Project Schedule-WCCC New Access Road Project Schedule.pdf

PDF 193 KB Posted

Attached to
WCCC New Access Road
Solicitation number
B27000435
Issued by
Honolulu County, Hawaii

About this file

This is a project schedule document for the WCCC New Access Road project managed by the Hawaii Department of Corrections and Rehabilitation (DCR). The project involves the installation of a new delivery and construction access road for the Women's Community Correction Center. A prebid meeting is scheduled for October 1, 2026, at 10:00 AM, with prebid requests for information due by October 14, 2026, at 5:00 PM. Bids are due on October 30, 2026, at 5:00 PM, with a Notice of Award expected on November 6, 2026. The contract duration is 180 calendar days, with the project start date (PO Issuance/NTP) on November 13, 2026, job site mobilization on January 4, 2027, and project acceptance on May 12, 2027. A 60-calendar-day closeout period follows project completion.

Key procedural milestones include one week for DCR to evaluate bids, one week for the contractor to submit required documentation (W-9, HCE, and sample invoice), and one week for DCR to process the purchase order. The project schedule allocates four weeks for construction submittal review and two weeks for preconstruction meetings. The bid documents were issued on September 21, 2026, with responses to requests for information and any addenda due by October 21, 2026. Notably, the schedule indicates that HECO utility pole relocation must occur prior to construction commencement. Thanksgiving (November 26, 2026) is noted as a consideration during the contract award and mobilization period.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milestone Date/Time Notes

Issue Bid Docs 9/21/26, Mon 5 PM DCR to upload to HIePRO.

Prebid Meeting 10/1/26, Thurs 10

AM

Prebid RFIs Due 10/14/26, Wed 5 PM

RFIs Response / Addendum Due

10/21/26, Wed 5 PM

Bids Due 10/30/26, Fri 5 PM

Notice of Award 11/6/26, Fri 5 PM Approximate.

Contract Duration 180 Calendar Days Reference Specification Section

00410 Attachment A.

PO Issuance / NTP / Contract Start

11/13/26, Fri 5 PM Approximate.

Job Site Start/Mobilization

1/4/27, Mon Approximate.

Project Acceptance Date

5/12/27, Wed Approximate.

Closeout Period 60 Calendar Days Submit final Pay App and closing docs per IGC 7.33.2.

DCR 24-WCCC-0016 WO39 WCCC New Access Road Project Schedule

1 week to evaluate bids.

1 week for contractor to submit W-9, HCE, sample invoice for PO. Reference 00210-1.09. Start pre-con meeting schedule discussions and pre-construction submittals preparation.

1 week for DCR to cut the PO.

4 weeks for construction submittal review. (2 weeks to submit, 1 week to review, 1 week for resubmittals).

2 weeks to conduct pre-con meeting. Thanksgiving on Thursday, 11/26/26.

Note that HECO utility pole should be relocated prior to construction.

WO39 WCCC New Access Road Job No. DCR 24-WCCC-0016 Page 1 9/18/2026

Barry Rouse Cross-Out

File details come from the government source that posted it. Updated .