This is a Quality Assurance Surveillance Plan (QASP) document designed to monitor contractor performance on Leadership Development Classes services as outlined in the associated Performance Work Statement (PWS). The QASP establishes a systematic approach to verify the contractor delivers all required services in a timely, accurate, and complete manner through four primary performance elements: Contractor Quality Control Plan compliance, Contract Deliverables submission, Overall Contract Performance, and Invoicing accuracy.
The plan establishes specific surveillance methods and acceptable quality levels for each performance element. The Government, through the Contracting Officer's Representative (COR), will conduct 100 percent inspection of all contract deliverables with an acceptable quality level requiring greater than 95 percent timely submission without rework. Overall contract performance is assessed annually and must achieve a Satisfactory or higher rating. Monthly invoicing must maintain 100 percent accuracy. Contractors failing to meet satisfactory performance standards face Contract Discrepancy Reports (CDRs) requiring written responses within five days, potential contract termination, loss of future Government contracts, and non-exercise of available options. The Government may require contractors to replace or correct deficient work at no additional cost as an incentive mechanism to ensure quality and timely performance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS_2026-2030 DON OGC Training Symposium.docx | DOCX document | |
| Past Performance Information Form.docx | DOCX document | |
| CAP_FFP_.docx | DOCX document | |
| Solicitation - N0018926RD004.pdf | ||
| Minimum Requirements Compliance Chart.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN
Purpose: To ensure that the Government has an effective and systematic method of surveillance for the services in the PWS. The QASP will be used primarily as a tool to verify that the contractor is performing all services required by the PWS in a timely, accurate and complete fashion.
1. Critical performance processes and requirements. Critical to the performance of Leadership Development Classes is the timely, accurate and thorough completion of all contract/task order requirements.
2. Performance Standards
a. Schedule - The due dates for deliverables and the actual accomplishment of the schedule will be assessed against original due dates and milestones established for the contract or task order(s).
b. Deliverables – The deliverables required to be submitted will be assessed against the specifications for the deliverables detailed in the contract/task order(s) and the Quality Control Plan (QCP), if required by the contract, for the required content, quality, timeliness, and accuracy.
c. Past Performance - In addition to any schedule, deliverables, and cost aspects of performance discussed above, pursuant to FAR 42.15, the Government will assess the contractor’s record of conforming to contract requirements and to standards of good workmanship, the contractor’s adherence to contract schedules including the administrative aspects of performance, the contractor’s history of reasonable and cooperative behavior and commitment to customer satisfaction, and the contractor’s business-like concern for the interest of the customer.
3. Surveillance methods: The primary methods of surveillance used to monitor performance of this contract will include, but not be limited to, random or planned sampling, periodic or inspection, and validated customer complaints.
4. Performance Measurement: Performance will be measured in accordance with the following table:
| Performance Element |
| Performance Requirement |
| Surveillance Method |
| Frequency |
| Acceptable Quality Level |
| Contractor Quality Control Plan |
| QC activities, inspections, and corrective actions completed as required by the plan. |
| Inspection by the COR |
| Quarterly for overall QC activities; |
| 100% Compliance with the contractor plan. |
As Required for corrective actions.
(If required by the contract)
| Contract Deliverables |
| Contract deliverables furnished as prescribed in the PWS, attachments, CDRLs, Task Orders, etc., as applicable. |
| Inspection by the COR |
| 100% inspection of all contract deliverables. |
| >95% of deliverables submitted timely and without rework required. |
| Overall Contract Performance |
| Overall contract performance of sufficient quality to earn a Satisfactory (or higher) rating in the COR’s annual report on Contractor Performance |
| Assessment by the COR |
| Annual |
| All performance elements rated Satisfactory (or higher) |
| Invoicing |
| Monthly invoices per contract procedures are timely and accurate. |
| Review & acceptance of the invoice |
| Monthly |
| 100% accuracy |
If performance is within acceptable levels, it will be considered to be satisfactory. If not, overall performance may be considered unsatisfactory.
Incentives/Disincentives:
The COR’s makes an annual report on Contractor Performance (CPARS or other annual report). The contractor’s failure to achieve satisfactory performance under the contract/task order, reflected in the COR’s annual report, may result in termination of the contract/task order and may also result in the loss of future Government contracts/task orders. The contractor’s failure to achieve satisfactory performance under the contract/task order may result in the non-exercise of available options
For each item that does not meet acceptable levels, the Government may issue a Contract Discrepancy Report (CDR). CDRs will be forwarded to the Contracting Officer with a copy sent to the contractor. The contractor must reply in writing within 5 days of receipt identifying how future occurrences of the problem will be prevented. Based upon the contractor’s past performance and plan to solve the problem, the Contracting Officer will determine if any further action will be taken.
In accordance with the inspection of services provisions of the contract, the contractor will be incentivized to provide quality products in a timely manner since the Government can require the Contractor, at no additional cost, to replace or correct work that fails to meet contract requirements.