Center Administrative & Technical Support Services (CATSS) Quality Assurance Surveillance Plan (QASP)
FOR INFORMATIONAL PURPOSES ONLY
CENTER ADMINISTRATIVE & TECHNICAL SUPPORT SERVICES
(CATSS)
Solicitation No. 80AFRC22R0002
QUALITY ASSURANCE SURVEILLANCE PLAN
(QASP)
October 7, 2022
Neil A. Armstrong Flight Research Center (AFRC) Edwards, California 93523
CENTER ADMINISTRATIVE & TECHNICAL SUPPORT SERVICES (CATSS)
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
(QASP)
1 INTRODUCTION
This Government Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the Performance Work Statement (PWS) entitled Center Administrative and Technical Support Services (CATSS). This plan sets forth the procedures and guidelines NASA Armstrong Flight Research Center (AFRC) and NASA Ames Research Center (ARC) will use in ensuring the required performance standards or services levels of work performed under this contract are achieved by the CATSS Contractor.
This plan is applicable to all services performed by the CATSS Contractor(s). Throughout this QASP, the term CATSS Contractor is used. In terms of this plan, it should be known that unless explicitly stated, this term is applicable to both the CATSS Contractor and all subcontractors.
Under fixed price contracts, the contractor assumes more responsibility and greater risk in exchange for more flexibility and less direct Government involvement in contract activities.
However, the Government still has a responsibility to monitor the contractor’s performance over the course of the contract to ensure its acceptability. To meet this responsibility, the Government needs sufficient information on contractor performance to be assured contract requirements are being satisfied.
The QASP is a Government-developed surveillance tool prepared in accordance with FAR
46.601 and NFS 1846.401. It is not part of the contract, per NFS 1846.401, but provided to the Contractor for informational purposes only.
1.1 Purpose
The purpose of the QASP is to provide an effective surveillance method of monitoring contractor performance in accordance with the PWS. The QASP provides a systematic method to evaluate the services the Contractor is required to furnish. The Contractor, and not the Government, is responsible for management and quality control actions to meet the terms of the contract.
This QASP defines the roles and responsibilities of all members of the surveillance team, defines the process the Government expects to follow to obtain data, evaluate the Contractor, and determine if Contractor’s performance conforms to the contract requirements.
The QASP is intended to be a “living” document from which resources and activities will evolve during the life of the contract, and can be updated and changed unilaterally by the Government at any time during the contract.
1.2 Contract Goals and Objectives:
This requirement is an Indefinite Delivery Indefinite Quantity (IDIQ) contract, with firm-fixed price task orders issued for the required services. The Contractor’s primary requirement under this contract is to provide high quality administrative and technical support services to AFRC and ARC. The specific services covered are Technical Publications, Research Library, Strategic Communications, Archiving, Reproduction, General Administrative Support, and Business Systems Support.
2 FORMS OF SURVEILLANCE
Surveillance Strategy Definitions
Insight
Insight is an assurance process that uses performance requirements and performance metrics to ensure process capability, and quality of deliverables. Insight relies on gathering a minimum set of deliverable or process data that provides adequate visibility into the integrity of the deliverable or process. The data may be acquired from Contractor records or report deliverables, usually in a non-intrusive parallel method.
Insight as applied to this contract will result in lower levels of Government surveillance and allow the Contractor to assume increased responsibility and accountability for the integrity of processes. Insight will rely heavily on evaluating planned contract deliverables, performance standards, and existing Contractor procedures and working documents. The Government’s goal is to follow an insight-driven surveillance strategy
Oversight
Oversight results in higher levels of Government surveillance. The Government gathers information pertaining to the Contractor's process through involvement and/or inspection in the process and monitors the process itself.
Oversight is an assurance process that uses customer-imposed specification and process controls, such as performance specifications and mandatory inspections, to direct the development and production of the deliverable. Oversight entails very detailed monitoring of the process itself.
Oversight is an in-line involvement in an activity, principally through inspection, with review and approval authority implicit to the degree necessary to assure that a process or deliverable’s key characteristics are stable and in control. The Government's involvement in the Contractor's performance, through oversight, will be determined necessary by the Contracting Officer's Representative.
AFRC and ARC will strive to use an insight-driven surveillance approach through the performance period of the CATSS contract. However, the Government reserves the right to use am oversight approach to monitor questionable areas or areas of poor contract performance.
