Project_Specifications.pdf
PDF 995 KB Posted
- Attached to
- JAGA Intrusion & Fire Alarm System Installation Federal contract opportunity
- Solicitation number
- 140P6424B0008
About this file
This document is a solicitation notice for an Invitation for Bids (IFB) for an Intrusion & Fire Alarm System Installation project at the James A. Garfield National Historic Site in Lake County, OH. The scope of work includes removing and replacing the existing fire and intrusion alarm systems in nine buildings, installing new surveillance cameras, and laying new CAT-6 and fiber-optic cable. The project is estimated to cost between $250,000 and $500,000 and will be awarded as a firm-fixed price contract to the responsive, responsible bidder offering the lowest aggregate price. The contract is set aside for small businesses under NAICS code 238210. Bids are due by 12:00 PM ET on August 21, 2024, and a site visit is scheduled for July 30, 2024. Award is expected in August 2024 with a 270-day period of performance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Schedule.xlsx | XLSX spreadsheet | |
| Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Construction_Contract_Administration.pdf | ||
| Suggested_Products.pdf | ||
| Sol_140P6424B0008.pdf | ||
| Drawings.pdf | ||
| WD_-_Lake_County__OH.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2022-9-6 Page | 1
JAMES GARFIELD
NATIONAL HISTORIC SITE
MENTOR, OHIO
INSTALL NEW INTRUSION & FIRE ALARM SYSTEM
PMIS 319395
Drawing No: 487/80010
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
12/01/2023
Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 DIVISION 01 SHORT FORM GENERAL REQUIREMENTS
01 15 00 CUTTING AND PATCHING
DIVISION 6 – WOOD, PLASTIC AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 92 00 JOINT SEALENTS
DIVISION 9 – FINISHES
09 90 00 PAINTING
DIVISION 26 - ELECTRICAL
26 0400 COMMON REQUIREMENTS FOR ELECTRICAL
26 0519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND
CABLES
26 0526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 0529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 0534 CONDUIT
26 0537 BOXES
26 0553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 2726 WIRING DEVICES
DIVISION 27 - COMMUNICATIONS
27 0501 COMMON WORK RESULTS FOR COMMUNICATIONS
27 0527 GROUNDING AND BONDING FOR COMMUNICATIONS
SYSTEMS
27 0528 PATHWAYS FOR COMMUNICATIONS
27 0553.01 IDENTIFICATION FOR COMMUNICATIONS SYSTEMS
27 1323 COMMUNICATIONS OPTICAL BACKBONE CABLING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 0500 COMMON WORK RESULTS FOR ELECTRONIC SECURITY
28 1600 INTRUSION DETECTION SYSTEM
28 2300 ELECTRONIC VIDEO SURVEILLANCE SYSTEM
28 3101 WIRELESS FIRE DETECTION AND ALARM
28 4600 FIRE DETECTION AND ALARM
DRAWINGS
UNDER SEPARATE COVER
Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: This project will provide a design to remove and replace the fire and intrusion alarm systems at JAGA. This project will remove all devices of the fire/intrusion system and replace with new technology. Over two hundred and twenty-five devices and their associated wiring will be replaced. Panels (intrusion/alarm) and associated wiring will be replaced. Surveillance cameras will be installed with new closed circuit monitoring technology and devices. Project includes new Cat 6 cable and fiber optic cable installed underground. New components will be placed in the same locations as old components. The design shall include a system interface that will be installed/coordinated with the Cuyahoga Valley National Park Communication Center. New system must also satisfy curatorial requirements for the building’s museum collections, artifacts, and exhibits.
