Attachments A-1 and A-2.pdf

PDF 317 KB Posted

Attached to
Interior Demolition and Environmental Remediation
Solicitation number
2140474
Issued by
Broome County, New York

About this file

These documents are Agency Specific Terms and Conditions and Program Specific Terms and Conditions for the Zoos, Botanical Gardens and Aquaria (ZBGA) Capital Grant Program administered by the New York State Office of Parks, Recreation and Historic Preservation (OPRHP). The contract relates to an Interior Demolition and Environmental Remediation project at the Roberson Museum's main campus in Binghamton, New York, which seeks a general contractor to provide separate pricing for environmental remediation and general demolition services. The contract establishes standard notice procedures, payment terms directed to the designated contractor's NYS Vendor ID Number, and requirements for workers' compensation and disability benefits insurance coverage. Changes to the work plan or budget require prior written State approval, with substantive changes requiring amendment approval from the New York Attorney General Contract Approval Unit and the Office of the State Comptroller. The contract includes requirements for non-discrimination, compliance with the Freedom of Information Law, non-sectarian use of funds, and procedures for unanticipated archaeological discoveries.

The contract imposes significant compliance obligations on contractors, including adherence to historic preservation standards under Section 106 of the National Historic Preservation Act and Section 14.09 of New York State Parks, Recreation and Historic Preservation Law, and conformance with The Secretary of the Interior's Standards for the Treatment of Historic Properties. For construction projects, contractors must submit plans, specifications, and cost estimates for State review prior to construction contract execution and ensure compliance with the Uniform Federal Accessibility Standards, Americans with Disabilities Act Accessibility Guidelines, and New York State Uniform Fire Prevention and Building Code. Effective December 30, 2024, all contractors and subcontractors must register with the New York State Department of Labor under Labor Law Section 220-i, with digital certificates of registration required at bid submission. The contract identifies Minority/Women Business Enterprise (MWBE) contracting goals at 30 percent total and a Service-Disabled Veteran-Owned Business (SDVOB) goal at 6 percent. Procurement of all goods and services must follow prudent and economical practices consistent with General Municipal Law requirements where applicable, with documentation of competitive bidding or alternative procurement procedures required with reimbursement requests. The public must receive reasonable access to the funded facility, and the State retains inspection and audit rights throughout implementation and after project completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 of 3 – Attachment A-1 – Agency Specific Terms and Conditions 03/2025

ATTACHMENT A-1

AGENCY SPECIFIC TERMS AND CONDITIONS

A. Notice. For purposes of notice as contained in this State of New York Contract for Grants (Contract), Standard Terms and Conditions, Section I(G):

1. The State’s designee shall be the STATE AGENCY identified on the Face Page. Document submission and inquiries should be directed to the designated STATE AGENCY representative.

2. The Contractor’s designee shall be the CONTRACTOR NAME at the CONTRACTOR PRIMARY

MAILING ADDRESS, as identified on the Face Page.

B. Payment shall be made to the NYS Vendor ID Number at the CONTRACTOR PAYMENT ADDRESS identified on the Face Page.

C. Changes to Budget and Program Work Plan. Changes shall not be made in the work described in

Attachment C (Work Plan) or the proposed expenditure of funds as shown in Attachment B (Budget), without the prior written approval of the State. Such approval will be granted if the changes are not substantive and do not alter the scope, intent or basic elements of the contract. Changes in the Work Plan or Budget that are substantive or alter the scope, intent or basic elements of the contract, if agreed to by the State, will be implemented by an amendment that may require approval and filing with the New York

Attorney General Contract Approval Unit (AG) and the Office of the State Comptroller (OSC or State

Comptroller), per Section I(D) of this Contract.

D. It is the Contractor’s responsibility, pursuant to Sections 57 and 220 (8) of the Workers' Compensation

Law, to maintain for State audit and review either proof that they have Workers' Compensation and

Disability Benefits Insurance coverage for any employees, or proof of exemption from the New York

State Workers’ Compensation Board. The Contractor must also obtain from any contractor or subcontractor hired to provide a service pursuant to this Contract, similar proof or waivers from the contractor or subcontractor, and must maintain such documentation on file for audit.