3 ROLES AND RESPONSIBILITIES
General organization and responsibilities of the Surveillance Team are as follows:
3.1 General
The activities detailed in this plan will be supported and performed by a group of individuals, many with differing levels of responsibilities, but all maintaining a level of consistency in terms of the surveillance strategy, approach, and activities in general. The specific entities and their associated responsibilities/input to the surveillance activities on the contract are described in the following paragraphs.
3.2 Surveillance Team
3.2.1 Contracting Officer/Contract Specialist
The NASA ARC and AFRC Contracting Officers (CO) and/or Contract Specialists (CS) are responsible for monitoring contract compliance, contract administration, and for resolving any differences between the observations documented by the NASA Contracting Officer's Representative (COR) and the Contractor. The CO will designate one full-time COR at each center as the Government authority for performance management. The number of additional representatives serving as Task Monitors (TMs) depends on the number and complexity of the services, as well as the Contractor’s performance, and must be identified and designated by the
COR.
As required by FAR 42.1502(b), the CO will complete an annual Contractor performance assessment report for work performed under this contract using the Contractor Performance Assessment Reporting System (CPARS) evaluation, which will also be reviewed by the Contractor.
3.2.2 Contracting Officer’s Representatives
The NASA COR is designated in writing by the NASA CO to act as his or her authorized representative to assist in administering the contract. The COR’s limitations of authority are contained in the NASA Form 1634, COR Delegation. The COR is responsible for technical administration of the project and ensures proper Government surveillance of the Contractor’s performance. The COR is not empowered to make any contractual commitments, authorize any contractual changes on the Government’s behalf, or in any way direct the Contractor to operate in conflict with the contract. Any changes that the Contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR will have the responsibility for monitoring, inspecting, and evaluating the Contractor’s work performance. Government surveillance may occur under the inspection of services clause for any services provided under this contract.
The COR will assist the CO in the completion of the annual performance assessment report for work performed under this CONTRACT using CPARS.
3.2.3 Task Monitors
The NASA Task Monitors (TMs) are individuals appointed by the COR for the surveillance of specific areas under the contract. TMs provide detailed technical surveillance of the Contractor’s performance and report findings to the COR in a timely, complete and impartial fashion. While the TMs may serve as a direct conduit to provide Government guidance and feedback to the Contractor on technical matters, the TMs are not empowered to make any contractual commitments, authorize any contractual changes on the Government’s behalf, or in any way direct the Contractor to operate in conflict with the contract.
3.2.4 Other Surveillance Team Support
Other Government personnel such as the ARC and AFRC Safety and Mission Assurance Offices, Defense Contract Audit Agency (DCAA), Defense Contract Management Agency (DCMA), and local contract support personnel, as required may assist in surveillance activities.
4 METHODOLOGIES TO MONITOR PERFORMANCE
4.1 Surveillance Techniques
In an effort to minimize the performance management burden, simplified surveillance methods will be applied to the insight areas described in Section 5 of this document to evaluate Contractor performance to determine whether the performance standards/service levels required have been met. The primary methods of surveillance are described below.
4.1.1 Communications
Communications is a general surveillance activity. Communications is a two-way process and includes both written and oral communication. Examples of written communications activities that may be used in conducting surveillance include:
a. Exchanges from the CATSS Contractor to the Government of plans, procedures, quality records, reports, etc., and/or provision of read-only access to repositories which retain these items.
b. Exchanges from the Government to CATSS Contractor of letters, reports, review results, etc.
c. Ad hoc information submitted by NASA COR and/or TM(s) to the CO related to the CATSS Contractor’s electronic mail.
Examples of oral communications activities that may be used in conducting surveillance include:
a. Informal telephone calls, teleconferences.
b. Informal verbal inquiries, discussions.
c. Working group meetings, technical/status briefings, progress reviews, technical information meetings, and formal and informal reviews.
d. Informal discussions.
4.1.2 Management Reviews and Reporting
Examples of management review and reporting activities that may be used in conducting surveillance include:
a. Formal, process, and progress reviews
b. Review of contract deliverables (e.g., Monthly Reports) and documentation
c. Documentation of problems, issues and concerns
d. Data collection reporting
4.1.3 Customer Feedback
The Contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction.
Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.
Performance management drives the Contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems but the customer always has the option to communicate complaints to the CO or COR, as opposed to the Contractor.
Customer complaints, to be considered valid, must set forth clearly and in writing the detailed nature of the complaint, must be signed, and must be forwarded to the COR. The COR will accept those customer complaints, perform an investigation, and notify the CO and Contractor, accordingly. Customer feedback may also be obtained either from the results of formal customer satisfaction surveys or from random customer complaints and feedback.
