This is a Project Statement from the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division for the Bay de Noc Community College Manufacturing Innovation Center (MIC) project. The project involves renovating the college's existing Shipping and Receiving Building and Welding building into a Manufacturing Innovation Center for the Central Upper Peninsula, with a proposal due date of Thursday, 08/28/25. A mandatory virtual pre-proposal meeting is scheduled for 08/12/25 at 2:30 ET, with an optional onsite walkthrough on 08/13/25. The renovation will modify the existing spaces to create a modular industrial space for collaboration and innovation, maintain the current welding instruction area, and serve as a Safety Training Center supporting OSHA and MIOSHA training.

The total project budget is fixed at $1,875,000, covering design, construction, and miscellaneous internal fees. The Professional Services Contractor (PSC) is responsible for designing the project within this budget using a design-bid-build delivery method. Proposal responses must be uploaded to SIGMA VSS, with firms encouraged to combine technical and cost proposals into a single attachment. The project timeline includes Programming and Schematic Design draft submissions in mid-February 2026, with final submittals expected by 03/13/26. Future phases are dependent on state funding and legislative approval. The project will comply with federal and state agency regulations and standards, including those from EPA, OSHA, DOT, DHHS, EGLE, DNR, and MIOSHA.

View the file

Other files for this state and local contract opportunity

Other files attached to 362/24390. CDP; BaydeNoc CC-Manufacturing Innov Ctr, newest first.
File Type Posted
Capital Outlay Design Manual.pdf PDF
RFP 24390.pdf PDF
Addendum 1 24390.pdf PDF
Addendum 2 24390.pdf PDF
MIC Concept Plans.pdf PDF
SAMPLE Billable Rate Contract (Rev 04-25).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0427 (R 10/22)

PROJECT STATEMENT

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET (DTMB)

State Facilities Administration (SFA), Design and Construction Division (DCD)

3111 West St. Joseph Street Lansing, Michigan 48909

FILE NUMBER

362/24390.CDP

PROPOSAL DUE DATE

Thursday, 08/28/25

PROJECT NAME

Bay de Noc Community College (Bay College) Manufacturing Innovation Center (MIC)

PROJECT ADDRESS

2001 N Lincoln Rd, Escanaba, MI 49829

CLIENT AGENCY CONTACT

Lynn Martinson

DTMB - DCD PROJECT DIRECTOR

Chris Parsons, parsonsc5@michigan.gov, 517-256-5677

WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION:

MANDATORY virtual pre-proposal meeting: 08/12/25 2:30 ET. For a Teams invite email parsonsc5@michigan.gov at least one business day before the meeting.

An OPTIONAL onsite walkthrough will be held for interested firms on 08/13/25 2:30 ET to review the site.

Please RSVP by emailing parsonsc5@michigan.gov at least two business days before the walkthrough so we will have an idea of who will be attending.

The walkthrough is only to provide access to the site and any questions arising from the visit are to be submitted in writing to be addressed.

PROJECT DESCRIPTION/SERVICES REQUESTED:

This project includes the renovation of Bay College’s existing Shipping and Receiving Building and Welding building into a Manufacturing Innovation Center (MIC) for the Central Upper Peninsula. Originally used as a diesel shop, the Shipping and Receiving building was constructed in 1974. A welding laboratory was added in 1989 with the original addition renovated in 2015 doubling the size of the welding lab. With the recent relocation of the machine tool equipment into the lab, as well as a growing demand from local manufacturers for customized manufacturing courses, the need for a MIC is significant to the region. The renovation will allow for welding instruction to remain as it currently exists, with modification of the existing Shipping and Receiving area to a reduced footprint, and the space gained to be utilized as modular industrial space for collaboration and innovation. This modular space would allow for the space to change as needed for the requested application. The MIC will fill a regional need to support the manufacturing sector by producing a highly skilled, trained and educated workforce critical to existing and future operations. The MIC will also serve as a Safety Training Center to support OSHA and MIOSHA trainings for construction and general industry, boot camp style trainings around safety to include but not limited to credential forklift operators, confined space training and industrial rigging.

The scope of the project will include new electrical and mechanical installs to support equipment, ventilation upgrades, lighting upgrades, mobile partitions for flexible space utilization, demolition of the existing office space, one new shipping office, interior finishes, industrial coating floor epoxy in new innovation center, an automated sprinkler system for fire suppression, an opening added between the existing welding area and the Manufacturing Innovation Center, and planning for covered storage over the existing stock storage yard, with an access door on this exterior wall, and also for building graphics.

The Capital Outlay Design Manual must be followed and is to be closely reviewed by the PSC for all requirements including the requirements for various submissions. The document is geared towards a mailto:parsonsc5@michigan.gov

College/University self-managing the project but for this project DTMB-SFA-DCD will be working for Bay College and managing the project and holding the contracts.

Phase I Environmental Survey and Hazardous Material Survey are not part of this scope and will be contracted for directly by Bay College.

For proposal purposes the PSC is to assume a design-bid-build delivery method.

Total project budget is fixed at $1,875,000 (inclusive of design, construction, and miscellaneous internal fees). The Professional Services Contractor (PSC) is responsible for designing a project within the stated budget.

Please NOTE:

• Proposal responses MUST be uploaded to SIGMA VSS. Please enter the total cost for all phases as the bid amount.

• Firms are encouraged to combine their technical and cost proposals into one (1) attachment for proposal submission.

• Please remember that attachments can be no larger than 25mb.

• Do not wait until just before the 2:00 p.m. solicitation deadline to submit your proposal response.

SIGMA VSS will not allow a proposal to be submitted after 2:00 p.m., even if a portion of the proposal response has been uploaded.

• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m., solicitation deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749. You may also email the SIGMA Help Desk at sigma-procurement-helpdesk@michigan.gov

• Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).

• You may be asked by our contract specialists to email your proposal. Emailed submissions will require DCD approval and will be handled on a case-by-case basis.

• Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.

• Responses should not be emailed to the Project Director.

NIGP CODES

90607, 90610, 90638, 92507, 92531, 92533, 92567

DESIRED SCHEDULE OF WORK

Programming (Phase 200) and Schematic Design (Phase 300) draft design submissions per the Capital Outlay Design Manual are to be submitted in mid-February 2026 with the expectation that final submittals will be ready by 03/13/26. Future phases (final design & construction) are dependent upon the availability of state funding which requires legislative approval.

ACCEPTING RFP QUESTIONS UNTIL:

Please do not submit online questions via VSS. ALL questions should be emailed to Chris Parsons at parsonsc5@michigan.gov address no later than 2:00 p.m., Eastern on 08/19/25.

REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers' safety rules that are administered by federal agencies (EPA, OSHA, and DOT), state agencies (DHHS, EGLE, DNR, and MIOSHA), and any other local regulations and standards that may apply.

This form is required to be a part of the professional service contract. (Authority: 1984 PA 431)

Attachments:

1. Request for Proposal

2. MIC Concept Plans

3. Capital Outlay Design Manual mailto:sigma-procurement-helpdesk@michigan.gov mailto:WatrosA@michigan.gov mailto:KleinD4@michigan.gov

File details come from the government source that posted it. Updated .