1.2 Work Covered by the Contract Documents:
A. Project Location: James Garfield National Historic Site, 8095 Mentor Ave., Mentor, Ohio 44060.
B. Work consists of:
1. The existing fire alarm system and intrusion alarm system will be removed and a wireless fire alarm system and a wireless intrusion alarm system will be provided in the nine (9) buildings listed below:
• Visitor Center Carriage House/Gas Holder; national register listed
• Tenant House; national register eligible
• Horse Barn; national register listed
• Main House; national historic landmark
• Campaign Office
• Windmill
• Grainery
• Maintenance Building
• Comfort Station
2. Surveillance cameras will be installed with new closed circuit monitoring technology and devices.
3. Selective work to provide a finished project such as cutting, patching, and painting.
C. All work will be performed under a single contract.
Page | 4
D. Period of performance: Work shall be completed within 270 calendar days of the start date provided on the Notice to Proceed.
ITEM 2 – PROTECTING EXISTING UTILITIES
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
Superintendent’s Compendium – James A. Garfield National Historic Site (U.S. National Park Service)(nps.gov)(https://home.nps.gov/jaga/learn/management/superintendent-s-compendium.htm)
A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of
Page | 5 the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan (see Drawings). Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Define site disturbance area, including earthwork and clearing of vegetation, to:
1. 25 feet around areas used for boring machines.
2. 10 feet beyond utility trenches.
3. 10 feet around areas at new in-ground pull boxes.
4. 10 feet around machine or hand dug holes used for utility placement.
D. Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction where directed to do so by the
CO/COR.
E. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Page | 6
2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Waste Operation:
a. Toilets: Contractor shall be able to use the existing restroom facilities at the Visitor’s
Center. The restroom facilities shall be kept in immaculate condition. At the discretion of Park personnel and/or COR; contractor may lose the use of the restroom facilities if they are not kept clean and orderly. Restroom use will be a “one strike and you’re out” policy.
1. If restroom privileges are revoked Contractor will be required to provide a toilet for contracting personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location.
b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.
F. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees impacted in construction area. Coordinate with COR. Restore damaged areas to original condition, repairing or replacing damaged trees and plants, at no additional expense to the Government.
a. Provide temporary barriers to protect existing trees and plants and root zones.
b. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.
c. Do not fasten ropes, cables, or guys to trees.
d. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
Page | 7
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Provide temporary enclosures such as orange snow fence as required for protection of construction in progress and completed, from access by visitors or staff, other construction operations, and similar activities.
3.4 Storage - Staging Areas:
A. Confine storage of materials and equipment to the project staging area. Specific storage and staging areas will be discussed at the preconstruction briefing.
B. CO/COR will designate a location on-site for a contractor provided 20’ conex container for on-site secured storage. Staging will be adjacent to the container. Container shall be in good and suitable condition. CO/COR and the Park reserve the right to request the Contractor to provide a different container if the condition of the container isn’t suitable.
C. Storage within a park-controlled building is at the discretion of the CO/COR and the Park.
Limits of use and control shall be subject to CO/COR approval.
D. Schedule deliveries prior to 10:00 am to minimize impact on visitors and the public.
3.5 Preservation of Natural Features: N/A.
3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.
3.7 Housekeeping:
A. Keep project neat, orderly, and in a safe condition at all times.
1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters
2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
Page | 8
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
c. Contractor will coordinate access to and work in curated spaces with the CO/COR.
Curated spaces may require Contractor’s personnel to be escorted by NPS staff and/or prior (daily) notification submitted to the CO/COR before working in those spaces.
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email or via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
Page | 9
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and Park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Noise Control: Perform all operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items viewable during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.nps.gov/orgs/1671/do-business-with-us.htm
Page | 10
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
Page | 11
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain two sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR.
B. Submittal List: Administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
Page | 12
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan.
