This is a Project Manual for the Roberson Museum Office Renovation located at 30 Front Street, Binghamton, New York, issued for permit on August 28, 2026. The document, prepared by Stantec Architecture Inc., serves as the comprehensive specification and administrative guide for the renovation project, which encompasses HVAC system modernization, planetarium link renovations, and green initiatives. The manual includes detailed sections on general procurement and contracting requirements, administrative procedures, quality assurance standards, and technical specifications for construction work including cold-formed metal framing, decorative formed metal, exterior insulation and finish systems, sheet metal flashing, glazing, and joint sealants. The project is identified by multiple funding and project identifiers including DASNY Project IDs 27539 and 27126, NYSCA project numbers, and various grant fund references. Key administrative requirements include mandatory use of an electronic document submittal service (Newforma ConstructEx), preconstruction and site mobilization meetings, bi-monthly progress meetings, and a comprehensive submittal and RFI process with specified review timelines of seven calendar days for RFIs and fifteen days for submittal reviews.
The manual establishes strict quality control protocols requiring independent testing agencies, professional engineer design services and seals for specified work, mock-up approvals, and compliance with referenced standards including AISI, ASTM, AWS, and ICC building codes. All submittals must be prepared electronically in PDF format with contractor certification stamps. Substitution requests are permitted only within specific timeframes: ten days prior to bid for procurement phase substitutions and thirty days after the Agreement date for construction phase substitutions, with detailed justification and supporting documentation required. The document includes mandatory preinstallation meetings, detailed tolerance requirements, and specifies that contractors must provide qualified personnel for welding operations with current AWS certifications. Special requirements include protection of existing utilities, hazardous materials discovery protocols, and coordination with the Project Coordinator, who is designated as the General Contractor. The contract emphasizes that cost for the electronic submittal service must be included in the Contract Sum, and all work must comply with the specified reference standards and manufacturer instructions, with conflicts to be resolved through RFI procedures before work commences.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Manual
ROBERSON MUSEUM
OFFICE RENOVATION
30 FRONT STREET
BINGHAMTON, NY 13905
ISSUED FOR PERMIT
08/28/2026
Prepared by:
STANTEC ARCHITECTURE INC.
dba Stantec Architecture and Engineering
600 GRANT STREET SUITE 4940
PITTSBURGH, PA 15219
Project: 218012249
Project identifiers:
ESD Project No. 139,490 / CFA No. 146313 DASNY Project ID 27539 – Modernization of HVAC System DASNY Project ID 27126 – Renovations to Link Planetarium GRG Project No. 2257 / CWSRF Project No. 9268-01-00 – Roberson Museum Green Initiative NYSCA C251110GM – Roberson Museum Modernization: Design Phase Initiative NYSCA C261071GM – Critical HVAC Modernization ZBGA C24ZC945GM – ZBGACap – HVAC Project ZBGA 25130 – Museum Rehabilitation Project
ROBERSON MUSEUM
BINGHAMTON, NY
STANTEC PROJECT NO. 218012249
REVISION 00
DOCUMENT 00 00 02 - TABLE OF CONTENTS
IS
S
U E
F O
R
P E
R M
IT
Division Section Title CURRENT
VERSION
REVISION
08.28.2026
00 00 02 TABLE OF CONTENTS 00 00
00 00 05 PROFESSIONAL SEALS 00 00
01 25 00 SUBSTITUTION PROCEDURES 00 00
01 25 00a SUBSTITUTION REQUEST FORM INSTRUCTIONS 00 00 01 25 00b SUBSTITUTION REQUEST FORM 00 00
01 30 00 ADMINISTRATIVE REQUIREMENTS 00 00
01 30 00a ELECTRONIC EXCHANGE AGREEMENT 00 00 01 30 00b RFI FORM 00 00 01 30 00c SUBMITTAL REVIEW FORM 00 00
01 40 00 QUALITY REQUIREMENTS 00 00
01 60 00 PRODUCT REQUIREMENTS 00 00
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION 00 00
DIVISION 05 - METALS
05 40 00 COLD-FORMED METAL FRAMING 00 00
05 57 00 DECORATIVE FORMED METAL 00 00
DIVISION 07- THERMAL AND MOISTURE PROTECTION
07 24 00 EXTERIOR INSULATION AND FINISH SYSTEM 00 00
07 62 00 SHEET METAL FLASHING AND TRIM 00 00
07 92 00 JOINT SEALANTS 00 00
DIVISION 08- OPENINGS
08 44 13 GLAZED ALUMINUM CURTAIN WALLS 00 00
08 80 00 GLAZING 00 00
END OF TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 01 – GENERAL REQUIREMENTS
TABLE OF CONTENTS 000002 - 1
ROBERSON MUSEUM_OFFICE RENOVATION REVISION 00
STANTEC PROJECT NO. 218012249
PROFESSIONAL SEALS 00 00 05 - Page 1 of 1
DOCUMENT 00 00 05 - PROFESSIONAL SEALS
ARCHITECT
STANTEC PROJECT NO. 218012249
SUBSTITUTION PROCEDURES 01 25 00 - 1
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Procedural requirements for proposed substitutions.
