Q and A B54412.docx
DOCX document 28 KB Posted
- Solicitation number
- 27-444DHS-MENTH-B-54412
- Issued by
- Madison County, Illinois
About this file
This document is a Question and Answers file for the Illinois Department of Human Services (DHS) regarding the Chester Mental Health Center (CMHC) Unit F Flooring Tile Abatement and Refinishing project (IFB 27-444DHS-MENTH-B-54412). The project encompasses the abatement and removal of approximately 10,632 square feet of asbestos-containing floor tiles and mastic across two patient housing modules at 1315 Lehmen Drive, Chester, Illinois, followed by installation of epoxy flooring systems with a minimum 80-mil thickness. The scope includes concrete substrate preparation to a 120-grit finish, application of a manufacturer-approved vapor barrier, installation of non-slip two-part epoxy flooring with decorative flakes (except in patient rooms), cove base details (2-inch radial coves in non-patient areas and 4-inch wall bases in patient rooms), and installation of three heavy-duty vandal-resistant transition strips per module. The project must be completed module-by-module, with Module 1 fully completed, inspected, and accepted before Module 2 work begins, with an estimated two-week transition period between modules. The overall contract term runs through June 30, 2027, with work restricted to Monday through Friday, 7:00 a.m. to 4:00 p.m., requiring one day advance scheduling notice.
This procurement is restricted exclusively to certified small-business vendors under the Small Business Set-Aside program, with the prime contractor required to perform at least 51 percent of total work (excluding materials) with its own organization, verified through Illinois Department of Labor Certified Payroll Reports and facility visitor logs. Subcontractors with annual contract values exceeding $100,000 require prior written State approval. The facility will remove shelving, furniture, and all items from units before work begins and will handle all repainting and touchup work following epoxy installation, though vendors must tape off areas to minimize paint removal. Payment is structured as a lump sum for the entire project with no progress billing by module; the entire project must be completed before payment processing begins following written facility acceptance and invoice receipt by the business office. Vendors are responsible for all materials, equipment, generators (if 220V power is needed), trailer storage, tool security, debris removal through designated exits, concrete crack repair (1/16-inch or greater), and corrective measures if slip resistance testing does not achieve the minimum Dynamic Coefficient of Friction of 0.42 (wet). Vendors must also implement dust containment, fume and odor control, and appropriate ventilation during grinding and coating operations in compliance with OSHA, EPA, IDPH, and manufacturer requirements. General Commercial Liability insurance of $1 million per occurrence and $2 million annual aggregate, Auto Liability insurance of $1 million per occurrence, and Worker's Compensation Insurance as required by law are mandatory.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DHS IFB Chester Flooring Unit F Contract B-54412.docx | DOCX document | |
| invitation-for-bid-offer-to-the-state-of-illinois-v-25-3-2-24-25 B-54412.pdf | ||
| RMO150~30.docx | DOCX document | |
| invitation-for-bid-vendor-instructions-and-requirements-v26-1 B-54412~2.docx | DOCX document | |
| B54412 Sign In Sheet.pdf | ||
| ipg-active-registered-vendor-disclosure-formerly-forms-b-v-26-1-8-26-2025-1 B-54412.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DMH IFB CMHC FY27 Unit F Flooring Tile Abatement & Refinishing
27-444DHS-MENTH-B-54412
Questions and Answers
1. Does the 51% self‑performance requirement include materials?
· No, it does not include materials. It refers only to actual work performed.
2. This unit has some carpet. Does the carpet need to be removed? If so, when the carpet is pulled up, sometimes the glue can cause the tiles to lift or pieces of the tile to come up. Since this job calls for no breaking of the tiles, will it be an issue if the carpet removal causes pieces of tile to come up?
· Yes, the carpet needs to be removed and disposed of. The requirement is that there be no deliberate breaking of the tiles. If, during the normal process of removing the carpet, some tile pieces come up, that is acceptable. There isn’t much we can do to avoid that, as long as no intentional breaking occurs.
3. Will shelving and shelving base be removed by the facility?
· Yes
4. Will a generator be required?
· If 220 power is needed, then the vendor will need to determine whether a generator is necessary.
5. Will we be able to bring the generator, park it nearby, and leave it until it is no longer needed, or will it need to be removed each day?
· Yes, we can find a place to keep it on-site while the work is being done. However, it must remain secured at all times, and any damages to the property that occur will be the vendor’s responsibility. As well, we are not responsible for any damages or issues with the generator.