5. SURVEILLANCE ACTIVITIES
5.1 General
There exist specific insight areas that the Government and the CATSS Contractor shall concentrate on during applicable stages of work being performed. Each of these insight areas and the Government’s expectations for these areas are described in Table 1.
Table 1. Surveillance Insight Areas
Area of Risk Identified Impact to Government Surveillance Team Activity Information Technology (IT) Security
Computer Security: Potential corruption and loss of data;
disruption of schedule
Review of IT security plans and contingency test results and controls.
Review compliance with policies, firewalls, protection software, vulnerability scans and external systems.
Property Management, Control, and Maintenance
Loss of or damage to equipment;
potential schedule impact
Review Contractor property management techniques, compliance with policies, and record-keeping.
Safety Loss of work-time or equipment, with schedule impact
Evaluate compliance with the Contractor's Safety, Health and Environmental Management Plan (SHEMP) and safety requirements.
Continuous Risk Management Technical, schedule, safety, and program success
Periodically ensure that the Contractor is performing a Continuous Risk Management program that identifies, analyzes, tracks, mitigates, controls and reports on related risks.
Quality Management Technical, schedule, safety, and program success
Monitor the Contractor’s internal and external audits for compliance with the Contractor’s established QCP.
Organizational Conflicts of Interest (OCI) Avoidance
Potential restrictions, ineligible to perform, and/or unfair competitive advantage on future work
Monitor submittal, enforcement and compliance with Contractor OCI Avoidance Plan.
5.2 Surveillance Team Activities
The surveillance team members will participate in review meetings. They will provide support, as necessary, with the review of technical requirements, and flow-down of requirements. They will also maintain insight into the Contractor’s compliance with relevant deliverables submitted under the contract and services performed. When the Government has concerns regarding Contractor performance, surveillance team members may conduct independent audits of the Contractor’s activities, processes, documentation, and data in order to provide assurance that the program is being implemented according to all requirements and performance standards. These audits will normally be conducted with advance notification and coordinated with the Contractor.
However, the Government reserves the right to conduct unscheduled audits when evidence indicates that Contractor performance is deficient.
The following selected surveillance team activities will be performed by various surveillance team members during applicable stages of work being performed (as provided in Table 2):
Table 2: Surveillance Performance Requirement Summary:
Performance Work Statement Paragraph
Performance Standards Performance Requirement
Section 4.1 Technical Publications Office
Perform technical editing and related assistance such as formatting to pertinent Scientific Technical Information (STI) and other applicable specifications.
Accuracy: Contractor shall inspect published products prior to release to customer. No more than one error per month. No more than 3 pieces of correspondence returned for errors each month.
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Required communication material review approvals shall be submitted to or approved by the Contract Manuscript Review process before completed work is sent for reproduction or released to the customer.
Accuracy: Contractor shall ensure material review approvals are performed prior to reproduction or distribution. No more than one missed review approval per quarter.
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Section 4.2 Research Library
Identify information resources that support research in science and technology information and deliver those resources to all ARC & AFRC personnel.
Accuracy: Contractor shall ensure all customer requirements are met and there is no more than one customer complaint per month.
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Performance Work Statement Paragraph
Performance Standards Performance Requirement
Section 4.3 Reproduction Services (AFRC only)
Provide duplicating and printing support and safeguard all sensitive, classified or proprietary material.
Accuracy: Duplicating and printing support shall be provided without errors and handling of classified or proprietary material shall be 98% compliant with Agency, AFRC, Government Printing Office (GPO) and other government policies and procedures.
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Section 4.4 Office of Strategic Communications (AFRC only)
Performance Measures will be identified by the nature of the deliverable, conformance of deliverable to requirements, and scheduled delivery dates.
Contractor shall ensure all customer requirements are met and there is no more than one missed report/action per month
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Section 4.5 Office of Internal Controls and Management Support
Performance Measures will be identified by the nature of the deliverable, conformance of deliverable to requirements, and scheduled delivery dates.
Accuracy: Final products shall be free of any errors.
Contractor shall ensure all customer requirements are met and there is no more than one customer complaint per month
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Section 4.6 Administrative Support Services
Prepare various office correspondence;
perform data processing and other administrative functions.
Accuracy: Final products shall be free of any errors.
No more than 3 pieces of correspondence returned for errors each month. No errors in scheduling appointments.
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Section 4.6 Administrative Support Services Business System Support
Prepare documentation or presentation material, participate in meetings, etc., Accuracy: Information shall be clearly articulated.
