This is a Quality Assurance Surveillance Plan (QASP) for mortuary services provided to the VA Salt Lake City Health Care System. The QASP establishes the Government's methodology for monitoring contractor performance against the Performance Work Statement (PWS v3) requirements for cremation and burial services for deceased unclaimed or indigent Veterans in Utah. The plan defines roles and responsibilities for the Contracting Officer, Contracting Officer Representative (COR), Technical Subject Matter Experts, and Station Quality Assurance personnel who will oversee contractor compliance.
The QASP outlines six primary surveillance methods: random inspections of mortuary operations, scheduled inspections aligned with service milestones, customer feedback collection, document reviews, onsite facility inspections, and case timeline tracking. Key performance requirements include a 1-business-day response time for remains removal, minimum 14-calendar-day holding periods, 5-business-day burial/inurnment completion following the Proceed Notice, proper refrigeration and storage, appropriate body preparation and embalming when applicable, and secure transportation to Utah Veterans Cemetery & Memorial Park at Camp Williams or other designated Utah cemeteries. All performance requirements mandate 100% compliance with zero violations for confidentiality and privacy handling. The COR conducts pickup timeliness verification at every occurrence, burial/inurnment completion timeline verification at every occurrence, facility inspections as needed, and annual license and permit verification. Documentation is maintained through inspection logs, case timeline logs, deficiency reports, and monthly performance summary reports. When deficiencies occur, the contractor must submit a Corrective Action Plan within a specified timeframe, with COR follow-up verification. The QASP may be updated when the PWS changes, performance issues arise, or new high-risk areas are identified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ Cremation and Burial Services.docx | DOCX document | |
| BPA Terms.docx | DOCX document | |
| Past Performance Questionnaire.docx | DOCX document | |
| VHA Directive 1601B_04_2017-12-01.pdf | ||
| WD 15-5485 Rev 31.pdf | ||
| WD 15-5487 Rev 31.pdf | ||
| WD 15-5495 Rev 30.pdf | ||
| WD 15-6037 Rev 6.pdf | ||
| WD 15-5483 Rev 31.pdf | ||
| WD 15-5491 Rev 30.pdf | ||
| WD 15-5493 Rev 30.pdf | ||
| S02 36C25926Q0820.docx | DOCX document | |
| Performance Work Statement.docx | DOCX document | |
| SURVEILLANCE CHECKLIST.docx | DOCX document | |
| WD 15-5489 Rev 31.pdf | ||
| WD 15-5501 Rev 32.pdf | ||
| VA Handbook 6500_6_March_12_2010.pdf | ||
| SERVICES SUMMARY TABLE.docx | DOCX document | |
| WD 15-5497 Rev 30.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
Mortuary Services for Unclaimed or Indigent Veterans VA Salt Lake City Health Care System (VHSLCHCS)
1.0 Purpose
This Quality Assurance Surveillance Plan (QASP) provides the Government’s methodology for monitoring contractor performance and ensuring all requirements of the Performance Work Statement (PWS) in PWS v3 are met.
It outlines:
· What will be monitored
· How monitoring will occur
· Who will conduct surveillance
· How results will be documented
· Required corrective actions This QASP does not dictate how the Contractor performs the work; the Contractor is responsible for internal quality control, while the Government conducts quality assurance.
2.0 Roles and Responsibilities
Contracting Officer (CO)
· Overall authority for contract administration
· Enforces compliance with contract terms Contracting Officer Representative (COR)
· Primary surveillance official
· Conducts inspections, evaluations, records findings
· Coordinates with technical experts
· Reports deficiencies and recommends corrective actions
Technical Subject Matter Expert (SME)
· Advises COR on mortuary technical standards
· Participates in inspections when needed Station Quality Assurance
· Reviews PWS and QASP compliance
· Supports COR in independent verification activities
3.0 Surveillance Methods
Surveillance will be conducted using one or more of the following methods:
3.1 Random Inspections
Unscheduled checks of mortuary preparation, storage, transport vehicles, and documentation.
3.2 Scheduled Inspections
Periodic inspections aligned with performance events (pick‑up, embalming completion, cremation completion, delivery to cemetery, burial/inurnment completion).
3.3 Customer Feedback
Feedback from VA personnel interacting with contractor services.
3.4 Document Review
Review of logs, licenses, permits, staffing records, quality control records, and contractor submissions (semi‑annual QC reports).
3.5 On‑Site Facility Inspections
Includes inspection of:
· Facility cleanliness, safety, accessibility
· Refrigeration units
· Transport vehicles
· Embalming room compliance
3.6 Case Timeline Tracking
Tracking of the full case lifecycle from notification to burial/inurnment completion, to verify compliance with the 10-calendar-day standard.
4.0 Performance Requirements & Acceptable Quality Levels (AQLs) The following table aligns directly to the PWS requirements in PWS v1.
