This is a Performance Work Statement (PWS) for a comprehensive baseline assessment, inventory, and upgrade scoping project for the Vindicator Intrusion Detection System (IDS) and Access Control System (ACS) infrastructure at Eielson Air Force Base (EAFB), Alaska, and associated Geographically Separated Units (GSUs). The project title is FY26 Vindicator Intrusion Detection System (IDS) Base-Wide Assessment, Inventory, and Upgrade Scoping, with an expected contract award date in April 2026.
The contractor shall deliver five primary tasks over a 180-day performance period: (1) Project Management and Coordination, including development of a comprehensive Project Management Plan with Plan of Action and Milestones (POA&M), risk management plan, and communication plan; (2) Comprehensive Assessment and Baseline Inventory, documenting all current IDS/ACS components, lifecycle status, network infrastructure (legacy copper versus modern fiber), vulnerabilities, and physical/network capacity requirements for full system head-end replacement; (3) Site Surveys and Expansion Scoping, including physical surveys for Munitions & Airfield coverage, Cameras & Optical solutions (License Plate Readers upgraded to 1080p or 4K), and Specialized Access Control evaluation; (4) System Design, Engineering, and Integration Planning (IDP) incorporating the V6 Vindicator platform, hardware scoping (appliances, keypads, workstations, servers, sensors, controllers), network integration with fiber optic cabling in legacy copper areas, facility configurations with specialized viewing permissions, and DoD Risk Management Framework (RMF) and DISA Security Technical Implementation Guides (STIGs) compliance; and (5) Sparing and Maintenance Strategy, establishing baseline inventory requirements for critical failure points including Vindicator V5 IDS, V5 ACS, and AES-1500f components. Deliverables follow a phased approach: Project Management Plan (15 Days After Contract Award), Site Survey & Inventory Report (45 Days ACA), 30% IDP (60 Days ACA), 60% IDP (90 Days ACA), 90% IDP (120 Days ACA), and 100% Final IDP with Statement of Work and locked Bill of Materials including market pricing (150 Days ACA). The Government requires minimum ten business days for review at each design stage, with contractor correction and resubmission required within five business days at no additional cost if deliverables are rejected. Performance objectives include 100% on-time submission with no more than one late meeting or report per month, zero critical operational sites missed in surveys with 95% technical accuracy in reporting, timely IDP delivery with government-directed corrections completed within five business days, BOM pricing reflecting current market rates with 100% compliance to Original Equipment Manufacturer (OEM) lifecycle standards, and zero unauthorized Controlled Unclassified Information (CUI) disclosures with 100% adherence to photography and STIG protocols. Security requirements mandate DD Form 254 applicability, contractor personnel requiring Secret or Top Secret/SCI clearances for restricted area surveys with continuous escort by cleared government personnel, prohibition on personal photography or electronic recording devices without explicit written authorization and official Base Photography Pass (AF Form 833), treatment of all project data as CUI with secure DoD-approved transmission methods, and full compliance with DISA STIGs for all system architectures and configurations. Applicable regulations include DAFI 31-101 (Integrated Defense), AFA4S GENADMIN 2024-09-05 (IBDSS Guidance), AFI 31-101 Section 5.3 (Physical Security Systems), AFI 31-102 Section 3.5.2 (IDS Requirements), AFI 91-204 Section 4.2 (Explosive Safety), AFI 36-3208 Section 5.3 (Financial Management), AFI 32-106 Section 4.2.3 (Information Management), and ICD-705 (SCIF/SAP Physical Requirements). The Government shall provide facility access, existing facility blueprints/as-built drawings and network topologies where available, and points of contact for coordination. Days 151-180 of the performance period are reserved for final Government review, acceptance, and contract closeout.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IDS_ACS Building List Summary v2_1_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
(PWS)
FOR
Vindicator Intrusion Detection System (IDS)
– Base-Wide Assessment, Inventory, and Upgrade Scoping
April 2026
Project Management Plan / POA&M
Comprehensive schedule, risk management plan, and communication plan.
15 Days ACA
Site Survey & Inventory Report
Baseline of legacy/modern systems, infrastructure, and site conditions.
45 Days ACA
30% IDP Title Page, Legend Sheet, Block Diagram, Floor/Site Plan, Device Layouts.
60 Days ACA
60% IDP Updates from 30%, High-Level BOM, Riser Diagrams, Initial CCTV plan.
90 Days ACA
90% IDP Updates from 60%, Detailed BOM, Wiring Details, Cable Runs, Switch Configs, Sparing Plan.
120 Days ACA
100% Final IDP &
SOW
Final drawing package, locked BOM (market pricing), execution-ready SOW.
