This is a Questions and Answers document issued by the Florida Department of Transportation (FDOT) District 5 Operations regarding Invitation to Bid DOT-ITB-5012-OBWE for construction of bay walls and installation of electrical infrastructure at the Orlando Operations facility. The project encompasses constructing three framed walls within existing equipment storage bays and performing comprehensive electrical work including new circuit breakers, motorized roll-up door operators, LED lighting fixtures with emergency backup capability, exit signage, and exterior wall packs. Key electrical specifications clarified in the Q&A include: each bay will receive one regular LED light and one 90-minute emergency backup light controlled by a switch inside Bay 1; wall-mounted emergency lights will be relocated from interior to exterior positions at bay openings; push buttons for garage doors will be mounted on a gang box next to the man door inside each bay at 48 inches from the floor; all electrical work must be installed in conduit; and one receptacle will be installed at the man door in Bay 1. A mandatory site visit and pre-bid meeting was held on February 23, 2026, at 9:00 AM EST. Price proposals are due on or before March 10, 2026, at 10:00 AM EST, with public bid opening at 11:00 AM the same day. A selection committee meeting is scheduled for March 16, 2026, at 9:30 AM EST, with intended award posting by 2:00 PM that day. The contract is anticipated to begin on or about March 19, 2026, with all work to be completed by June 1, 2026.

The solicitation requires compensation as a lump-sum payment upon final completion and acceptance of work. Bidders must be registered in MyFloridaMarketplace, possess a Florida General Contractor's or Builder's license, and submit documentation of at least five years of experience in similar construction services, three business references, and E-Verify compliance certification. General liability insurance with combined bodily injury limits of at least $200,000 per person and $300,000 each occurrence, plus property damage insurance of at least $200,000 each occurrence, is required. Out-of-state corporations, limited liability companies, and limited partnerships must be authorized to do business in Florida. The contract award value or budget range is not disclosed in the available procurement materials. No specific set-asides for disadvantaged enterprises are identified, and no incumbent vendors or current contractors are identified. All bids must be submitted electronically in PDF format (maximum 25 MB) to D5.Purch@dot.state.fl.us, and the MFMP Transaction Fee will apply to all payments issued to the awarded vendor.

View the file

Other files

File Type Posted
Addendum 1- Selection Meeting Date CHANGE.pdf PDF
Q&A#2.pdf PDF
DOT-ITB-26-5012-OBWE COMPLETE.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Transportation

RON DESANTIS

GOVERNOR

719 S. Woodland Boulevard DeLand, Florida 32720-6834

JARED W. PERDUE, P.E.

SECRETARY

Improve Safety, Enhance Mobility, Inspire Innovation www.fdot.gov

Questions and Answers #1

ADVERTISEMENT NUMBER: DOT-ITB-5012-OBWE

DESCRIPTION: District 5, Orlando Ops Construction of Bay Walls & Installation of Electric

DATE: 2/23/2026

1. What will control the 2 new bay lights in each unit?

RESPONSE: All 2x4 lights will be control by a light switch installed on the inside of bay 1, by man door, from electrical box.

2. The garage door at each entrance get a wall mount emergency 1 or 8?

RESPONSE: No, only wall mount emergency one (1) over man door

3. What is the approximate distance the interior all pack be relocated (how many feet from existing location)?

RESPONSE: If we all are talking about wall pack – Wherever the wall packs lights are in the inside transferred to outside but center of opening.

Because of the bulkhead of roll-up doors, we will need to also move the existing conduit from the inside wall to the outside wall.

4. What is the meaning when the phase use (at man door)?

RESPONSE: The new 3-0 door that is being installed on bay #1

5. How many emergency lights do you want installed 1 or 8?

RESPONSE: 2x4 integral emergency battery backup one (1) per bay, and one (1) by man door on the inside of bay

6. Will the garage door have a wall switch at each entrance if so height and what side looking outside to in?

RESPONSE: All push buttons will be on gang box next to man door inside of bay, will need to run low voltage from box to motor via conduit, 48” from floor.

7. All electrical work to be in conduit or just dedicated home runs needed?

RESPONSE: Conduit

8. Each bay gets 2 - 2x4 one regular and one 90m emergency back up?

RESPONSE: Each bay will have one (1) regular LED and one (1) 90m emergency light.

9. The emergency lights over the door do you want it to have its own circuit?

RESPONSE: No

10. The one receptacle to be installed at man door. Which bay is that! From electrical panel box 1 through 4?

RESPONSE: Bay #1-man door side of bay