Q&A Document 1.pdf
PDF 4 KB Posted
- Attached to
- Cell 7 Site Fill
- Solicitation number
- 25-2568
- Issued by
- Muskegon County, Michigan
About this file
This document is a Questions and Answers (Q&A) file for the Cell 7 Site Fill project issued by Muskegon County, Michigan. The document contains seven questions from potential bidders regarding various aspects of the project, including water source availability, clearing and grubbing procedures, bid bond requirements, project timeline, soil borings, detailed site specifications, and a request for bid date extension. All answers direct respondents to consult Addendum 1 for comprehensive information. The project appears to involve structural fill work at the Muskegon County Landfill, with specific considerations around site preparation, monitoring well removal, snow fence installation, and restoration of disturbed areas.
The Q&A document reveals that the project is constrained to a 65-workday timeline (13 five-day work weeks of 10-hour days), with potential special damages for extended CQA (Construction Quality Assurance) efforts. Contractors are seeking clarification on multiple technical aspects, including haul routes, site clearing responsibilities, well abandonment procedures, fence specifications, and restoration methods. The questions suggest a complex project requiring detailed environmental and engineering considerations, with potential challenges related to project duration, site preparation, and specific infrastructure requirements. The consistent reference to "see addendum 1" indicates that more comprehensive details will be provided in a separate document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RAVENNA.pdf | ||
| 25-2568 Cell 7 Site Fill - Final.pdf | ||
| _OneGolderLarge.ctb | — | |
| wooden snow-fence-installation.jpg | JPG image | |
| SULLIVAN.pdf | ||
| BRIDGETON.pdf | ||
| SB-19 - SB-22.pdf | ||
| 31406824MI.1010A_002_TRANSMIT.dwg | DWG drawing | |
| 31406824MI.1010A_001_TRANSMIT.dwg | DWG drawing | |
| 31406824MI.1010A_001_TRANSMIT.txt | TXT text file | |
| W9 BLANK.pdf | ||
| 31406824MI.1010A_006_TRANSMIT.dwg | DWG drawing | |
| 31406824MI.1010A_005_TRANSMIT.dwg | DWG drawing | |
| DWG To PDF_LAYERS OFF.pc3 | — | |
| Pexco~PDS Winged Slat Product Sheet.pdf | ||
| _OneGolderSmall.ctb | — | |
| Retaining Wall Proposed Fence Sketch.PDF | ||
| MCL_Western_Expansion_1969.tif | TIF image | |
| WOLF_LAKE.pdf | ||
| 31406824MI.1010A_002_TRANSMIT.txt | TXT text file | |
| 31406824MI.1010A_004_TRANSMIT.dwg | DWG drawing | |
| 31406824MI.1010A_003_TRANSMIT.dwg | DWG drawing | |
| 20110707_PUT_811Eng_ver_RGB.jpg | JPG image | |
| 25-2568 Cell 7 Site Fill Bid Sheet.xlsx | XLSX spreadsheet | |
| 25-2568 Cell 7 Site Fill Addendum #1 - Final.pdf | ||
| Pic of Berm Well Retaining Wall.jpg | JPG image |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers - 1
Project 25-2568 - Cell 7 Site Fill
Buying Organization Muskegon County
No Question/Answer Question Date
Q1 Question: Water Source
Is there a water source on-site available for the contractor to use for dust control and compaction efforts? If so, are there any fees?
Answer: Please see addendum 1 for answers to questions.
01/03/2025
Q2 Question: Clearing and Grubbing
Can the contractor burn trees/brush from the clearing activities?
Answer: Please see addendum 1 for answers to questions.
01/03/2025
Q3 Question: Bid Bond Requirements
I don't see any requirements for a bid bond. Can you please clarify whether a bid bond is required?
Answer: Please see addendum 1 for answers to questions.
01/06/2025
Q4 Question: Muskegon Cell 7 Structural Fill
1. What date can we start the project ?
2. Section 4.02 Contract Times: CQA effort allows for a project span of 13, 5-day work weeks of 10-hour days (65 workdays). Any additional CQA required is subject to Special Damages listed in Paragraph
4.04 below. The project cannot be completed in 65 days, including clearing & grubbing, import, placement and restoration. Can the number of days be increased ?
3. Will silt fence be required around the Topsoil Stockpiles ?
4. Do we need to seed the Topsoil Stockpiles at the end of the project.
5. Can you provide specifications on the Wooden Snow Fence you are wanting ?
6. Snowmobile Trail Relocation Note states to be relocated. What surface are we required to leave on the snowmobile trail when complete ?
7. Item 10 Chain Link Well Protection - Can you provide a sketch of what you are looking for us to innstall around the Well ? How many wells require a fence ?
Answer: Please see addendum 1 for answers to questions.
01/06/2025
Q5 Question: Soil Borings
Can you please provide all soil boring information related to the work area of Cell #7 not included in the specs (specifically SB 19-22)
Answer: Please see addendum 1 for answers to questions.
01/07/2025
No Question/Answer Question Date
Q6 Question: Cell 7 Questions
1.Can a map be provided showing the proposed imported haul routes for importation of fill soils onsite?
2.Will the Owner be performing the site clearing prior to mobilization, if so, what is the schedule for the site clearing of the trees? And who is responsible for removing stumps?
3.What are the diameters and materials (PVC v. steel) of the monitoring wells to be removed? Can any well installation diagrams or logs be provided?
4.In the measurement and payment for the Abandonment of Existing Monitoring Wells, it states
“Abandonment is to be completed by an environmental driller in compliance with EGLE requirements” this typically includes grouting the wells in place and cutting well casing off below grade, but the “Well
Construction Schedule” indicates to “Remove” wells in the description. Is over drilling/removal a requirement? Is there any additional written description you can provide from project plans to detail how the wells are to be abandoned?
5.What is the required spacing on the T-post for the wooden snow fence and how long of a T-post do you want?
6.For the chain link, are you requiring the installation of 2” LP and 3” terminal posts? What is required for the top of the fence top rail v. tension wire?
7.Is Hydroseeding of an acceptable means of restoration of new and disturbed areas?
Answer: Please see addendum 1 for answers to questions.
01/07/2025
Q7 Question: Consideration of a Bid Extension
Good afternoon -
Given the fact that this opportunity came through just before the holidays, is there any possibility of getting an extension on the bid due date? Even by one week would be an immense help.
Thank you, Dave
Answer: Please see addendum 1 for answers to questions.
01/07/2025
Questions & Answers - 1
File details come from the government source that posted it. Updated .