E. Non-Discrimination:

1. If the project involves development or acquisition of public facilities, the Contractor shall not limit access or discriminate in the operation of the facilities on the basis of place of residence, race, creed, color, national origin, sex, age, disability or marital status.

2. The Contractor agrees to comply with all applicable Federal, State, and local Civil Rights and Human

Rights laws with reference to equal employment opportunities and the provisions of service.

F. Termination. In addition to the options available to the State in the Contract, in the event the Contractor fails to comply with its terms and conditions regarding completion of the project, the State at its option may require the Contractor to bring the project to a point of educational/interpretive, historical, recreational or conservation usefulness as determined by the State.

G. Documents submitted to the State may be subject to disclosure under the Freedom of Information Law.

H. Non-Sectarian Purposes. The Contractor agrees that funds made available as shown in Attachment B will only be used to achieve the intended public benefit and will not be used for any sectarian purposes.

I. Archeology. In the event of any unanticipated archeological discoveries, the Contractor shall stop all work and notify the State immediately. Work shall not resume until the State determines how any previously undiscovered archeological remains will be treated. Special attention shall be given to any discovery of burials, graves, or human remains.

Page 2 of 3 – Attachment A-1 – Agency Specific Terms and Conditions 03/2025

J. Preservation of Historic Properties. It is the public policy and in the public interest of the State to preserve New York’s historical, archeological, architectural and cultural heritage. All activities under this

Contract shall be reviewed under either Section 106 of the National Historic Preservation Act or Section 14.09 of the New York State Parks, Recreation and Historic Preservation Law to ensure that adverse effects or impacts on significant properties are avoided or mitigated. Any work that affects historic properties shall conform to The Secretary of the Interior's Standards for the Treatment of Historic Properties 1995, The

Secretary of the Interior's Standards and Guidelines for Archeological Documentation or any other applicable

Secretary of the Interior's Standards (collectively referenced as STANDARDS), which are available from the

State.

K. Post-Completion Requirements. Where the project involves acquisition of equipment or acquisition of or improvement of real property, the Contractor shall be responsible for maintaining and operating the equipment, property, and/or improvements; providing public access; maintaining public signage related to the project; and seeking any required State approvals. The State shall have the right and responsibility to inspect the project and property for compliance.

L. Construction Requirements. If the Project described in this Contract includes construction, the following shall apply:

1. Contract plans, specifications, and cost estimates shall be submitted to the State for review prior to the letting of any construction contract by the Contractor. The State shall verify that the plans, specifications and cost estimates are in conformance with the work described in Attachment B and shall so notify the Contractor in writing; the State shall further verify that appropriate documents have been prepared by a professional licensed to practice in the State of New York. All plans and specifications as reviewed shall become part of this Contract, and no change or revision may be made to such plans and specifications without the express written consent of the State.

2. The Contractor shall be responsible for assuring that the project is designed and constructed in conformance with the Uniform Federal Accessibility Standards (UFAS Appendix A to 41 CFR part

101 19.6), the Americans with Disabilities Act Accessibility Guidelines (ADAAG Appendix A to 28

CFR part 36) and the New York State Uniform Fire Prevention and Building (I) (Code (parts 1219

1228 of Title 19 NYCRR). Where there are discrepancies among the sets of standards with regard to a particular design/construction requirement, the one providing for the greatest degree of accommodation for the disabled shall apply.

3. It is the Contractor’s responsibility to assure that all work on the project complies with the State

Environmental Quality Review Act, receives all required permits in advance, and complies with all applicable Federal, State and/or local laws including, but not limited to, zoning ordinances and building codes.

M. At the discretion of the State, an Agreed Upon Procedure Review may be required of the grant performed by a representative of the STATE or a certified public accountant procured by the STATE or the CONTRACTOR currently licensed by the NYS Board of Public Accountancy, in accordance with attestation standards established by the American Institute of Certified Public Accountants and in accordance with Government Auditing Standards issued by the Comptroller General of the United States of America to the satisfaction of the STATE.

N. The State may make periodic inspections of the project both during its implementation and after its completion to assure compliance with this Contract. The Contractor shall allow the State unrestricted access to work during the preparation and progress of the work and provide for such access and inspection by the State in all construction contracts relating to the project.