6. Will we able to leave tool and equipment on the unit while the work is being done?
· Yes, tools and equipment may be left on the unit while work is in progress. However, the vendor is responsible for ensuring they are secured at the end of each day and must provide their own means of securing them (for example, a locked toolbox). Additionally, any sharp items such as knives, blades, or scrapers, must be removed or locked up each night. Once the project is completed, the vendor must confirm that no broken razor blades, sharp items, or similar materials have been misplaced, forgotten, or left undisposed of.
7. For the transition strips, are you able to tell us if there is a specific type or brand you want?
· The Chief Engineer – we can show you one that was used on other flooring project. They need to be vandal‑resistant, appropriate for behavioral‑health areas, securely fastened, and removable only with tools. We will need three per unit, not 2, we will need an additional one at the doorway of the nurse’s cage.
8. Are the doorways all the same size?
· Not sure, but I don’t believe so.
9. Is the 80 mil or greater requirement correct?
· Yes, we want 80 mil or greater.
10. A cove is required, correct? And do you have the approximate footage of the required cove base?
· Yes, a 2-inch cove from floor to wall is required at the perimeter of all epoxy areas except patient rooms and closets, with the exception that the housekeeping closet also needs to have the cove. Patient rooms shall receive an epoxy base strip approximately 4 inches high from the floor.
· The cove base is an estimated 365’ per unit which is 730’ total for both.
11. When installing epoxy up on the wall, it is best to remove the paint down to the block/concrete for it to adhere correctly. Will the facility complete that for the vendor beforehand?
· No, the vendor will be responsible for removing the paint down to the block/concrete.
12. If the vendor is responsible for this, sometimes removing the paint may result in areas where slightly more or less than 4 inches is removed. Who will be responsible for fixing the paint so it meets up cleanly with the epoxy?
· The facility will handle repainting and touch‑up work. However, we expect the vendor to tape off the area or use other methods to avoid removing excessive amounts of paint or creating a larger area than needed.
13. Will we be able to bring a trailer and leave it parked near the work site while the work is being done?
· Yes, we can find a place to keep it on-site while the work is being done. However, it must remain secured at all times, and any damages to the property that occur will be the vendor’s responsibility. Additionally, we are not responsible for any damages to the trailer.
14. Will we have to take the debris and waste back out the way we came in, through the hallway and the sally port gate, every time?
· No, we do not use those doors when patients are on the unit, but since this unit will not have any patient movement, you will be able to use the doors that lead directly outside from the unit.
15. The project calls for us to fill cracks 1/16" or wider before finishing. When the other flooring project was done on E, were there any cracks of this size or larger, or a large number of cracks?
· No , there were some cracks, but none that were very large.
16. Will the facility remove all the furniture and items from the units before the work begins?
· Yes, the facility will.
17. This project is calling for decorative flakes, but not in the patient rooms, correct?
· Yes, decorative flakes are required in all epoxy areas except patient rooms.
18. Is there a specific top coat that is required?
· No, there is no specific brand required. However, the top coat must be suitable for healthcare environments and easy to clean. It should not be too heavy or textured, as that would make cleaning difficult. The top coat must also provide UV protection to prevent discoloration and degradation, as well as chemical resistance and abrasion resistance appropriate for high‑traffic patient care areas.
Acceptance and Progress Payments During the walkthrough, facility representatives explained that Module 1 must be completed, cleared, inspected, and accepted before occupants can be relocated and Module 2 made available. The transition may involve an interruption of approximately two weeks or longer.
5. Will the State establish separate payment milestones for each completed and accepted module?
• No, this project is for a whole and should be invoiced that way.
6. Upon written acceptance of Module 1, may the contractor submit an invoice for the agreed value of that module without waiting for completion of Module 2?
• No, this project is for a whole and should be invoiced that way.
7. Will payment for accepted Module 1 work be processed independently of the State's relocation schedule and release of Module 2?
• No, this project is for a whole and should be invoiced that way.
8. If module-based progress billing is permitted, will the payment allocation and invoicing terms be established in the contract before award?
• No, this project is for a whole.
9. Will retainage apply, and what is the anticipated payment-processing period following receipt of an approved invoice?
• This project requires the entire project to be completed before payment can be processed. Once the facility has accepted the completed work and the invoice has been received by the business office, the payment‑processing steps will begin.
Requested clarification: Please confirm whether each module may be established as a separately acceptable and billable milestone, with payment eligibility upon written acceptance.
• No, this project is for the whole unit to be completed before processing payment.