9. Historic Preservation Treatment Plan Submitted to CO/COR
10. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
9.2 Project Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all color and product selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and
Page | 13 level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that Contractor:
1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
2. Will provide the same warranties for the proposed item as for the item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall
Page | 14 equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
Page | 15
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXCUTION (NOT USED)
END OF SECTION
JAGA 319395 06 10 00-1
DIVISION 6 – WOOD, PLASTIC AND COMPOSITES
SECTION 06 10 00
ROUGH CARPENTRY
PART 1 - GENERAL
1.1 RELATED WORK SPECIFIED ELSEWHERE
1.2 REFERENCES
1.3 QUALITY ASSURANCE
A. Comply with PS 20 and with applicable rules of the respective grading and inspecting agencies for species and products indicated. Comply with PS 1-74 (ANSI 199.1) or, for products not manufactured under PS 1-74 provisions, with applicable APA Performance Standard for type of panel indicated. Identify each plywood panel with the appropriate APA Trademark. All stress grades and stress criteria shall be based on the National Design Specifications for Wood Construction, latest edition.
1.4 SUSTAINABILITY REQUIREMENTS
A. Adhesives and sealants that comply with the following requirements:
1. Adhesives, sealants and sealant primers must comply with the South Coast Air Quality
Management District (SCAQMD) Rule #1168, which limits their VOC content by product type.
2. Aerosol adhesives must comply with Green Seal Standard for Commercial Adhesives GS-36 requirements in effect October 19, 2000.
1.5 STORAGE
A. Store rough carpentry materials on bunks or skids at least 6 inches above the ground, and protect materials from weather with waterproof covers.
1.6 JOB CONDITIONS
A. Fit carpentry work to other work; scribe and cope as required for accurate fit. Correlate location of furring, nailers, blocking, grounds, and similar supports to allow proper attachment to other work.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Lumber shall be S4S, kiln dried, with 19 percent maximum moisture content at time of dressing. Lumber shall be grade stamped in accordance with the latest edition of the standard grading rules of NELMA, SPIB, WCLIB, WWPA or NLGA (or equivalent Canadian governing authority).
2.2 MISCELLANEOUS
A. Electrical/Telephone Backing Panels: C-D Plugged, Exposure 1 plywood, fire-retardant treated, ¾-inch thick.
B. Planks and wood used for cabinet: Sanded Pine PSE/PAR. Grade stamps shall not be visible to the outside of the cabinet. Cabinet’s exterior door panels are to be made with planks of the same width.
C. Miscellaneous panels: C-D Plugged, Exposure 1 plywood, fire-retardant treated, 5/8-inch thick
2.3 MISCELLANEOUS MATERIALS
JAGA 319395 06 10 00-2
A. Fasteners and anchorages shall be of the size, type, material and finish as indicated below or on the Drawings and as recommended by applicable standards complying with applicable Federal Specifications for nails, (staples), screws, bolts, nuts, washers and anchoring devices. Metal anchors shall be of the size and type recommended by the manufacturer for each use. Where rough carpentry work is exposed to the weather, in ground contact, or in areas of high humidity, provide fasteners and anchorages with a hot-dip zinc coating (ASTM A 153).
B. Adhesives shall conform to Specification AFG-01 of the American Plywood Association.
C. Cabinet fasteners: Contractor shall use square head nails for fastening wood members and slotted screws for the hardware.
D. Electrical Cabinet Hardware: Provide black 6” heavy-duty T-hinges and black surface bolts for the electrical cabinets.
PART 3 - EXECUTION
3.1 MISCELLANEOUS WOOD BLOCKING
A. Erect miscellaneous blocking as shown on the Drawings or as required to secure materials to rough construction.
3.2 CONCEALED BLOCKING
A. Wood blocking shall be nominal 2" thick and secured to structural members for the anchorage of all surface-mounted items. Blocking shall be provided and installed as recommended by the manufacturer of the product to be mounted on the wall/ceiling. Blocking shall be installed for, but not limited to, the following items:
1. Security and fire alarm panels and other wall/ceiling mounted items to be mounted in new construction.
2. As needed, security and fire alarm panels and other wall/ceiling mounted items to be mounted in existing construction.
3.3 INSTALLATION OF TREATED WOOD
A. Provide pressure-treated wood where framing lumber is in contact with concrete or masonry. Field cuts shall be coated with a concentrated solution of preservative treatment.
