to meet ASTM F3190 standards.

3.7 INSTALLATION OF VALVES

A. AWWA Gate Valves: Comply with AWWA C906 and AWWA M55. Install each underground valve with stem pointing up and with valve box.

3.8 INSTALLATION OF CONCRETE VAULTS

A. Install precast concrete vaults in accordance with ASTM C891.

3.9 CONNECTIONS

A. Connect water-distribution piping to existing water main connection. Use a flanged fitting to connect to existing valve.

B. Connect water-distribution piping to interior domestic water piping.

3.10 FIELD QUALITY CONTROL

A. Piping Tests: Conduct piping tests before joints are covered and after concrete thrust blocks have hardened sufficiently. Fill pipeline 24 hours before testing and apply test pressure to stabilize system. Use only potable water.

B. Hydrostatic Tests: Test at not less than one-and-one-half times working pressure for two hours.

1. Increase pressure in 50 psig increments and inspect each joint between increments. Hold at test pressure for one hour; decrease to 0 psig. Slowly increase again to test pressure and hold for one more hour. Maximum allowable leakage is 2 quarts per hour per 100 joints.

Remake leaking joints with new materials and repeat test until leakage is within allowed limits.

C. Prepare reports of testing activities.

3.11 IDENTIFICATION

A. Install continuous underground warning tape and detectable trace wire during backfilling of trench for underground water-distribution piping. Locate below finished grade, directly over piping. Underground warning tapes are specified in Section 312000 "Earth Moving."

3.12 CLEANING

A. Clean and disinfect water-distribution piping as follows:

1. Use purging and disinfecting procedure prescribed by authorities having jurisdiction or, if method is not prescribed by authorities having jurisdiction, use procedure described in

AWWA C651 or do as follows:

a. Fill system or part of system with water/chlorine solution containing at least 50 ppm of chlorine; isolate and allow to stand for 24 hours.

b. After standing time, flush system with clean, potable water until no chlorine remains in water coming from system.

c. Submit water samples in sterile bottles to authorities having jurisdiction. Repeat procedure if biological examination shows evidence of contamination.

B. Prepare reports of purging and disinfecting activities.

END OF SECTION 331415