3. State-Controlled Delays and Remobilization
10. If Module 2 is unavailable following acceptance of Module 1, will the contract completion schedule be extended for the period of State-controlled delay?
• This entire project must be completed by 6/30/2027.
11. If the interval between modules exceeds the anticipated transition period, will documented additional mobilization, equipment rental, storage, or other delay-related costs be eligible for compensation through an authorized written contract amendment?
• No, vendors need to take this into consideration when quoting the project.
12. What written notification will the State provide when Module 2 is ready for contractor remobilization?
The Contractor shall provide a schedule proposal for the first module, and the Facility will evaluate the time required to return the completed module to service and prepare the second module for construction activities.
The anticipated interval between completion of the first module and authorization to begin work in the second module is approximately two (2) weeks; however, actual timing will be determined by Facility operational needs.
The Contractor will receive written authorization via email from the Chief Engineer confirming that the second module has been released for construction and that remobilization may proceed.
4. Minimum 80-Mil Flooring Thickness
13. Does the minimum 80-mil requirement refer to the completed, fully cured flooring system rather than wet application thickness?
Fully cured.
14. Which layers count toward the required thickness, including vapor barrier, primer, epoxy body coats, decorative flake, and protective topcoats?
The 80 mil minimum refers to the combined epoxy system thickness—primer, body coats, build coats, flake build, and topcoats. The vapor barrier is a separate requirement and does not contribute toward the required system thickness.
15. Does the minimum thickness apply equally to patient rooms without decorative flake?
Yes.
16. What method will be used to verify and accept the finished thickness? Would a documented witness panel prepared alongside the flooring installation be acceptable?
Dry‑film thickness (DFT) measurements shall be performed by the Contractor using a calibrated dry‑film thickness gauge appropriate for resinous flooring systems installed over concrete substrates. The Contractor shall document all readings and submit a DFT report to the Facility for review and acceptance.
The Facility reserves the right to:
• witness DFT measurements,
• require additional readings at locations it designates, and
• reject areas that fail to meet the specified minimum installed thickness of 80 mil.
The Facility is not responsible for performing DFT measurements.
A witness panel may be provided as supplemental documentation.
Calipers may be used on the witness panel only if the panel is constructed to allow cross‑sectional measurement. The witness panel does not replace required DFT readings on the installed flooring system.
5. Moisture Testing and Vapor Barrier
17. What concrete moisture-testing methods and acceptance limits will the State require before flooring application?
The State requires that concrete moisture testing be performed in accordance with the epoxy manufacturer’s instructions. Testing may include ASTM F2170 (in situ RH), slab pH testing, and any additional methods required by the epoxy system manufacturer to ensure warranty compliance.
Moisture testing is performed to document slab conditions and verify compatibility with the specified flooring system; however, a vapor barrier (moisture mitigation system) shall be applied regardless of moisture levels.
Acceptance limits for moisture tests shall follow the flooring and vapor barrier manufacturers’ published installation requirements, and test results shall be submitted to the Facility prior to installation.
18. Is the specified vapor barrier required throughout the entire flooring area, including patient rooms?
Yes.
19. If testing identifies moisture conditions exceeding the flooring manufacturer's approved limits, how will additional treatment, cost, and schedule impacts be addressed?
Because the Facility requires installation of a vapor barrier / moisture mitigation system regardless of moisture levels, elevated moisture readings will not result in a change in scope, cost, or schedule for the Contractor. Moisture testing is performed only to verify slab conditions and ensure compatibility with manufacturer requirements.
If moisture levels exceed the epoxy manufacturer’s published installation limits, the Contractor shall:
| 1. | Follow the epoxy manufacturer’s instructions for installation over a vapor barrier system. |
| 2. | Proceed with installation of the vapor barrier, which is already required in the project scope, regardless of moisture test results. |
| 3. | Assume all associated cost, labor, and scheduling requirements necessary to achieve a warrantable system. |
No additional compensation, schedule extensions, or change orders will be approved for moisture related conditions, as moisture mitigation is already included in the base contract requirements.
6. Topcoat Performance and Cleaning Requirements
20. Are manufacturer-approved polyaspartic or aliphatic polyurethane topcoats acceptable when they meet the specified performance criteria?