3.4 ALLOWABLE TOLERANCES
A. The following tolerances establish the range of acceptable variances. Assure that work outside this range is removed; act to prevent reoccurrence.
1. Lumber
a. Straightness, no bows exceeding 0.1%, i.e., 1/8-inch in 10 feet, 1/16-inch in 5 feet.
b. No twisted or split lumber allowed.
c. Moisture content not to exceed 14% when installed.
JAGA 319395 07 92 00-1
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
SECTION 07 92 00
JOINT SEALERS
1.1 RELATED WORK SPECIFIED ELSEWHERE
Joint Sealers in Electrical and Communications Work Divisions 26, 27 & 28
1.2 SUSTAINABILITY REQUIREMENTS
A. For field applications that are inside the weatherproofing system, use adhesives and sealants that comply with the following requirements:
1. Adhesives, sealants and sealant primers must comply with the South Coast Air Quality
Management District (SCAQMD) Rule #1168, UL2818 (Greenguard) Gold or Scientific Certification Systems Global Services Indoor Advantage Gold.
1.3 GENERAL PERFORMANCE
A. Joint sealers, except as otherwise indicated, are required to establish and maintain airtight and waterproof continuous seals to the substrates they will be applied to in this project on a permanent basis, within recognized limitations of wear and aging as indicated for each application. Failures of installed sealers to comply with this requirement will be recognized as failures of materials and workmanship.
B. Sealants shall be compatible for use with each joint substrate used on this project in accordance with sealant manufacturer’s documented recommendations for each application.
1.4 SUBMITTALS
A. Color samples shall be submitted in accordance with Section 01 33 23. Samples shall be strips of actual caulking. Paper samples will not be acceptable.
B. Submit test reports indicating compatibility of joint sealers with exact materials being used on this project in accordance with Section 01 33 23.
1.5 JOB CONDITIONS
A. Sealants shall be installed on dry days preferably with temperatures between 40 deg. F and 75 def. F, but in no case shall sealants be installed when temperatures are below 40 deg. F or above 90 deg. F.
B. Special care shall be exercised to prevent damage to adjacent work during installation of sealants.
C. Sequencing:
1. Install sealant adjacent to painted surfaces before adjacent surfaces receive their final coat of paint.
2.1 SEALANTS
A. Multi-Purpose Silicone Sealant (Type S-1):
1. Pecora Corp.: PCS
2. BASF/Sonneborn:
JAGA 319395 07 92 00-2
3. Sika Corp: Sika WS-305 CN
4. Dow Corning: CWS Contractors Weatherproofing Sealant
B. Acrylic-Emulsion Sealant (Type S-2):
1. Pecora Corp: AC-20
2. Sika Corp: Acrylic
3. Tremco, Inc.: Tremflex 834
C. Mildew-Resistant Silicone Sealant (Type S-4):
1. Pecora Corp.: 860
2. General Electric: SCS 1700
3. Sika Corp: Sika Sil N Plus
4. Tremco: Tremsil 200
5. Dow Corning: 786 Mildew Resistant
D. Mildew Resistant Neutral Curing Silicone Sealant (Type S-4A):
1. Pecora: 898 NST
E. Urethane Sealant for Joints Subjected to Traffic (Type S-5):
1. Pecora Corp.: NR-21
2. Sika Corp: Sika Flex 1C SL
3. Tremco: Vulkem 45SSL
4. BASF/Sonneborn: MasterSeal SL 1
F. Silicone Sealant for Joints Subjected to Traffic (Type S-5A)
1. Pecora Corp.: 300 SL, 301 NS
2. Tremco: 900, 800
3. Dow Corning: 890 SL, 888 NS
G. Firestopping sealant (Type S-7) for use at all penetrations through fire-rated walls, at tops of such walls, and at smoke-resistance-rated floors and walls shall be CP25WB Sealant, MPS-2 and MMP-4S putty and other accessories as manufactured by 3M Corp., or equivalent products manufactured by RectorSeal Corporation, Bio Fireshield, Tremco, Specified Technologies, Johns Manville, or United States Gypsum Co. Provide proper product at each appropriate location.