O. Department of Labor Public Work Contractor Registry. Effective December 30, 2024, all contractors and subcontractors submitting bids or performing construction work on public work projects or private projects covered by Article 8 of the Labor Law are required to register with the

Page 3 of 3 – Attachment A-1 – Agency Specific Terms and Conditions 03/2025

New York State Department of Labor under Labor Law Section 220-i. Private projects subject to

Article 8 of the Labor Law include those covered by Labor Law Sections 224-a (public subsidy funded projects), 224-d (renewable energy systems), 224-e (broadband projects), 224-f (climate risk-related and energy transition projects, and roadway excavations). A Certificate of Registration with a unique registration number will be issued to the applicant electronically through the Contractor

Registry portal. A digital copy of the certificate must be submitted with bid submission or bidder may be found to be non-responsive. Contractors are responsible for verifying that any subcontractors they work with are registered. Please refer to this website for information:

https://dol.ny.gov/contractor-and-subcontractor-landing. The registration login page is found here: Log In - Management System for Protecting Workers’ Rights.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fdol.ny.gov%2Fcontractor-and-subcontractor-landing&data=05%7C02%7CBeatrice.Gamache%40parks.ny.gov%7C6b1cefb2732b4e28c2ca08dd5b7660c4%7Cf46cb8ea79004d108ceb80e8c1c81ee7%7C0%7C0%7C638767286583289806%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=DuNSK5ya8Ogt%2Boq00dYvOjyCEA0QxMwKJMzzWsc11f8%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fmpwr-public.labor.ny.gov%2Fen%2Flogin&data=05%7C02%7CBeatrice.Gamache%40parks.ny.gov%7C6b1cefb2732b4e28c2ca08dd5b7660c4%7Cf46cb8ea79004d108ceb80e8c1c81ee7%7C0%7C0%7C638767286583314892%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=%2FN0xAhfePsU7GMB7j1W6moI7F1eBB%2FfpIQjYWu2wOgc%3D&reserved=0

Page 1 of 1, Attachment A-2 – Program Specific Terms and Conditions January 2025

ATTACHMENT A-2

PROGRAM SPECIFIC TERMS AND CONDITIONS

ZOOS, BOTANICAL GARDENS and AQUARIA CAPITAL GRANT PROGRAM

A. Funding for this project is provided by the Zoos, Botanical Gardens & Aquaria (ZBGA) Capital Grant Program, funded through an appropriation from the New York State Budget and is administered by the New York State Office of Parks, Recreation and Historic Preservation (OPRHP or Agency).

B. Procurement: All goods and services required for this project must be procured in a manner so as to assure the prudent and economical use of grant moneys, to facilitate the acquisition of goods and services of maximum quality at the lowest possible cost under the circumstances, and to guard against nepotism, favoritism, improvidence, extravagance, fraud and corruption.

1. If the Contractor is subject to General Municipal Law, documentation of the Contractor’s compliance with the procurement and bidding requirements of General Municipal Law shall be included with the applicable request for reimbursement.

2. If the total amount of the goods or services is less than the dollar threshold for competitive bidding, as outlined in section 103 of General Municipal Law, or if the Contractor is not subject to General Municipal Law, the Contractor must follow procurement procedures designed to achieve the purpose of this clause. Such procedures may include, but are not limited to, competitive bidding, the solicitation of three price quotes, written requests for proposals, etc. When submitting a request for reimbursement, the Contractor must include a copy of the organizational procurement policy applicable to the relevant expenditures and/or documentation of the specific procurement process used for those expenditures.

C. Public Benefit Requirements.

1. In order to ensure a public benefit accrues from the development or construction project that is being funded the Contractor shall:

a. Afford the public reasonable access to or use of the funded facility as specified by the State;

b. Own or hold by lease or maintain and operate the project as specified by the State;

c. Not alter, demolish, sell, lease or otherwise convey the ZBGA natural heritage collection, without the prior written approval of the State; and

D. In the case that this grant involves State-owned land, the grant recipient shall have in place a current, approved agreement with the agency of jurisdiction that specifies compliance for the elements funded with this grant as set forth in all Attachments included as part of this Contract.

File details come from the government source that posted it. Updated .