This Invitation to Negotiate (ITN) document represents a competitive procurement by the Greater Orlando Aviation Authority (GOAA) for the implementation of an enterprise-wide Project Management Information System (PMIS) serving Orlando International Airport (MCO) and Orlando Executive Airport (OEA) in Orange County, Florida. GOAA seeks a comprehensive, configurable PMIS solution that will serve as the centralized platform for planning, managing, monitoring, and reporting on the Authority's Capital Improvement Programs (CIP). The system must provide integrated portfolio, program, and project management capabilities including capital planning and budgeting, cost and budget management, project-level controls, risk and change order management, task and workflow management, document sharing and storage, schedule management, Earned Value Management, KPI tracking, project collaboration, and executive-level dashboards and reporting. The vendor must deliver a turnkey solution with seamless integration to GOAA's existing enterprise systems, particularly Oracle ERP and IBM Maximo. Responses are due December 22, 2026, with a pre-submittal meeting scheduled for November 2, 2026, question submission deadline of November 9, 2026, and question response deadline of December 1, 2026. The tentative evaluation committee date is January 26, 2027, with optional interviews on February 23, 2027, conclusion of negotiations on March 25, 2027, and Aviation Authority Board contract approval on April 21, 2027. The contract is intended as a non-exclusive agreement for a five-year period with one five-year renewal option, with an anticipated start date of January 1, 2027.

Pricing will be evaluated on a mathematical basis with the lowest-priced respondent receiving maximum points, with other respondents' scores calculated using a percentage ratio methodology. The solicitation does not identify a specific set-aside program. Respondents must meet all minimum requirements including employment verification, drug-free workplace certification, IT security requirements, and proof of verifiable experience successfully implementing a PMIS with a go-live date within five years prior to the solicitation date. A minimum of two references from clients within the past five years are required. The vendor must demonstrate ability to obtain required insurance coverage and register with the Aviation Authority's designated vendor performance management platform (Procurated's Canary). The contract includes comprehensive Service Level Agreement requirements with 99.9% minimum system availability, severity-based incident response and resolution timeframes ranging from one hour (critical incidents) to twenty-four hours (minor incidents), and defined performance metrics for system responsiveness. All data shall remain the property of GOAA, with the vendor required to maintain backup and disaster recovery capabilities including a four-hour Recovery Point Objective and eight-hour Recovery Time Objective. The vendor must implement appropriate cybersecurity controls including Multi-Factor Authentication, Single Sign-On integration, data encryption, and compliance with NIST cybersecurity framework and TSA security directives.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION TO NEGOTIATE

26-320-ITN

PROJECT MANAGEMENT INFORMATION

SYSTEM (PMIS)

TABLE OF CONTENTS

1. INTRODUCTION

2. GENERAL INFORMATION AND RESPONSE PREPARATION

3. SCOPE OF WORK / SPECIFICATIONS

4. SCOPE OF SERVICES: ACCOUNTING AND FINANCE REQUIREMENTS FOR PMIS

5. SERVICE LEVEL AGREEMENT

6. MINIMUM REQUIREMENTS

7. OTHER REQUIREMENTS

8. SELECTION PROCESS AND AWARD

9. CONTRACT EXECUTION INSTRUCTIONS

10. EVALUATION CRITERIA

11. VENDOR QUESTIONNAIRE

12. PRICE TABLE(S)

GREATER ORLANDO AVIATION AUTHORITY

Project Management Information System (PMIS)

1. INTRODUCTION

1.1. Summary

The Greater Orlando Aviation Authority (GOAA) seeks to implement a comprehensive, enterprise-wide Project Management Information System (PMIS) that will serve as the centralized platform for planning, managing, monitoring, and reporting on the

Authority's Capital Improvement Programs (CIP) for Orlando International Airport

(MCO) and Orlando Executive Airport (OEA). The PMIS will support the successful execution of initiatives aligned with GOAA's Strategic Plan, Master Plans, and long-term capital investment objectives.

The ideal solution will offer a suite of portfolio, program, and project management level functionalities to support capital planning and budgeting, cost and budget management, project-level controls, risk and change order management, task and workflow management, document sharing and storage, schedule management, Earned Value

Management, KPI tracking, project collaboration, executive level dashboards and reporting that integrates with existing systems used by GOAA.

