This is a Performance Work Statement for the inspection and repair of a 10-ton Detroit double girder bridge crane located at the Machine Shop Building at US Moorings, 8010 NW St. Helens Rd., Portland, OR 97210. The contractor must provide all labor, material, and equipment necessary to troubleshoot and repair the overhead crane rails within a 90-day period of performance starting from contract award.
The work is divided into three contract line items (CLINs). CLIN 0001 requires disassembly and comprehensive inspection of the crane rails, wheels, bearings, and pins, with submission of a Condition Found Report identifying damaged components requiring manufacturing or replacement. CLIN 0002 involves repair and assembly pending written Contracting Officer approval, including proper shimming of new rails to maintain parallelism and elevation per overhead crane specifications, and operational testing to ASME and OSHA standards. CLIN 0003 requires functional testing with weight certification and verification by the Machine Shop Supervisor that all repairs resolve the documented tracking issue and restore the equipment to full 10-ton operational capacity. Performance standards require 0% deviation in accurate identification of required repairs, zero instances of unauthorized work, and 100% functionality with no binding, jamming, or mechanical failures during final operational testing. The contractor must develop and submit a Quality Control Plan within 14 calendar days of award and complete DoD/Army security training within 30 days. All personnel must be E-Verify verified within three business days of award. The technical lead is Brandon Scherschel at Brandon.Scherschel@usace.army.mil or (503) 808-5422, and the contract is administered by the Department of the Army, Portland District, Corps of Engineers.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement
Inspection and Repair of the Machine Shop Overhead Crane Rails
Portland, OR
1. General: Provide all labor, material, and equipment necessary troubleshoot and repair 10-ton Detroit double girder bridge crane rails, hereinafter referred to as “the equipment”.
1.1. Government Furnished Materials (GFM):
None.
1.2. Safety Precautions:
Follow all applicable state, local, and federal requirements including those specified in EM-385-1-1 latest revision.
1.3. Submittals:
None.
1.4. Period of Performance:
Period of Performance (PoP) is 90 days starting from an award date.
1.5. Work Location:
The equipment is currently located in the Machine Shop Building.
Address: US Moorings, 8010 NW St. Helens Rd., Portland, OR 97210
2. Definitions:
• Acceptable Quality Level (AQL): The performance standard that defines the maximum allowable margin of error or defect rate before performance is considered unsatisfactory. The Contractor must re-perform all unsatisfactory work unless excused by the Government Representative.
• Contracting Officer (KO): The Government employee who is authorized to enter into, administer, and/or terminate contracts and make related determinations and findings.
• Contract Discrepancy Report (CDR): A written record of unsatisfactory performance by the Contractor as observed by the Government Representative.
• Performance Requirements Summary (PRS): Identifies critical success factors for the contract, including performance objectives and the threshold required for each objective.
• Quality Assurance (QA): A method used by the Government to provide control over the quality of services received.
• Quality Assurance Surveillance Plan (QASP): A systematic method used by the Government to evaluate the services the Contractor is required to furnish.
• Quality Control (QC): A method implemented by the Contractor to control the quality of goods and services provided.
• Condition Found Report (CFR): A document prepared by the Contractor used to transmit specific information concerning inspections, deficiencies, or to propose additional work requiring a Government response.
3. Specification and Tasks:
Background Issue: During recent operations, the bridge crane experienced severe tracking failure. Due to structural misalignment, unsecured rail mounts, and excessive wear on the crane rails and crane wheels, the bridge attempted to climb on top of the rails and dropped back down.
This near derailment occurred directly above the radial arm drill press on the northwest side of the
Machine Shop. The equipment is currently highly unstable and poses an immediate threat to safety and machinery.
3.1. CLIN 0001: Disassembly & Inspection
Disassemble and comprehensively inspect the crane rails, wheels, bearings, and pins. Determine which components are damaged and require manufacturing or replacement. Submit a Condition Found Report
(CFR) outlining these required parts to ensure the equipment will be restored to its full operation.
3.2. CLIN 0002: Repair & Assembly
Pending written approval and authorization from the Contracting Officer (KO) based on the CFR, proceed with the repairs. Reassemble the crane components, ensure new rails are properly shimmed, maintaining parallelism and elevation within overhead crane specifications from the south end of the Machine Shop to the north end of the Machine Shop, and properly secured. Conduct operational testing on the overhead crane to ensure the equipment is fully restored to ASME, and OSHA operational parameters.
3.3. CLIN 0003: Operational Testing & Restoration
Functional test the equipment. Machine Shop Supervisor verifies work is completed and perform a weight test. Contractor shall provide an updated crane certificate to authorize full operation of 10 tons. Machine Shop
Supervisor or Government Representative ensures repairs resolve the tracking issue and performance meets
PWS scope prior to final acceptance.
4. Inspection & Acceptance:
Machine Shop Supervisor shall be present during the service to ensure the service is conformed to the scope in this Performance Work Statement (PWS). Machine Shop Supervisor or a Government
Representative shall be present during final testing to ensure service conforms to the scope defined in this
PWS and that all repairs successfully resolve the identified issues prior to final acceptance.