150 Days ACA
3.2 Government Review and Acceptance: The Government requires a minimum of ten (10) business days to review and provide comments at each design stage. If the Government rejects a deliverable due to inaccuracies or failure to meet PWS requirements, the contractor shall correct and resubmit the deliverable within five (5) business days at no additional cost to the Government.
4.0 SERVICES SUMMARY (SS)
The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required.
Performance Objective
PWS
Reference
Acceptable Quality Level
(AQL)
Method of Surveillance
SS-1: Project Management.
Provide POA&M and facilitate
Task 1 100% on-time submission. No more than 1 late meeting or report per month.
Periodic Inspection by Government Representative progress meetings.
SS-2: Baseline Inventory & Surveys.
Document
IDS/ACS
components and vulnerabilities.
Task 2 & 3 Zero critical operational sites missed. Report is 95% free of technical inaccuracies.
100% Inspection by Government Representative
SS-3: System Design & IDP.
Deliver 30%, 60%, 90%, and 100% IDPs.
Task 4 & 3.1 Delivered on time.
Government-directed corrections made within 5 business days.
100% Inspection / Peer Review
SS-4: Sparing & Maintenance Plan. Deliver lifecycle BOM and sparing strategy.
Task 5 BOM pricing reflects current market rates.
100% compliance with OEM lifecycle standards.
100% Inspection by Government Representative
SS-5: Information Security
Section 6.0 Zero unauthorized disclosures of
CUI. 100%
adherence to photography/STIG protocols.
100% Inspection by Government Representative
/SM
5.0 GOVERNMENT FURNISHED PROPERTY AND SERVICES (GFP/GFS)
5.1 Government Provided Items: The Government will provide access to facilities for site surveys, existing facility blueprints/as-built drawings/network topologies (where available), and Points of Contact within for coordination.
6.0 SECURITY REQUIREMENTS
6.1 Clearance Requirements: A DD Form 254 (Contract Security Classification Specification) is applicable to this contract. Contractor personnel performing surveys in restricted areas must possess the appropriate security clearances (Secret or Top Secret/SCI) as dictated by the facility owner. Uncleared personnel require continuous escort by appropriately cleared government personnel, which must be coordinated in advance through the unit security managers.
6.2 Photography and Electronic Devices: The Contractor shall not take photographs or use personal electronic devices for recording within restricted areas, SCIFs, or SAP facilities without explicit written authorization. The contractor shall obtain an official Base Photography Pass (e.g., AF Form 833) prior to conducting any visual surveys. All photographs and digital recordings taken during the site surveys must be reviewed and cleared by or the applicable facility security manager prior to being removed from the installation or transmitted electronically.
6.3 Controlled Unclassified Information (CUI) and OPSEC: All data generated under this contract (including site survey reports, network topologies, blueprints, and IDPs) shall be treated as Controlled Unclassified Information (CUI). The contractor shall not store, process, or transmit CUI on personal or unsecured corporate networks. All deliverables must be properly marked as CUI and transmitted via secure, DoD-approved methods (e.g., DoD SAFE, encrypted email).
The contractor shall not publish, disclose, or discuss any details of this project outside of official Government coordination.
6.4 Cybersecurity Compliance: All proposed system architectures, network switch configurations, and head-end server designs must comply with Defense Information Systems Agency (DISA) Security Technical Implementation Guides (STIGs).
7.0 APPLICABLE REGULATIONS
The contractor shall design the system to meet all applicable security and infrastructure regulations, including:
• DAFI 31-101, Integrated Defense
• AFA4S GENADMIN 2024-09-05, SF Guidance for IBDSS
• AFI 31-101 Section 5.3, Physical Security Systems
• AFI 31-102 Section 3.5.2, IDS Requirements
• AFI 91-204 Section 4.2, Explosive Safety
• AFI 36-3208 Section 5.3, Financial Management
• AFI 32-106 Section 4.2.3, Information Management
• ICD-705, SCIF / SAP Physical Requirements
• SAP Community Regulations (As directed by Special Security Officer)
8.0 GENERAL INFORMATION
8.1 Place of Performance: Eielson Air Force Base (EAFB), AK, and associated Geographically Separated Units (GSUs).
8.2 Period of Performance: The Period of Performance shall be 180 Days from Date of Award.
(Note: Days 151-180 are reserved for final Government review, acceptance, and contract closeout).
8.3 Government Oversight: Government personnel will be appointed by the to perform technical inspections and accept deliverables. These representatives do not have the authority to alter the contract's scope, price, terms, or conditions. Only the warranted Contracting Officer (CO) has this authority.