Not more than one report/presentation returned for errors per month.
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline.
Section 4.7 Archiving Support Services
Identify and sort formal records from informal records and from non-records.
Contractor shall ensure all customer requirements are met and there is no more than one missed report/action per month
Timeliness: All established deadlines are met 98% of the time. Projected delays are renegotiated with the requiring organization prior to the original deadline
5.2.1 Work Area/Floor Checks
The surveillance team members will make a physical inspection of the Contractor's onsite work semi-annually. In addition, the COR may make informal inspections, as required. These inspections are made to assure compliance with NASA regulations regarding:
a. All Contractor employees have a NASA identification badge.
b. The total number of Contractor employees provided onsite office space.
c. The Contractor knows who the building's Facilities Operation Manager (FOM) is, and what his/her functions are.
d. The Contractor is familiar with the building emergency evacuation procedures.
e. The Contractor employees are aware that work area checks may be conducted at any time.
f. The Contractor is familiar with NASA and AFRC and ARC Policy Directives and Procedural Requirements as it pertains to ANSI/ISO/ASQ Q9001 or AS 9100 governing onsite performance. These procedures can be accessed via the following NASA Online Directive Information System Website: https://odie.ndc.nasa.gov/SitePages/Home.aspx
g. The Contractor is aware of the appropriate protection procedures for handling Government planning data, private medical information, Controlled Unclassified Information (CUI) data, and other Contractor confidential or financial data.
h. The Contractor employees are aware that the use of Government telephones and computers are for official business only.
i. The Contractor employees are following the proper Checkout Procedures when out processing from NASA (e.g., returning PIV card (badges)).
j. The Contractor employees are aware of the NASA IT Security compliance requirements.
k. The Contractor employees are aware of the Contractor’s Organizational Conflict of Interest
Plan and the have appropriate Non-Disclosures Agreements (NDAs) on file.
In addition to checking conformance with NASA regulations listed above, the COR may make periodic checks of the Contractor's workspace to assess adequacy of facilities, equipment, and materials.
5.2.2 Work Review and Performance Monitoring
The COR, with the assistance of the TMs, will perform the following functions to evaluate the Contractor's performance:
a. Reviews the Contractor's monthly Progress Report for accuracy and completeness.
Consult with TM, as necessary, to assess the fidelity of reports.
b. Meets monthly, or more often if required, with the Contractor's Program Manager/Site
Manager to discuss overall management and performance, and review staffing and schedule issues.
c. Certifies the Contractor’s invoices for payment in accordance with NASA procedures.
d. In the event of a discrepancy in the Contractor's performance, the COR promptly notifies both the CO and the Contractor's Program Manager and arranges a meeting to rectify the situation.
5.2.3 Government Property Administration
The COR will carry out the following functions.
a. Validate that all Installation-Accountable Government Property (IAGP) is being properly utilized and maintained.
b. Conduct periodic inspection of equipment and its location, compared to the data on the property records.
c. Validate that all existing and new equipment is properly tagged.
d. Validate that Government property is made available in accordance with the terms of the contract.
e. Validate that the Contractor does not modify or provide additional facilities, plant equipment, or real property at NASA, except as specifically required by the contract, or as directed or approved in writing by the CO.
5.2.4 Performance Monitoring
The COR will ensure that employer–employee relationships do not occur between Government and Contractor personnel. This is achieved if the following is adhered to:
a. Only the Contractor interviews prospective employees.
b. Only the Contractor’s Program Manager assigns work directly to the employees.
c. Only the Contractor approves timecards and absences.
d. Government personnel do not interfere with the Contractor regarding personnel and administrative activities.
5.2.5 Safety
The responsibility for meeting all safety requirements rests with the Contractor. Surveillance team safety engineers and technical personnel will review Contractor-generated hazard analyses, safety compliance data packages or other safety-related documentation, as appropriate, to help ensure all safety requirements have been satisfied. Surveillance team personnel will also maintain insight into the Contractor’s safety activities through the review of the Contractor’s submitted Safety, Health and Environmental Management Plan (SHEMP), and updates, as required by this contract.
6.0 SUMMARY
This QASP describes the approach ARC and AFRC intends to use to monitor the CATSS contract and assure that the Contractor performs in accordance with the terms and conditions of the contract. NASA anticipates using an insight surveillance approach. The goal is to balance the level of Government surveillance with the perceived impacts and risks of mission failure.
Quality Assurance Office Signature Date
Contracting Officer’s Representative Signature Date
Contracting Officer Signature Date