Yes. Manufacturer approved polyaspartic or aliphatic polyurethane topcoats are acceptable, provided that:
1. The topcoat meets or exceeds all specified performance criteria, including:
• UV protection
• chemical resistance
• abrasion resistance
• slip resistance requirements for hospital patient care areas
| 2. | The product is fully compatible with the selected epoxy system and is included in the flooring manufacturer’s recommended or warrantable system. |
| 3. | The Contractor follows all manufacturer installation instructions to maintain warranty eligibility. |
| 4. | The manufacturer provides written confirmation that the proposed topcoat is approved for use within their warranty program for the specified application. |
Final determination of acceptability shall be based on compliance with all project requirements and submission of manufacturer documentation demonstrating compatibility and warranty coverage.
21. Does the facility have a list of disinfectants, cleaning chemicals, or maintenance products against which the proposed flooring system must demonstrate chemical resistance?
The cleaner in service for epoxy flooring at the center is Echo Labs 6100036 – High-Performance Neutral Floor Cleaner.
22. Are there specified slip-resistance or surface-texture acceptance criteria for the completed floor?
Field Testing Requirements for Slip Resistance
1. Field Testing Standard Slip resistance of the installed flooring system shall be verified in the field using a portable tribometer meeting the requirements of ANSI A326.3 for measuring Dynamic Coefficient of Friction (DCOF).
2. Required Performance Level The finished flooring system shall achieve:
• Minimum DCOF (wet): 0.42, measured in accordance with ANSI A326.3.
This requirement provides adequate traction for hospital patient care areas while avoiding overly rough textures that hinder cleaning or trap moisture in environments lacking humidity control.
3. Testing Locations Field testing shall be performed at:
• a minimum of three random areas per module, and
• any additional locations designated by the Facility.
4. Responsibility for Testing
• The Contractor shall perform the field slip resistance testing.
• The Facility reserves the right to witness testing or request additional verification.
5. Corrective Action If the installed flooring fails to meet the required DCOF value:
• The Contractor shall perform corrective measures (e.g., additional topcoat, adjustment of anti slip media) at no additional cost to the Facility.
• Retesting shall be performed until compliance is achieved.
7. Cove Base, Patient Rooms, and Transitions
23. Please confirm the required height and profile of the integral cove base in non-patient areas, including any specified radius or horizontal floor extension.
Epoxy Cove Base Cove base shall include:
• A 2-inch (2") radial cove transition from floor to wall, formed using manufacturer approved materials and tools to produce a uniform, smooth radius profile.
• 4 inches (4") of epoxy system applied vertically onto the wall surface above the cove radius, matching the flooring system’s resin, aggregate, and finish.
• Cove base shall be fully bonded, non-porous, and integrated monolithically with the floor system to create a continuous, hygienic, and chemically resistant surface with no gaps or cold joints.
• All materials, application methods, and thicknesses shall comply with the epoxy system manufacturer’s written specifications for cove base installation.
• Final finish shall be uniform in texture and color, with clean, true lines and smooth transitions.
The 80-mil minimum flooring system thickness applies to the horizontal floor system. Cove base and vertical wall extensions shall be installed in accordance with manufacturer recommendations for a warrantable system.
24. For patient rooms without decorative flake, please confirm the required four-inch epoxy wall-base detail and whether a formed cove is excluded.
Formed cove is excluded. The four-inch epoxy wall base should match the height of the non-patient areas wall bases.
25. Can the State provide a room schedule, drawings, or verified linear footage for cove-base and patient-room wall-base work?
Drawings and available quantity information will be provided upon request.
26. During the walkthrough, a recommended heavy-duty threshold or transition product was discussed. Please provide the preferred manufacturer, product, profile, or performance specification.
No specific manufacturer or product is required. Proposed transition products shall be heavy-duty, suitable for healthcare and behavioral health environments, vandal-resistant, securely fastened, removable only with tools, and compatible with the flooring system.
27. Please confirm the total number and locations of required transitions for both modules.
3 per module and 6 total.
8. Existing Substrate Conditions and Additional Work
28. What level of concrete crack repair, leveling, adhesive removal, and surface correction is included in the base bid?
The Base Bid shall include:
| • | Complete removal of all ACM floor tile and mastic as specified. |
| • | Mechanical preparation of the concrete surface to a minimum 120-grit finish. |
| • | Filling of cracks 1/16 inch or greater with a compatible filler. |
| • | Minor surface repairs necessary to provide a sound, uniform substrate suitable for installation of the specified vapor barrier and epoxy flooring system. |
| • | Surface preparation required by the flooring manufacturer to obtain a warrantable installation. |
| • | Removal of residual mastic and adhesive necessary to achieve manufacturer-required substrate conditions. |
| • | Concrete patching, void repair, spall repair, surface leveling, and surface correction affecting up to 10% of the total floor area within each module shall be included in the Base Bid. |
Repairs exceeding the included 10% floor area allowance or involving structural concrete deficiencies, concealed subsurface conditions, or conditions not reasonably identifiable during the mandatory pre-bid inspection may be considered for additional compensation through the contract change-order process. No additional work shall be performed without written authorization from the Facility.