1.02 RELATED REQUIREMENTS
A. Section 01 30 00 - Administrative Requirements: Submittal procedures, coordination.
1.03 DEFINITIONS
A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.
1. Substitutions for Cause: Proposed due to changed Project circumstances beyond
Contractor's control.
a. Unavailability.
b. Regulatory changes.
2. Substitutions for Convenience: Proposed due to possibility of offering substantial advantage to the Project.
a. Substitution requests offering advantages solely to the Contractor will not be considered.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 GENERAL REQUIREMENTS
A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:
1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.
2. Agrees to provide the same warranty for the substitution as for the specified product.
3. Agrees to provide same or equivalent maintenance service and source of replacement parts, as applicable.
4. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.
5. Waives claims for additional costs or time extension that may subsequently become apparent.
6. Agrees to reimburse Owner and Architect for review or redesign services associated with re-approval by authorities.
STANTEC PROJECT NO. 218012249
SUBSTITUTION PROCEDURES 01 25 00 - 2
B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.
1. Note explicitly any non-compliant characteristics.
C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.
1. Forms included in the Project Manual are adequate for this purpose, and must be used.
D. Limit each request to a single proposed substitution item.
1. Submit an electronic document, combining the request form with supporting data into single document.
3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT
A. Submittal Time Restrictions:
1. Owner will consider requests for substitutions only if submitted at least 10 days prior to the date for receipt of bids.
B. Submittal Form (before award of contract):
1. Submit substitution requests by completing the form attached to this section. See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.
3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION
A. Submittal Form (after award of contract):
1. Submit substitution requests by completing the form attached to this section. See this section for additional information and instructions. Use only this form; other forms of submission are unacceptable.
B. Architect will consider requests for substitutions only within 30 days after date of Agreement.
C. Submit request for Substitution for Cause immediately upon discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Architect, in order to stay on approved project schedule.
D. Substitutions will not be considered under one or more of the following circumstances:
1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.
2. Without a separate written request.
3. When acceptance will require revisions to Contract Documents.
3.04 RESOLUTION
A. Architect may request additional information and documentation prior to rendering a decision.
Provide this data in an expeditious manner.
B. Architect will notify Contractor in writing of decision to accept or reject request.
1. Architect's decision following review of proposed substitution will be noted on the submitted form.
STANTEC PROJECT NO. 218012249
SUBSTITUTION PROCEDURES 01 25 00 - 3
3.05 ACCEPTANCE
A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.
3.06 CLOSEOUT ACTIVITIES
A. Include completed Substitution Request Forms as part of the Project record.
END OF SECTION
SUBSTITUTIONS REQUEST INSTRUCTIONS
1. Complete this form in its entirety. All requested information is required. Attach all supporting documents which are required for review to the submittal. The complete document package is to be submitted electronically in PDF format. Where technical documentation or electronic media will be required for review, include with the submittal. Incomplete documents will not be considered.
2. For each product or system proposed for consideration: Provide a complete package of information for review, equivalent to a “product data + shop drawings submittal” as a minimum‐ provide additional documentation as required to perform a complete review of the proposed substitution. Provide a summary on the cover of the submittal indicating the number and type of documents included for review. Incomplete submittal documents will not be considered.
3. Indicate on the submittal documents conformance with the specified requirements, as well as any proposed deviations or revisions to the referenced specification(s) for the product or system. Include a copy of the specification, manufacturers recommended specification, or other technical documentation which supports the proposal. Deviations or revisions which would reduce or limit the number of possible providers for a specified system or product are generally not considered.
4. Additional information may be required to process a Substitution Request. Suppliers/ Contractors will be notified of the progress of each request. In order to advance through the process, all required or requested information must be provided. Incomplete submittals will not be considered.
012500a - page 1
SUBSTITUTION REQUEST FORM
PROJECT: ________________________________________________________________________
We hereby submit for your consideration, the following products instead of the specified items for the above project:
Drawing: Spec Section: Paragraph: Specified Item:
The submittor hereby:
• Certifies that the proposed substitute item has been fully investigated and has been determined to be equal or superior to that specified in all respects; that the same or greater warranty will be furnished, that required maintenance service and source for replacement parts are available, and that incorporation of the proposed substitute item will not affect functional clearances.
• Warrants that coordination, installation, and changes to the project as necessary to accommodate the proposed substitution shall be the Supplier/ Contractor's responsibility, that use of the substitute item(s) will not delay project completion, and that claims for additional costs related to its incorporation which may become subsequently apparent will be borne by the Supplier/ Contractor.