H. Acoustical sealant (Type S-8) for use at certain GWB partitions (as shown on Drawings) shall be one-component, Butyl Rubber Base sealant, aluminum gray color, and shall be Acoustical Sealant BA-98 manufactured by Pecora Corporation, or approved equal.
2.2 SEALANT LOCATION TYPE
S-1 Exterior, except joints subject to traffic S-2 Interior, except expansion joints in exterior walls and as noted below S-4 Interior joints around plumbing fixtures and countertops S-4A Interior joints around plumbing fixtures and countertops S-5 Joints subject to traffic S-5A Joints subject to traffic S-7 For firestopping at fire-rated construction S-8 At penetrations thru sound-resistant construction
2.3 MISCELLANEOUS MATERIALS
A. Provide the sealant manufacturer's recommended type of joint primer for joint surfaces to be primed.
Verify with the sealant manufacturers which materials require priming for each of the sealants used.
B. Bond breaker, where required to break the bond between sealant and the back-up material or joint filler, shall be a tape material recommended by the sealant manufacturer, or shall be polyethylene film.
JAGA 319395 07 92 00-3
C. Provide glass fiber roving, neoprene, butyl, polyurethane, or polyethylene foams free from oil or other staining elements as recommended by sealant manufacturer. Provide 25 to 33 percent oversized backing for closed cell material and 40 to 50 percent oversized backing for open cell material, unless otherwise indicated. Provide backstop material that is compatible with sealant. Do not use oakum or other types of absorptive materials as backstops.
D. Cleaning solvents shall be type(s) recommended by the sealant manufacturer and in accordance with applicable environmental requirements. Protect adjacent glass, aluminum and bronze surfaces from solvents.
3.1 INSPECTION
A. Installer must examine substrates (joint surfaces) and conditions under which joint sealer work is to be performed, including joint width tolerances, and must notify Contractor in writing of unsatisfactory conditions. Do not proceed with joint sealer work until unsatisfactory conditions have been corrected in a manner acceptable to installer.
3.2 PREPARATION
A. Clean down joint surfaces using oil-free solvent for metal, glass, and other non-porous surfaces.
Surfaces to receive sealant shall be sound, clean and dry, and free of frost, laitance, curing compounds, waterproofing compounds, mastic compounds, corrosion, mill scale, rust, oil, tar, wax, paint, mastic, and similar contaminates.
B. Sandblast concrete in contact with form release agents.
C. Prime concrete, masonry, wood and similar porous surfaces. Brush out excess material to ensure a uniform film over the joint face. Allow primer to dry out before applying sealant.
D. Mask adjacent areas as necessary to obtain a neat sealant line.
3.3 INSTALLATION
A. Comply with the manufacturer's documented instructions except where more stringent requirements are shown or specified, and except where manufacturer's technical representative directs otherwise.
B. Mix two-part sealants by mixing the activator with the resin uniformly and thoroughly, in the proportions supplied to meet the recommendations of the sealant manufacturer. Sealant shall be mixed in a mechanical mixer, except very small amounts may be hand mixed with a trowel.
C. Clean out loose particles from joints immediately prior to application of primer. Apply primer to joints in concrete masonry units, wood, and other porous surfaces in accordance with sealant manufacturer’s documented instructions. Do not apply primer to exposed finished surfaces.
D. Install backer rod with a blunt rod or plain faced roller. Recess into joint to meet the sealant manufacturer's recommendations for joint width and depth ratio. Do not puncture, fold, twist, or crease backer rod.
E. Install bond breaker where sealant would otherwise bond to backer rod or joint filler.
F. Do not allow sealants or compounds to overflow from confines of joints, to spill onto adjoining work, or to migrate into voids of exposed finishes. Clean adjoining surfaces by whatever means may be necessary to eliminate evidence of spillage.
