This document is a Performance Work Statement (PWS) Attachment E detailing Material Review Board (MRB) Exemptions dated 06 Dec 24, specifically for the T56 Series engine contract. The attachment outlines specific materials and components that are exempt from Material Review Board disposition by the government, which may be scrapped when they meet certain criteria and are beyond technical order overhaul reparable limits.
The exemptions cover multiple categories including: (a) materials under $5,000 replacement cost, (b) superseded material configurations like non-rub-tolerant T56-A15 turbine vanes and non-stiffened main diaphragms, (d) bearings, (e) electrical components rejected during testing with no rework criteria, (f) commercial off-the-shelf (CFM) materials excluding parts with life limits, and (g) common hardware like brackets, fasteners, seals, packings, and O-rings. The government retains the right to revise or update this list based on requirements, with deviations to MRB review requirements potentially identified by either the contractor or government and finalized by the Procuring Contracting Officer (PCO) or Administrative Contracting Officer (ACO).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T56 PWS ATTACHMENT E
Material Review Board Exemptions 06 Dec 24
NOTE: Government retains the right to revise or update this list based on Government requirements.
The following material is exempt from MRB disposition by the Government. It may be dispositioned to scrap when it is determined to meet the following criteria and be beyond T.O.
overhaul reparable limits by Contractor local engineering review The Government retains the right to amend the list below. Deviations to MRB review requirements may be identified by the Contractor or Government and finalized by the PCO/ACO.
(a) Material of less than $5,000 replacement cost
(b) Material configuration has been superseded, or replaced by improved configuration and listed below:
Non rub-tolerant 2nd and 3rd stage T56-A15 turbine vanes Non-stiffened main diaphragm Hastelloy C T56-A15 turbine vane cases Prop shaft seal and Nose bearing plate, P/N 6851491/6846127/6875798, and 6788467/6877391
(d) Bearings
(e) Electrical components rejected for electrical test criteria where no T.O. rework criteria is specified in applicable manuals
(f) Material is CFM, except for parts and assemblies with life limits.
(g) Common hardware; brackets, fasteners, etc. and 100% replacement items; e.g. seals, packings, O-rings, etc.