CERTIFICATION OF EQUAL PERFORMANCE AND
ASSUMPTION OF LIABILITY FOR EQUAL PERFORMANCE.
The undersigned states that the function, appearance and quality are equivalent or superior to the specified item.
Submitted By (print name)
Title
Signature Date
Company
Address
Address
Telephone
Signature must be person having authority to legally bind the Company to the above terms. Failure to provide legally binding signature will result in retraction of approval.
For Use by design Consultant:
ACCEPTED ACCEPTED
AS NOTED
NOT RECEIVED
ACCEPTED TOO LATE
Reviewed By
Date
REMARKS:
Proposed Substitution:
Form 012500b - page 1
SUBSTITUTION REQUEST FORM
COMPLETE THE FOLLOWING IN ITS ENTIRETY (Use additional sheets if necessary, or annotate the supporting documents to indicate requested / required information).
1. Reason for substitution request. Provide as much detail as possible:
2. Does this substitution affect dimensions shown on Template Drawings? Yes_______. No_______.
If yes, indicate changes:
3. What effect does the substitution have on other trades?
4. What effect do applicable code requirements have on substitution?
5. Describe the differences between the proposed substitution and the specified item(s):
6. How do manufacturer guarantees compare between proposed and specified items? Same_______.
Different (Provide details)_________.
Details:
Attachments:
What projected lump sum installed cost difference between proposed substitution and least expensive specified item?
$___________________. [ 0; (decrease); increase ]
Form 012500b - page 2
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. General administrative requirements.
B. Electronic document submittal service.
C. Preconstruction meeting.
D. Site mobilization meeting.
E. Progress meetings.
F. Construction progress schedule.
G. Progress photographs.
H. Coordination drawings.
I. Submittals for review, information, and project closeout.
J. Number of copies of submittals.
K. Requests for Interpretation (RFI) procedures.
L. Submittal procedures.
1.02 GENERAL ADMINISTRATIVE REQUIREMENTS
A. Make the following types of submittals to Architect:
1. Requests for Interpretation (RFI).
2. Requests for substitution.
3. Shop drawings, product data, and samples.
4. Test and inspection reports.
5. Design data.
6. Manufacturer's instructions and field reports.
7. Applications for payment and change order requests.
8. Progress schedules.
9. Coordination drawings.
10. Correction Punch List and Final Correction Punch List for Substantial Completion.
11. Closeout submittals.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 2
1.03 PROJECT COORDINATOR
A. Project Coordinator: General Contractor.
B. Cooperate with the Project Coordinator in allocation of mobilization areas of site; project site and building access, traffic, deliveries, and parking facilities.
C. During construction, coordinate use of site and facilities through the Project Coordinator.
D. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.
E. Make the following types of submittals to Architect through the Project Coordinator:
1. Requests for Interpretation.
2. Requests for substitution.
3. Shop drawings, product data, and samples.
4. Test and inspection reports.
5. Design data.
6. Applications for payment and change order requests.
7. Progress schedules.
8. Coordination drawings.
9. Correction Punch List and Final Correction Punch List for Substantial Completion.
10. Closeout submittals.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 ELECTRONIC DOCUMENT SUBMITTAL SERVICE
A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF, MS Word, or MS Excel) format, as appropriate to the document, and transmitted via an Internet-based submittal service that receives, logs and stores documents, provides electronic stamping and signatures, and notifies addressees via email.
1. Besides submittals for review, information, and closeout, this procedure applies to
Requests for Interpretation (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction punchlist, and any other document any participant wishes to make part of the project record.
2. Contractor and Architect are required to use this service.
3. It is Contractor's responsibility to submit documents in allowable format.
4. Subcontractors, suppliers, and Architect's consultants are to be permitted to use the service at no extra charge.
5. Users of the service need an email address, internet access, and PDF review software that includes ability to mark up and apply electronic stamps (such as Adobe Acrobat, STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 3
www.adobe.com, or Bluebeam PDF Revu, www.bluebeam.com), unless such software capability is provided by the service provider.
6. Paper document transmittals will not be reviewed; emailed electronic documents will not be reviewed.
7. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.
B. Cost: The cost of the service is to be paid by Contractor; include the cost of the service in the Contract Sum.
C. Submittal Service: The selected service is:
1. Newforma ConstructEx: www.newforma.com/our-solutions/constructex/#sle.
D. Training: One, one-hour, web-based training session will be arranged for all participants, with representatives of Architect and Contractor participating; further training is the responsibility of the user of the service.
E. Project Closeout: Architect will determine when to terminate the service for the project and is responsible for obtaining archive copies of files for Owner.
3.02 PRECONSTRUCTION MEETING
A. Schedule meeting after Notice of Award.
B. Attendance Required:
1. Owner.
2. Architect.
3. Contractor.
C. Agenda:
1. Execution of Owner-Contractor Agreement.
2. Submission of executed bonds and insurance certificates.
3. Distribution of Contract Documents.
4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.
