This Purchase Description Document outlines a solicitation (W50S8525QA006) for an overhead door replacement project at Selfridge Air National Guard Base (ANGB), Building 190. The project requires complete removal and replacement of a 12'W x 14'T overhead door and operator, with specific technical requirements including a rolling steel, insulated, flat slat door with vision lights, wind locks, and a galvanized door cowl/hood. The replacement door must be color-matched to the existing door, necessitating a site visit.
Additional key project specifications include a 115V, right-side drive operator to be wired by the contractor, a new operation switch with constant pressure down functionality, and complete replacement of all door seals. The contractor is responsible for supplying all necessary equipment, removing the existing door, and properly disposing of materials off-base (except for the old operator, which must be turned over to the government). A site visit is scheduled for Wednesday, 3 April 2025 at 2pm EST, with base access requiring submission of a request form at least 3 days prior. The government anticipates funds will become available no later than 30 September 2025, and the project will be managed by the Department of the Army Michigan Army National Guard.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SELFRIDGE ANGB BLDG. 190 OVERHEAD DOOR REPLACEMENT
PURCHASE DESCRIPTION DOCUMENT
SOLICITATION # W50S8525QA006
Bldg. 190 Overhead Door Replacement Supply Purchase and General Install
Complete removal and replacement of 12’W x 14’T and operator to include the following
-Replacement door must be rolling steel, insulated, flat slat door with vision lights, and wind locks.
-Door needs to be color matched to existing door. (Will require a site visit)
-Door cowl/hood must be galvanized.
-Replacement operator must be 115V, right side drive, and wired by contractor.
-New operation switch must operate with constant pressure down.
-All seals are to be removed and replaced to include bottom, sides, and top brush.
-Contractor needs to supply all the equipment needed to remove and replace the door.
-All material needs to be hauled away and disposed of properly off base, except for the operator.
Old Operator to be turned over to government upon completion of project.