Q&A Document 1.pdf
PDF 2 KB Posted
- Solicitation number
- RFP-24-20-FM
- Issued by
- Boulder County, Lakewood City, Colorado
About this file
This document is a Questions & Answers (Q&A) file for the City of Lafayette's Police Department VCT Flooring Project (RFP-24-20-FM), involving a request for clarification from LS Contracting LLC regarding the flooring replacement proposal. The Q&A addresses two specific inquiries: the nature of VCT-1 and VCT-2 flooring designations and a request for comprehensive room location information for the flooring replacement project.
The city's response clarifies that VCT-1 & VCT-2 refer to pattern types rather than specific product specifications, with an expectation that contractors will match existing floor patterns and colors as closely as possible. Vendors are instructed to refer to the included plan set and are responsible for bidding on all floors highlighted in the documentation. The Q&A document was dated 08/23/2024 and provides guidance to potential bidders about the scope of the flooring replacement work at the Lafayette Police Department.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| APPENDIX B - Floor _ Finish plan.pdf | ||
| APPENDIX A (Short Form - Goods _ Services Less Than 50K).docx | DOCX document | |
| RFP-24-20-FM (Police Department VCT Flooring).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers - 1
Project RFP-24-20-FM - City of Lafayette: Police Department VCT Flooring Project
Buying Organization City of Lafayette
No Question/Answer Question Date
Q1 Question: LS Contracting Question and Request
City of Lafayette
1290 South Public Road
Lafayette, Colorado 80026
Attention: Mike Nielsen- Project Manager
RE: Police Department VCT Flooring Replacement RFP-24-20-FM
Below are the questions and requests we have for the above-referenced proposal.
1.What is the current VCT product that is listed as “VCT-1” and “VCT-2” on Appendix B Floor Finish
Plan?
2.We request a comprehensive list of all room numbers and their respective locations on the floor plan where VCT replacement has been requested so we ensure that no rooms have been overlooked in our proposal.
Thank you for your time and I look forward to hearing back from you.
Lisa Lovern
LS Contracting LLC
719-232-0128
Answer: VCT-1 & VCT-2 refers to pattern and not product. There is no product specifics mentioned in the request with the expectation that the patterns and colors of the existing are matched as closely as possible.
Please refer to the included plan set for the room information. Vendors are responsible to bid all floors highlighted in the plan set.
08/23/2024