5. Submission of initial Submittal schedule.
6. Designation of personnel representing the parties to Contract and Architect.
7. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
8. Scheduling.
D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.
3.03 SITE MOBILIZATION MEETING
A. Project Coordinator will schedule meeting at the Project site prior to Contractor occupancy.
B. Attendance Required:
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 4
1. Contractor.
2. Owner.
3. Architect.
4. Special consultants.
5. Contractor's superintendent.
6. Major subcontractors.
C. Agenda:
1. Use of premises by Owner and Contractor.
2. Owner's requirements.
3. Construction facilities and controls provided by Owner.
4. Temporary utilities provided by Owner.
5. Survey and building layout.
6. Security and housekeeping procedures.
7. Schedules.
8. Application for payment procedures.
9. Procedures for testing.
10. Procedures for maintaining record documents.
11. Requirements for start-up of equipment.
12. Inspection and acceptance of equipment put into service during construction period.
D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.04 PROGRESS MEETINGS
A. Schedule and administer meetings throughout progress of the work at maximum bi-monthly intervals.
B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.
C. Attendance Required:
1. Contractor.
2. Owner.
3. Architect.
4. Contractor's superintendent.
5. Major subcontractors.
D. Agenda:
1. Review minutes of previous meetings.
2. Review of work progress.
3. Field observations, problems, and decisions.
4. Identification of problems that impede, or will impede, planned progress.
5. Review of submittals schedule and status of submittals.
6. Review of RFIs log and status of responses.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 5
7. Review of off-site fabrication and delivery schedules.
8. Maintenance of progress schedule.
9. Corrective measures to regain projected schedules.
10. Planned progress during succeeding work period.
11. Coordination of projected progress.
12. Maintenance of quality and work standards.
13. Effect of proposed changes on progress schedule and coordination.
14. Other business relating to work.
E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.
3.05 CONSTRUCTION PROGRESS SCHEDULE
A. Within 10 days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.
B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.
C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.
1. Include written certification that major Subcontractors have reviewed and accepted proposed schedule.
D. Within 10 days after joint review, submit complete schedule.
E. Submit updated schedule with each Application for Payment.
3.06 PROGRESS PHOTOGRAPHS
A. Submit photographs with each application for payment, taken not more than 3 days prior to submission of application for payment.
B. Maintain one set of all photographs at project site for reference; same copies as submitted, identified as such.
C. Photography Type: Digital; electronic files.
D. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to Architect.
E. In addition to periodic, recurring views, take photographs of each of the following events:
1. Completion of demolition work.
2. Excavations in progress.
3. Foundations in progress and upon completion.
4. Structural framing in progress and upon completion.
5. Enclosure of concealed areas of construction.
6. Final completion, minimum of ten (10) photos.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 6
F. Take photographs as evidence of existing project conditions as follows:
1. Interior views: Showing condition of existing areas of construction including adjacent areas not included as part of construction.
2. Exterior views.
G. Views:
1. Provide photographs from four cardinal views at each specified time, until date of
Substantial Completion.
2. Consult with Architect for instructions on views required.
3. Provide factual presentation.
4. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.
H. Digital Photographs: 24 bit color, minimum resolution of 1024 by 768, in JPG format; provide files unaltered by photo editing software.
1. Delivery Medium: Via email.
2. File Naming: Include project identification, date and time of view, and view identification.
3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.
4. Hard Copy: Printed hardcopy (grayscale) of PDF file and point of view sketch.
3.07 COORDINATION DRAWINGS
A. Provide information required by Project Coordinator for preparation of coordination drawings.
B. Review drawings prior to submission to Architect.
3.08 REQUESTS FOR INTERPRETATION (RFI)
A. Definition: A request seeking one of the following:
1. An interpretation, amplification, or clarification of some requirement of Contract
Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.
2. A resolution to an issue which has arisen due to field conditions and affects design intent.
B. Whenever possible, request clarifications at the next appropriate project progress meeting, with response entered into meeting minutes, rendering unnecessary the issuance of a formal
RFI.
C. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.
1. Prepare a separate RFI for each specific item.
a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.
b. Do not forward requests which solely require internal coordination between subcontractors.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 7
2. Prepare in a format and with content acceptable to Owner.
3. Prepare using an electronic version of the form appended to this section.
4. Prepare using software provided by the Electronic Document Submittal Service.
5. Combine RFI and its attachments into a single electronic file. PDF format is preferred.
D. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.
1. Include in each request Contractor's signature attesting to good faith effort to determine from Contract Documents information requiring interpretation.
2. Unacceptable Uses for RFIs: Do not use RFIs to request the following::
a. Approval of submittals (use procedures specified elsewhere in this section).
b. Approval of substitutions.
c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Conditions of the Contract).