4.1 Services Summary Table (SST)
| Performance Requirement |
| Standard |
| Surveillance Method |
| AQL |
| Removal of Remains |
| Contractor responds within 1 business day. |
| COR review of notifications, random checks. |
| 100% compliance. |
| Holding Period Compliance |
| Remains held for the full applicable holding period (minimum 14 calendar days, or longer if required by state or local law) from VA notification, absent an early NOK claim requiring different disposition. |
| Case timeline tracking; COR log review. |
| 100% compliance. |
| Burial/Inurnment Completion |
| Full burial or inurnment process completed within 5 business days following receipt of the Proceed Notice, unless otherwise agreed in writing by the COR. |
| Case timeline tracking; COR log review; Proceed Notice issuance log. |
| 100% compliance. |
| Transportation of Remains |
| Proper vehicle; safe, professional handling; timely delivery to cemetery. |
| Scheduled/unscheduled inspections. |
| No deviations permitted. |
| Storage of Remains |
| Refrigeration adequate to preserve remains for the duration of the holding period, any Proceed Notice waiting period, and completion of burial or inurnment; sufficient for volume of cases reasonably anticipated; secure and sanitary storage. |
| Facility inspections. |
| 100% acceptable preservation. |
| Body Preparation |
| Remains prepared and presented per industry standard and applicable state/local law, suitable for positive identification viewing if conducted; refrigerated storage used to preserve remains absent an embalming trigger. |
| Case file review and physical inspection. |
| 100% of cases meet specifications. |
| Embalming (when applicable) |
| When embalming is performed (per known Veteran preference or applicable state/local law), results in uniform preservation, disinfection, and odor elimination; no leakage. |
| Inspection of remains; case file review; verification of embalming trigger (preference or legal requirement). |
| 100% compliance when embalming trigger applies. |
| Cremation Services |
| Durable, sealed, nonleaking urn, labeled and identified on both interior and exterior; complete cremation documentation |
| Documentation review; urn inspection. |
| 100% accuracy. |
| Casketing & Flag Placement |
| Meets size/material requirements (20‑gauge metal or better); proper presentation; U.S. flag properly draped when applicable. |
| Visual inspection. |
| No unacceptable findings. |
| Facility Standards & Licenses |
| All licenses (funeral establishment, embalmers) verified and current for the Contractor and any subcontractor performing work under this contract. |
| Document review; on‑site validation. |
| All required documents current and valid. |
| Quality Control Program (QCP) |
| QCP submitted within 15 days; semi‑annual QC reports provided. |
| Document review. |
| All submissions on time. |
| Confidentiality & Sensitive Information Handling |
| Contractor and subcontractor signs required confidentiality statements; follows VA privacy/security policies; no unauthorized disclosure. |
| Audits; incident reporting review; document review of signed statements. |
| Zero violations. |
5.0 Surveillance Frequency
| Activity |
| Frequency |
| Pick‑up timeliness verification |
| Every occurrence |
| Burial/inurnment completion timeline verification |
| Every occurrence |
| Facility inspection |
| As needed |
| Embalming/preparation inspection |
| Every case prior to release as determined by VA |
| Cremation/urn review |
| Every occurrence includes an urn that is durable, sealed, and non-leaking made of plastic, metal, wood, ceramic/stone, etc. Urns shall be labeled and identified on both the interior and exterior. |
| Casketing & flag placement review |
| Every occurrence involving burial includes a casket with a minimum size and quality requirement of 20-gauge or thicker metal. U.S. flag is draped over the casket for burial services. |
| Transport vehicle inspection |
| As needed |
| License and permit verification |
| Annual |
| Review of Contractor’s QC Program |
| Semi‑annual |
| Sensitive information compliance review |
| Annual or after any incident |
| Confidentiality statement verification |
| Upon contract start; annually thereafter |
6.0 Documentation and Reporting
6.1 Surveillance Records
The COR will maintain:
· Inspection logs
· Case Timeline Logs
· Deficiency reports
· Corrective action requests
· Contractor responses
· Follow‑up verification records
6.2 Monthly Summary
COR compiles monthly performance summary reports for CO review.
6.3 Deficiency Notification
If performance does not meet contract standards:
· COR issues a Contract Discrepancy Report (CDR)
· Contractor provides a Corrective Action Plan (CAP) within specified period
· COR validates the correction
7.0 Corrective Actions
When performance falls below standards:
1. Immediate Notification – COR informs Contractor of deficiency.
2. Corrective Action Plan – Contractor must propose resolution steps and timelines.
3. Follow‑up Surveillance – COR verifies correction and documents results.
4. Escalation – Severe or repeated failures reported to CO for contractual remedies.
8.0 Acceptance Criteria
Performance is considered acceptable when:
· All mandatory PWS requirements are met
· AQL thresholds are achieved
· No serious health, safety, or privacy violations occur
· Contractor fulfills submission of all required deliverables (QCP, permits, reports)
9.0 Updates to the QASP
This QASP may be updated:
· When PWS changes
· When performance issues require new surveillance measures
· When COR or CO identify new high‑risk areas Approval authority includes the Service Chief, Station QA, COR, and CO.