JAGA 319395 07 92 00-4
G. Install sealants in uniform, continuous ribbons without gaps or air pockets, with complete "wetting" of joint bond surfaces equally on opposite sides. Except as otherwise indicated, fill sealant rabbet to a slightly concave surface slightly below adjoining surfaces.
H. Where horizontal joints are between the horizontal surface and vertical surface, fill joint to form a slight cove, so that joint will not trap moisture and dirt.
I. Apply non-self-leveling sealants by holding the gun nozzle at an angle of about 45 degrees and move steadily along the joint so that a uniform bead is applied without dragging, tearing, or leaving unfilled spaces. Push the bead rather than draw it with the gun leading. Fill joints in vertical surfaces level with adjacent surfaces and tool within ten minutes of application with one continuous stroke to insure intimate contact with the joint surfaces, to remove any trapped air or voids, to consolidate material, and to provide a neat, uniform, appearance. Fill joints in horizontal surfaces holding the top surface of the sealant slightly below the adjacent surfaces.
J. Install self-leveling sealants to a depth equal to 75 percent of joint width but neither more than 5/8-inch deep or less than 3/8-inch deep as recommended by sealant manufacturer. Pour sealant into joints and fill to within 1/16-inch of adjacent surfaces, exercising care not to spill sealant on such surfaces. Refill any areas where sealant seeps out of joint through the expansion joint filler before sealant sets up.
3.4 CLEANING AND PROTECTION
A. Remove masking immediately after application and tooling operations are complete. Clean excess or spilled sealant from non-porous surfaces with solvent before curing. Clean excess or spilled sealant from porous surfaces with abrasive or mechanical means after curing.
B. Protect sealant where bituminous material is to be applied over thermosetting joint sealant with vinyl or polyethylene sheet material.
C. Cure sealants in compliance with manufacturer's instructions and recommendations to obtain high early bond strength, internal cohesive strength and surface durability. Advise Contractor of procedures required for cure and protection of joint sealers during construction period, so that they will be without deterioration or damage (other than normal wear and weathering) at time of Substantial Completion.
Replace or restore sealants which are damaged or deteriorated during construction period.
3.5 SCHEDULE OF SPECIAL SEALANT COLORS
A. Special sealant colors shall be as follows:
At perimeter of exterior wall openings Match adjacent colors At joints between wall & other surfaces Match wall color At miscellaneous locations shown on the Drawings Standard color to most closely match adjacent colors
JAGA 319395 09 29 00-1
SECTION 09 29 00
GYPSUM DRYWALL
1.1 WORK SPECIFIED
A. Use gypsum drywall where required to patch/repair existing abandoned, new &/or modified openings in interior gypsum walls & ceilings.
1.2 QUALITY ASSURANCE
A. On faces of work exposed in occupied spaces, limit offsets between planes of board faces to 1/8-inch, and limit variations from plumb and location (including warp and bow) not to exceed 1/4-inch in 8'-0".
1.3 SUSTAINABILITY REQUIREMENTS
B. Use adhesives and sealants that comply with South Coast Air Quality Management District (SCAQMD) Rule #1168, which limits their VOC content by product type.
1.4 DELIVERY, STORAGE AND HANDLING
A. Gypsum drywall shall not be delivered to the project site until immediately before application begins. All gypsum drywall materials shall be delivered in original packages, containers or bundles bearing brand name and identification nomenclature.
B. Gypsum drywall shall be stored inside under cover and stacked flat in a manner to keep material flat, dry, protected from weather, direct sunlight, surface contamination, traffic or other construction damage.
Other materials and accessories shall remain in their original wrappings or containers, stored flat and protected from weather damage and bending until ready for actual use.
C. Handle materials in a manner to prevent damage to edges, ends or surfaces. Damaged materials or accessories shall not be incorporated within the work and shall be immediately removed from the site.
1.5 JOB CONDITIONS
A. Comply with requirements of…