3. Improper RFIs: Requests not prepared in compliance with requirements of this section, and/or missing key information required to render an actionable response. They will be returned without a response.
4. Frivolous RFIs: Requests regarding information that is clearly indicated on, or reasonably inferable from, Contract Documents, with no additional input required to clarify the question. They will be returned without a response.
E. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.
1. Official Project name and number, and any additional required identifiers established in
Contract Documents.
2. Discrete and consecutive RFI number, and descriptive subject/title.
3. Issue date, and requested reply date.
4. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).
5. Annotations: Field dimensions and/or description of conditions which have engendered the request.
6. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;
routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.
F. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.
G. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.
1. Indicate current status of every RFI. Update log promptly and on a regular basis.
2. Note dates of when each request is made, and when a response is received.
3. Highlight items requiring priority or expedited response.
4. Highlight items for which a timely response has not been received to date.
5. Identify and include improper or frivolous RFIs.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 8
H. Review Time: Architect will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 3:00 PM will be considered as having been received on the following regular working day. This time is the prevailing time at the Architect's office indicated on the Contract Documents.
1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.
I. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Sum or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.
1. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith.
Identify the amended RFI with an R suffix to the original number.
2. Do not extend applicability of a response to specific item to encompass other similar conditions, unless specifically so noted in the response.
3. Upon receipt of a response, promptly review and distribute it to all affected parties, and update the RFI Log.
4. Notify Architect within seven calendar days if an additional or corrected response is required by submitting an amended version of the original RFI, identified as specified above.
3.09 SUBMITTAL SCHEDULE
A. Submit to Architect for review a schedule for submittals in tabular format.
1. Coordinate with Contractor's construction schedule and schedule of values.
2. Format schedule to allow tracking of status of submittals throughout duration of construction.
3. Arrange information to include scheduled date for initial submittal, specification number and title, submittal category (for review or for information), description of item of work covered, and role and name of subcontractor.
4. Account for time required for preparation, review, manufacturing, fabrication and delivery when establishing submittal delivery and review deadline dates.
a. For assemblies, equipment, systems comprised of multiple components and/or requiring detailed coordination with other work, allow for additional time to make corrections or revisions to initial submittals, and time for their review.
3.10 SUBMITTALS FOR REVIEW
A. When the following are specified in individual sections, submit them for review:
1. Product data.
2. Design data.
3. Shop drawings.
4. Samples for selection.
5. Samples for verification.
B. Submit to Architect for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 9
C. Samples will be reviewed for aesthetic, color, or finish selection.
D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00 - Closeout Submittals.
3.11 SUBMITTALS FOR INFORMATION
A. When the following are specified in individual sections, submit them for information:
1. Certificates.
2. Test reports.
3. Inspection reports.
4. Manufacturer's instructions.
5. Manufacturer's field reports.
6. Other types indicated.
B. Submit for Architect's knowledge as contract administrator or for Owner.
3.12 SUBMITTALS FOR PROJECT CLOSEOUT
A. Submit Correction Punch List for Substantial Completion.
B. Submit Final Correction Punch List for Substantial Completion.
C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 01 78 00 - Closeout Submittals:
1. Project record documents.
2. Operation and maintenance data.
3. Warranties.
4. Bonds.
5. Other types as indicated.
D. Submit for Owner's benefit during and after project completion.
3.13 NUMBER OF COPIES OF SUBMITTALS
A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.
B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.
1. After review, produce duplicates.
2. Retained samples will not be returned to Contractor unless specifically so stated.
3.14 SUBMITTAL PROCEDURES
A. General Requirements:
1. Use a single transmittal for related items.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 10
2. Submit separate packages of submittals for review and submittals for information, when included in the same specification section.
3. Transmit using an electronic version of the form appended to this section.
4. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.
5. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.
6. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.
a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.
7. Deliver each submittal on date noted in submittal schedule, unless an earlier date has been agreed to by all affected parties, and is of the benefit to the project.
a. Upload submittals in electronic form to Electronic Document Submittal Service website.
8. Schedule submittals to expedite the Project, and coordinate submission of related items.
a. For each submittal for review, allow 15 days excluding delivery time to and from the Contractor.
b. For sequential reviews involving Architect's consultants, Owner, or another affected party, allow an additional 7 days.
c. For sequential reviews involving approval from authorities having jurisdiction (AHJ), in addition to Architect's approval, allow an additional 30 days.
9. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.
10. Provide space for Contractor and Architect review stamps.
11. When revised for resubmission, identify all changes made since previous submission.
12. Distribute reviewed submittals. Instruct parties to promptly report inability to comply with requirements.
13. Incomplete submittals will not be reviewed, unless they are partial submittals for distinct portion(s) of the work, and have received prior approval for their use.
