Q_A Document 1 (55).pdf

PDF 7 KB Posted

Attached to
PATCHING, MILLING AND RESURFACING OF VARIOUS DOUGLAS COUNTY ROADS
Solicitation number
PE-64800-NONST-2026-000000071
Issued by
Douglas County, Georgia

About this file

This is a Questions and Answers document for Project 26-012 related to patching, milling, and resurfacing work on various Douglas County roads. The project involves significant asphalt work including patching (10,000 tons total), milling, and resurfacing of residential and commercial driveways across multiple roads including Dorsett Shoals, Miller Street, E. County Line Road, and Post Road (from I-20 Bridge to Highway 78). The document addresses 21 questions submitted by bidders between March 20 and April 2, 2026, covering technical specifications, work procedures, and project logistics. Key clarifications include confirmation that turn lanes and side roads will be included in milling and paving work, temporary advance warning signs on tripod stands are acceptable, and finished asphalt on roads with curb and gutter should be flush with the gutter lip. The contractor must complete milling for patching on the same day, with profile milling allowed 36 hours before topping application. Patching width must be a minimum of 7 feet to accommodate standard milling equipment, and 4.5mm asphalt should be used for leveling. The contractor is responsible for preserving asphalt curbs and replacing any damaged during work.

Specific work requirements include posting temporary striping within three days (tape acceptable for short-term use) and maintaining awareness of school traffic and pedestrian activity on E. County Line Road near Lithia Springs High School. The county declined to extend the bid due date despite requests for additional time and indicated that patching tonnage distribution across individual roads will remain at the engineer's discretion rather than being provided in advance. A county reference form was made available to bidders, and a bid opening link would be provided closer to the opening date. No information regarding pricing, contract term, funding sources, or award timeline is included in this Q&A document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers - 1

Project 26-012 - PATCHING, MILLING AND RESURFACING OF VARIOUS DOUGLAS

COUNTY ROADS

Buying Organization Douglas County

No Question/Answer Question Date

Q1 Question: Missing Reference Form

Please provide the County Reference Form to upload.

Answer: This form has been attached.

03/20/2026

Q2 Question: Bid Opening

Will there be a Bid Opening link provided?

Answer: Yes. a link will be added closer to the opening date.

03/20/2026

Q3 Question: Temporary Signs

Can temporary advance warning signs be used?

Answer: Yes they can

03/30/2026

Q4 Question: Driveways Resurfacing

Are all residential and commercial driveways to be included in the resurfacing?

Answer: Yes they are.

03/30/2026

Q5 Question: Leveling Asphalt

What type of asphalt is to be used for leveling?

Answer: 4.5mm should be used

03/30/2026

Q6 Question: Missing Information

The Appendix A (Summary of Information by Road) is blank. Can Douglas Co. issue this information to the bidding contractors?

Answer: Appendix A List of Roads clearly states road name and from where to where for the work to be performed.

04/01/2026

Q7 Question: Paving Turn Lanes

Several of the roads (Dorsett Shoals, Miller St., E. County Line Rd.) have existing turn lanes. Will the turn lanes be included in the milling and paving limits?

Answer: Yes they should

04/01/2026

Q8 Question: Work Hour Restrictions

Since E. County Line Rd. goes in front of Lithia Springs High School will the work hours for this road be any different?

Answer: No, However the contractor needs to be mindful of school traffic and pedestrian traffic

04/01/2026

Q9 Question: Patching for Each Road

With 10,000 tons of Patching to be performed on these roads can Douglas Co. issue the tons of

Patching on each road?

Answer: Patching will be at engineers discretion

04/01/2026

No Question/Answer Question Date

Q10 Question: Advanced Warning Signs

Will the contractor be required to post mount the advanced warning signs or can these signs be placed on tripod stands?

Answer: Tripod stands will be acceptable

04/01/2026

Q11 Question: Final Paving Elevation

On the roads with curb and gutter should the finished asphalt be flush with the lip of the gutter?

Answer: Yes it should

04/01/2026

Q12 Question: Bid Due Date Extension

Since the Documents are missing vital information needed to provide the best possible bid, would you please extend the bid due date two weeks after this important information is provided?

Answer: No, this will not be possible.

04/01/2026

Q13 Question: Patching Width

Will all patching be marked at a minimum width of 7 feet to allow for the use of a standard milling machine? If not, what will the minimum patch width be?

Answer: Yes a minimum of 7 feet

04/02/2026

Q14 Question: Advanced Warning Signage

May the contractor use temporary advanced warning signage mounted on mobile tripod stands, or are they required to be post mounted?

Answer: Yes you may

04/02/2026

Q15 Question: Milling cover up time

How long will the contractor be allowed to leave a milled surface prior to placing topping?

Answer: Areas milled for patching will be required to be put back the same day. Profile milling is 36 hours

04/02/2026

Q16 Question: Temporary Striping

May tape be used as temporary striping?

Answer: Tape may be used for short term. Temporary striping is to be done within three days. See

General Notes paragraph 21 Phase 1

04/02/2026

Q17 Question: Curb Reveal and Quarter Crown

Regarding roads with asphalt that is currently paved higher than existing curb and gutter, will the contractor only be required to mill the depth required for the final topping to be the same as the current existing elevation at the gutter line? Or, will the contractor be required to mill additional depth (if necessary) to allow the new topping to be flush with existing curb and gutter? If the contractor is required to go deeper, only edge milling, there is a high likelihood that a "quarter crown" will be created, causing the topping to thin significantly at the half way point across the lane (7 feet in from the edge of pavement, edge milling width) since the paver screed is not flexible in the middle where the edge milling will end. With the topping thickness only being 135Lbs/SY, this could be a serious issue.

Answer: The counties goal is to try to get the edge line back to the top of curb however the county of these type issues. Milling is priced per square yard and additional milling may be required.

04/02/2026

No Question/Answer Question Date

Q18 Question: Patching tonnage per road

Is the County able to provide a breakdown of how many tons of patching is anticipated per road?

Answer: Patching will be at the engineers discretion.

04/02/2026

Q19 Question: Asphalt Curb

Miller Street (and others possibly) has a pretty significant amount of asphalt curb in some areas. What will be required of the contractor regarding this? Is the contractor required to preserve it, remove it, replace it, replace it, only if damaged?

Answer: Preserve. It will be the contractors responsibility to replace if damaged

04/02/2026

Q20 Question: Side roads and turn lanes

Will the contractor be required to mill and pave into side roads and turn lanes?

Answer: Yes they will

04/02/2026

Q21 Question: Post road Limits

Could the County please provide more precise start and stop points for Post Road?

Answer: I-20 ( Bridge ) to Hwy 78

04/02/2026

Questions & Answers - 1

File details come from the government source that posted it. Updated .