5. Performance Requirement Summary (PRS)
5.1. General: The PRS determines if the Contractor meets the performance standards of the contract and provides guidelines for surveillance. Government contract quality assurance will be performed per the
PRS surveillance schedule.
5.2. Performance Requirements Summary Table: Work shall be considered incomplete or unacceptable when any of the following conditions exist in accordance with the QASP.
5.3. Surveillance: Periodic inspection by the Machine Shop Supervisor or Government Representative will serve as the primary surveillance method. If the Machine Shop Supervisor or Government
Representative discovers deficiencies, the Contractor will be alerted for immediate correction.
5.4. Quality Control: The Contractor is responsible for quality control. The Contractor shall develop and submit a Quality Control Plan (QCP) for Government approval within 14 calendar days after contract award. Non-conforming services shall be rejected.
5.5. Unacceptable Performance: When performance is determined unacceptable, the Machine Shop
Supervisor or Government Representative will provide written documentation via Form DD 2772, Contract
Discrepancy Report. If services do not conform to contract requirements, the Government may require the
Contractor to re-perform the services at no increase in contract amount. If defects cannot be corrected by re-performance, the Government may:
5.5.1.1. Reduce the contract price to reflect the reduced value of the services.
5.5.1.2. Have the services performed by another party and charge the Contractor for incurred costs.
5.5.1.3. Issue a Cure Notice or Terminate the contract for Cause/Convenience.
5.6. Correction of Non-Performance: The Contractor shall employ adequate personnel to ensure any non-compliant area is made acceptable during the first business day after the noncompliance has been reported to and verified by the Government Representative.
Performance Objective Performance Standard Acceptable Quality Level (AQL) Surveillance Method
Disassembly, Inspection, &
CFR (PWS 3.1)
Thoroughly inspect bearings, pons, bushings, and rails on the overhead crane.
Accurately identify damaged parts and submit a complete
Condition Found Report
(CFR).
0% Deviation. 100% accurate identification of required repairs in the CFR prior to any repair work starting.
100% Review of CFR by
Government (Government
Representative/Machine Shop
Supervisor).
Repair & Assembly (PWS
3.2)
Manufacture or replace components strictly per the
KO-approved CFR and reassemble the overhead crane.
0 Instances of unauthorized work.
100% compliance with repairing only what is authorized in the CFR.
Periodic Visual Inspection by
Machine Shop Supervisor during the repair phase.
Operational Testing &
Restoration (PWS 3.3)
Crane operates smoothly during threading operations.
Equipment restored to full operational parameters.
100% Functionality. Zero (0) binding, jamming, or mechanical failures during final operational testing.
100% Visual and Operational
Functional Test observed by the
Machine Shop Supervisor prior to final acceptance.
6. Security Requirement:
6.1. General Security: The security requirements apply to all prime and subcontractor personnel. Contract personnel are critical to the overall security and safety of USACE installations. All personnel shall complete DoD/Army security initial training within 30 days of contract award. Within five (5) business days of completion, the Contractor shall provide written documentation to the Government representative.
Personnel and vehicles are subject to search when entering federal installations. Personnel shall comply with Force Protection Condition (FPCON) and Health Protection Condition (HPCON) measures.
6.2. Physical Security & Access Control: Contract personnel requiring unescorted access to a DoD installation shall be vetted by the Provost Marshal/Security Office using the NCIC-III and TSDB.
Personnel who do not meet requirements for unescorted access shall coordinate escorted access with the
Machine Shop Supervisor or Government Representative.
6.3. Escorting in Sensitive Areas: Personnel without appropriate security clearances will be escorted in areas where they may be exposed to sensitive information or restricted activities.
6.4. E-Verify Program: Contractors shall comply with FAR clause 52.222-54 Employment Eligibility
Verification, using the E-Verify Program (https://www.e-verify.gov/) to meet employment eligibility requirements. An initial list of verified candidates shall be provided to the Government Representative no later than three (3) business days after contract award.
https://www.google.com/url?q=https%3A%2F%2Fwww.e-verify.gov%2F
7. Subcontracting Requirements:
The Contractor shall notify the Machine Shop Supervisor or the KO in writing of any work to be subcontracted.
Compliance with the provisions of this contract by subcontractors remains the strict responsibility of the Prime
Contractor.
8. Point of Contact:
Technical Lead: Brandon Scherschel
Email: Brandon.Scherschel@usace.army.mil
Tel: (503) 808-5422
9. Invoice Submittal:
Upon satisfactory completion and acceptance of delivery, please submit an electronic PDF invoice to:
USACE Finance Center (Millington): cefc-g2invoices@usace.army.mil
Invoice submittal emails shall CC:
Brandon.Scherschel@usace.army.mil
Trista.M.Stark@usace.army.mil; and
Ian.K.Lutjens@usace.army.mil
For invoice receipt verification or for a vendor's Payment problem, the vendor may contact the USACE Finance
Center at Phone Number (901) 873-9077.
10. Contract Administration:
Contract will be administered by:
Department of the Army, Portland District, Corps of Engineers
P. O. Box 2946
Attn: CECT-NWP
Portland, Oregon 97208-2946