14. Submittals not requested will be recognized, and will be returned "Not Reviewed", B. Product Data Procedures:
1. Submit only information required by individual specification sections.
2. Collect required information into a single submittal.
3. Submit concurrently with related shop drawing submittal.
4. Do not submit (Material) Safety Data Sheets for materials or products.
C. Shop Drawing Procedures:
1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting
Contract Documents and coordinating related work.
2. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.
D. Samples Procedures:
1. Transmit related items together as single package.
STANTEC PROJECT NO. 218012249
ADMINISTRATIVE REQUIREMENTS 01 30 00 - 11
2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.
3. Include with transmittal high-resolution image files of samples to facilitate electronic review and approval. Provide separate submittal page for each item image.
3.15 SUBMITTAL REVIEW
A. Submittals for Review: Architect will review each submittal, and approve, or take other appropriate action.
B. Submittals for Information: Architect will not acknowledge receipt, and take no other action.
C. Architect's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.
1. Notations may be made directly on submitted items and/or listed on appended Submittal
Review cover sheet.
D. Architect's and consultants' actions on items submitted for review:
1. Authorizing purchasing, fabrication, delivery, and installation:
a. "Reviewed".
b. "Reviewed, as noted".
1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.
2. Not Authorizing fabrication, delivery, and installation:
a. "Revise and Resubmit".
1) Resubmit revised item, with review notations acknowledged and incorporated.
2) Non-responsive resubmittals may be rejected.
b. "Not Reviewed".
1) Submit item complying with requirements of Contract Documents.
E. Architect's and consultants' actions on items submitted for information:
1. No acknowledgement of receipt will be given and no action will be taken
ELECTRONIC EXCHANGE AGREEMENT
Document2
THIS AGREEMENT is made and entered into effective (the “Agreement Date”) by and between:
“OWNER”
Name:
Address:
Phone:
Representative:
“RECIPIENT”
Name:
Address:
Phone:
Representative:
“PROJECT”
Name:
Address:
Fax:
Fax:
WHEREAS, Stantec and its consultants have prepared for this , computer-aided drawings for the construction of the Project including a Building Information Model (“BIM”) and/or other electronic data (hereinafter referred to jointly as “Electronic Data”) – graphic or non-graphic in nature, which do not constitute part of the
Contract Documents as described under the Recipient’s Contract with the Owner.
WHEREAS, Recipient has requested that it be provided with the Electronic Data for Recipient’s use(s) solely on this project. Stantec agrees to provide Electronic Data to support the following (check all that apply):
Construction Modeling
Clash Detection
Timeline Simulations
Logistics planning
Quantity extraction / Cost Estimating
Shop Drawings
Bidding
Other
NOW, THEREFORE, to effect the arrangement to transfer Electronic Data to Recipient, the Parties agree as follows:
That the Recipient may use the Electronic Data to assist it solely in connection with the uses stated above and no changes are to be made without Stantec’s prior written consent.
That the Electronic Data is being provided to Recipient in the following format(s) (check all that apply):
3 Dimensional Format(s):
Revit version (.rvt)
Navisworks version (.nwc/.nwd/.nwf)
AutoCAD version (.dwg)
AutoCAD version (.dxf)
MicroStation version (.dgn)
IFC (IFC)
Other
ELECTRONIC EXCHANGE AGREEMENT Page 2
2 Dimensional Format(s):
(.dwg)
(.dxf)
(.dgn)
AutoCAD version
AutoCAD version
MicroStation version
Other
Data Format(s):
(.xls) Microsoft Excel version
COBie
Other
The Recipient acknowledges that Stantec may change the software version and/or build for any application(s) used to create Electronic Files as needed at any time. Stantec will not supply alternate versions or formats unless agreed to in writing.
It is understood that any Electronic Data provided including BIM information is not a substitute for final hard copy
Construction Documents. The Electronic Data is not complementary to the final Construction Documents and it is understood that Electronic Data can not be relied upon to be coordinated, accurate, complete, and can not be relied upon to represent correct quantities. Recipient also acknowledges that subsequent BIM updates may contain significant changes that might conflict with legacy models and therefore be incompatible. It is understood that the
Electronic Data supplied under this agreement was prepared for Stantec’s design purposes and not for the Recipient’s uses, and that Recipient will not use the Electronic Data as a substitute for its traditional processes and own technology.
Stantec makes no representation about the electronic data that can be relied upon by the Recipient or user for any purpose.
Check the paragraph that applies:
The Recipient understands that this is a onetime exchange and that updated files will not be provided.
The Recipient recognizes that Stantec’s Electronic Data development does not follow the Recipient's schedule for their intended use of the files. Therefore, after the first exchange of Electronic Data, the Recipient may request updated files from Stantec no sooner than ________weeks from first exchange and not more frequently than ________weeks thereafter. It is at Stantec's sole discretion to provide updated files outside of this established schedule.