29. If asbestos removal exposes concealed concrete deterioration or conditions beyond the specified preparation requirements, what is the procedure for obtaining written authorization and compensation before additional work is performed?
If asbestos abatement exposes concealed conditions that could not have reasonably been identified during the mandatory pre-bid inspection and that exceed the scope of preparation and repair work included in the Base Bid, the Contractor shall:
| 1. | Immediately notify the Facility in writing. |
| 2. | Document the condition with photographs, dimensions, and a description of the impacted area. |
| 3. | Identify the extent of repairs already included within the Base Bid, including the required 10% floor area repair allowance. |
| 4. | Provide a proposed corrective action and detailed cost estimate for any work exceeding the Base Bid requirements. |
The Base Bid includes concrete patching, void repair, spall repair, surface leveling, and surface correction affecting up to 10% of the total floor area within each module. Conditions falling within this allowance shall not constitute grounds for a change order.
No additional work beyond the contracted scope shall be performed without written authorization from the Facility. Any approved additional work will be addressed in accordance with the contract change-order provisions. The total payments under the initial term of this contract shall not exceed that amount without a formal amendment.
30. Who will determine when the abated substrate is sufficiently clean and released for concrete preparation and epoxy installation?
The abated substrate shall be considered released for concrete preparation and flooring installation after:
| • | Completion of all required asbestos abatement activities. |
| • | Completion of any required regulatory inspections and clearance procedures. |
| • | Written confirmation from the Contractor's asbestos abatement project supervisor that the work area has been properly cleaned and is ready for subsequent work. |
The Contractor remains responsible for ensuring the substrate is suitable for installation of the specified flooring system and shall notify the facility of any conditions that may affect the quality or warranty of the finished installation. Release of the substrate by the asbestos abatement contractor does not relieve the flooring contractor of responsibility for evaluating substrate conditions and notifying the facility of any condition that may adversely affect flooring performance, quality, or warranty eligibility.
9. Power, Environmental Controls, and Work Access
31. The walkthrough indicated that the contractor may need to supply its own 220V generator. Please confirm whether facility electrical power is available for smaller equipment and whether a tow-behind generator may remain in an approved location overnight.
Limited facility electrical power may be available for standard small tools and equipment; however, bidders shall assume responsibility for providing all power necessary to complete the Work.
If 220V power or other specialized electrical service is required, the Contractor shall provide suitable temporary power equipment.
A tow-behind generator may remain onsite overnight only in a location approved by the Facility. The Contractor shall be responsible for fuel storage, spill prevention, and compliance with all applicable environmental and safety requirements.
32. Are there specific requirements for negative air, dust containment, odor control, or ventilation during grinding and coating operations beyond those stated in the solicitation?
Yes.
The Contractor shall implement all measures necessary to protect patients, staff, visitors, and facility operations from dust, odors, fumes, and contaminants generated by the Work.
At a minimum, the Contractor shall:
| 1. | Maintain appropriate dust containment during grinding operations. |
| 2. | Control fumes and odors generated by flooring materials and solvents. |
| 3. | Provide ventilation and air movement as required by applicable regulations, product manufacturers, and project conditions. |
| 4. | Comply with OSHA, EPA, IDPH, manufacturer requirements, and all facility infection-control and safety requirements. |
| 5. | Conduct all work in a manner that prevents the migration of dust, fumes, and odors into occupied patient-care areas. |
33. Please confirm whether an enclosed contractor trailer may remain in a designated secured area during the interval between modules.
Yes. Subject to Facility approval, an enclosed contractor trailer may remain onsite in a designated location near the active project module between phases of work.
The Contractor shall:
| • | Coordinate trailer location with the Facility prior to placement. |
| • | Ensure the trailer is secured and locked at all times when not in use. |
| • | Be responsible for the security, maintenance, and housekeeping of the trailer and surrounding area. |
| • | Maintain compliance with all facility safety, security, and operational requirements. |
| • | Be responsible for repairing any lawn or landscaping damage resulting from trailer placement, access, or project activities at no additional cost to the Facility. |
The Facility reserves the right to relocate or remove approval for the trailer if it interferes with operations, safety, security, emergency access, or other facility activities
File details come from the government source that posted it. Updated .