The Recipient agrees that Stantec will issue additional electronic files only at scheduled project milestones.
Transmission of the files may follow the milestone date by up _____days. It is at Stantec's sole discretion to provide updated files outside of this established schedule.
The Recipient is being granted access to a cloud-based system, where data is being updated on a continuous basis. The data available for download may not represent the most up to date files, and the Recipient may or may not receive notifications that new information is available.
The Recipient recognizes that the condition of the Electronic Data may warrant a live work session with Stantec to explain changes or conditions in the model that may impact the Recipient’s ability to use the Electronic Data for those purposes listed above or that it might impact the design of the project. In each such case Recipient agrees to participate in said work session and share the changes to the Electronic Data and its observations it has made through the use of the Electronic Data.
The Recipient agrees that Stantec’s title block on each drawing contained with the Electronic Data must be deleted, and this Agreement grants no right to reproduce the title block.
Under no circumstances shall the providing of the Electronic Data be deemed a sale of a product or good, and neither the Owner nor Stantec or their Consultants make any warranties, express or implied, including warranty of fitness for a particular purpose or warranty of merchantability or other any other warranty.
It is understood that the automated conversion of information and data from the system and format used by Stantec to an alternate system or format cannot be accomplished without the risk of introducing inexactitudes, anomalies, and/or errors. Recipient also understands the inherent risk of data loss or corruption from the use and/or storage of Electronic
Data. Recipient also understands that the Electronic Data may be incomplete and/or uncoordinated with other portions of the project design, or that it might change through the term of the Project, and Recipient must verify all information as contained in the Contract Documents before it uses it for any purpose. Recipient also understands that this agreement or the Recipient’s use of the Electronic Data does not relieve it of its other contractual responsibilities under the Construction Contract, that it remains fully responsible for its shop drawings and other submittals, and remains
ELECTRONIC EXCHANGE AGREEMENT Page 3 responsible to ensure that the electronic design data is in conformity with the design shown on the contract documents to the extent necessary to properly prepare its shop drawings or perform its work. Accordingly, the Digital Files, provided by Stantec, are for informational purposes only and are not intended to be directly incorporated into the
Contractor’s end product. Recipient remains fully responsible for determining its own means, methods, sequences and procedures, and is not entitled to rely upon any information or assumptions related to means, methods, sequences or procedures assumed by Stantec, project engineers or other designers in developing the Electronic Data, whether the information or assumptions are shared with the Recipient or not. Recipient agrees to assume all risks associated with the use, conversion or storage of the Electronic Data.
Recipient also recognizes that changes or modifications to Stantec’s instruments of professional service introduced by anyone other than Stantec may result in adverse consequences which cannot be predicted nor controlled and understood.
Therefore, and in consideration of the Owner’s agreement to deliver their instruments of professional service in machine readable form, Recipient agrees, to the fullest extent permitted by law, to defend, hold harmless and indemnify the
Owner and Stantec and their consultants, and each of their officers, employees, and affiliated and successor companies from and against all claims, liabilities, losses, damages, and costs, including but not limited to attorney’s fees, whether asserted as a breach of contract, breach of warranty, negligence, misrepresentation or other tort, or otherwise, arising out of or in any way connected with the use, conversion, modification, misinterpretation, misuse, or reuse by the Recipient or others for whom the Recipient is responsible of the Electronic Data provided by Stantec under this Agreement.
Recipient agrees not to reverse-engineer, or use in any way, the BIM or its contents (including Revit families or objects) provided by Stantec except to use specifically for this project and only for the uses described herein. Recipient will not export or share the Electronic Data or any unique or novel aspects of Stantec’s model(s) or Stantec’s BIM process with any third party, in full or in part, for any reason other than to fulfill the project requirements set forth in this Agreement or in the Recipient’s prime agreement with the Owner.
The Recipient agrees to require its subcontractors who use any of the Electronic Data to sign acceptance of the terms of this agreement as though they/it were the Recipient, by agreement with the Recipient for the benefit of the Owner, Stantec and their officers, employees, and consultants.
Use of any medium or files containing the described Electronic Data by any party (the “user”) constitutes acceptance of the terms of this Agreement by the user as though the user were the Recipient described in this Agreement.
This Agreement does not constitute an agreement with Stantec or create any cause of action of any kind in favor of the Recipient, its subcontractor, suppliers or any third party against Stantec or the Owner. This Electronic Exchange
Agreement is made solely for the benefit of the Owner, the Recipient, Stantec and its consultants, and no other party is an intended beneficiary of this Agreement.
RECIPIENT COMPANY NAME
By:
Signature
01 26 13.13 - 1
REQUEST FOR INTERPRETATION FORM
REQUEST FOR INTERPRETATION FORM
PROJECT: RFI NUMBER:
FROM: DATE:
RE: CONTRACT FOR:
SECTION NUMBER: TITLE:
PAGE: ARTICLE/PARAGRAPH:
DRAWING NUMBER: DETAIL REFERENCE:
Contractor's Request:
Attachments
SIGNED BY: DATE:
Architect's Response:
Attachments
RESPONSE FROM: REC'D:
TO: RETURNED:
SIGNED BY: DATE:
END OF FORM 01 26 13.13
Y:\DROPBOX (WDEO)\2020\2020.S23 WASHBURN LAW SCHOOL\04 SPECIFICATIONS\2021-03-17 CONSTRUCTION ISSUE\BY ABA\FORMS & SCHEDULES\WSX FORMS\01 26 13.13_WSX REQUEST FOR INTERPRETATION FORM.DOC© 2021 WDEO Associates, Inc.
SUBMITTAL REVIEW
013300ba
Contractor Name & Address Phone/Fax Project Name & No.:
Contractor Review Item Submitted:
Submittal:
Dwg. No.:
Subcontractor:
Supplier:
Manf.
Spec. Ref.: Architect Review
Dwg. Ref.:
Deviations from
Contract Doc.:
Submitted By:
Title:
Comments
Date:
Submittal
No.:
rlcook Cross-Out
STANTEC PROJECT NO. 218012249
QUALITY REQUIREMENTS 01 40 00 - 1
SECTION 01 40 00
QUALITY REQUIREMENTS
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Submittals.
B. Quality assurance.
C. References and standards.
D. Testing and inspection agencies and services.
E. Contractor's design-related professional design services.
F. Control of installation.
G. Mock-ups.
H. Tolerances.
I. Manufacturers' field services.
J. Defect Assessment.
1.02 RELATED REQUIREMENTS
A. Section 01 30 00 - Administrative Requirements: Submittal procedures.
1.03 CONTRACTOR'S DESIGN-RELATED PROFESSIONAL DESIGN SERVICES
A. Coordination: Contractor's professional design services are subject to requirements of project's Conditions for Construction Contract.
B. Base design on performance and/or design criteria indicated in individual specification sections.
1. Submit a Request for Interpretation to Architect if the criteria indicated are not sufficient to perform required design services.
C. Scope of Contractor's Professional Design Services: Provide for the following items of work:
1. Structural Design of Metal Framing: As described in Section 05 40 00 - Cold-Formed
Metal Framing.
2. Structural Design: Include calculations for resisting wind loads, anchor locations, loads at points of attachment to building structure, physical characteristics, resulting dimensional limitations as described in Section 08 44 13 - Glazed Aluminum Curtain Walls.
STANTEC PROJECT NO. 218012249
QUALITY REQUIREMENTS 01 40 00 - 2
1.04 SUBMITTALS
A. See Section 01 30 00 - Administrative Requirements, for submittal procedures.
B. Designer's Qualification Statement: Submit for Architect's knowledge as contract administrator, or for Owner's information.
1. Include information for each individual professional responsible for producing, or supervising production of, design-related professional services provided by Contractor.
a. Full name.
b. Professional licensure information.
c. Statement addressing extent and depth of experience specifically relevant to design of items assigned to Contractor.
C. Design Data: Submit for Architect's knowledge as contract administrator for the limited purpose of assessing compliance with information given and the design concept expressed in the Contract Documents, or for Owner's information.
1. Include calculations that have been used to demonstrate compliance to performance and regulatory criteria provided, and to determine design solutions.
2. Include a statement or certification attesting that design data complies with criteria indicated, such as building codes, loads, functional, and similar engineering requirements.
3. Include signature and seal of design professional responsible for allocated design services on calculations and drawings.
D. Test Reports: After each test/inspection, promptly submit two copies of report to Architect and to Contractor.
1.05 QUALITY ASSURANCE
A. Designer Qualifications: Where professional engineering design services and design data submittals are specifically required of Contractor by Contract Documents, provide services of a Professional Engineer experienced in design of this type of work and licensed in the State in which the Project is located.
1.06 REFERENCES AND STANDARDS
A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.
B. Comply with reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.
C. Obtain copies of standards where required by product specification sections.
D. Maintain copy at project site during submittals, planning, and progress of the specific work, until Substantial Completion.
E. Should specified reference standards conflict with Contract Documents, request clarification from Architect before proceeding.
STANTEC PROJECT NO. 218012249
QUALITY REQUIREMENTS 01 40 00 - 3
F. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Architect shall be altered from Contract Documents by mention or inference otherwise in any reference document.
1.07 TESTING AND INSPECTION AGENCIES AND SERVICES
A. Contractor shall employ and pay for services of an independent testing agency to perform specified testing and inspection .
B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION
3.01 CONTROL OF INSTALLATION
A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.
B. Comply with manufacturers' instructions, including each step in sequence.
C. Should manufacturers' instructions conflict with…