The selected solution must provide integrated portfolio, program, and project management capabilities that enable effective capital planning, budgeting, project controls, risk management, schedule management, document management, workflow automation, performance monitoring, and executive reporting. The system shall serve as the single source of truth for capital project information and facilitate informed decision-making through real-time data, analytics, and dashboard reporting.

The proposed solution must seamlessly integrate with GOAA's existing enterprise systems and provide scalable functionality to support the Authority's evolving business, operational, and capital development requirements.

1.2. Procurement Services Point of Contact

When the Questions and Answers function is not available, please contact Jamie Lopez, Assistant Manager Procurement, via email at jamie.lopez@goaa.org.

1.3. Intent

The Aviation Authority's intent is to enter into a non-exclusive Contract for the services described in this solicitation for a five (5) year period with one 5-year renewal. Contract to start on or about January 1, 2027.

1.4. Background

GOAA manages a complex and continually evolving portfolio of capital improvement projects in support of one of the nation's leading international airports. To enhance operational efficiency, governance, transparency, and data-driven decision-making, GOAA seeks a modern PMIS solution specifically designed to support large-scale infrastructure and aviation capital programs.

The proposed PMIS platform shall be a highly configurable, low-code or no-code business process and workflow management solution that supports the full lifecycle of capital projects, from planning and authorization through design, construction, commissioning, and closeout. The system must enable process standardization, automate workflows, improve collaboration among stakeholders, and provide comprehensive visibility into project performance across the organization.

At a minimum, the PMIS shall:

Capital Program Management

• Serve as the centralized system of record for managing capital portfolios, programs, and projects throughout their entire lifecycle.

• Support strategic planning, capital planning, budgeting, forecasting, and project prioritization activities.

• Provide visibility into project status, milestones, performance metrics, and organizational objectives.

Project Controls and Performance Management

• Support comprehensive cost, budget, schedule, risk, issue, and change management processes.

• Provide Earned Value Management (EVM) capabilities and other project performance measurement tools.

• Facilitate forecasting, trend analysis, and proactive management of project risks and opportunities.

• Monitor and report key performance indicators (KPIs) across portfolios, programs, and projects.

Data Migration and Data Management

The PMIS solution shall provide comprehensive data migration capabilities to support the transition of historical and active capital project information from existing systems, databases, spreadsheets, and document repositories into the new platform.

• Support the migration of portfolio, program, project, financial, schedule, document, contract, risk, issue, and change management data from legacy systems.

• Facilitate migration from spreadsheets, file shares, document management systems, existing PMIS applications, ERP systems, and other enterprise platforms.

• Support phased and incremental migration approaches, as required by GOAA.

• Minimize disruption to ongoing capital projects and business operations during migration activities.

• Deliver a comprehensive Data Migration Plan that includes migration strategy, testing procedures, validation criteria, cutover activities, rollback procedures, and post-migration support.

Workflow Automation and Accountability

• Automate business processes through configurable workflows, approvals, notifications, and task management capabilities.

• Improve organizational accountability through clearly defined responsibilities, escalation procedures, and audit trails.

• Reduce reliance on manual processes, spreadsheets, and disconnected software applications.

Collaboration and Document Management

• Enable secure collaboration among internal departments, consultants, contractors, and other stakeholders.

• Provide centralized document storage, sharing, version control, and records management capabilities.

• Ensure efficient communication and information accessibility across project teams.

Executive Reporting and Decision Support

• Deliver real-time dashboards, analytics, and reporting for executives, program managers, project managers, and other stakeholders.

• Provide actionable insights that support informed decision-making and strategic planning.

• Offer configurable reporting capabilities that enable visibility into financial performance, schedule health, risk exposure, and overall portfolio performance.

Compliance and Financial Management

• Support governance, regulatory compliance, and audit requirements.

• Track and manage projects funded through multiple funding sources.

• Provide integrated financial management capabilities that support forecasting, budget controls, cost management, and performance reporting.

System Integration Requirements

The PMIS solution shall integrate with GOAA's enterprise technology ecosystem, including but not limited to:

• Oracle Enterprise Resource Planning (ERP) systems for financial management, budgeting, forecasting, and reporting.

• IBM Maximo Enterprise Asset Management (EAM) systems for asset lifecycle and maintenance management.

• Existing airport business applications, operational systems, and future enterprise platforms as required.

Through the implementation of a modern, integrated PMIS platform, GOAA seeks to improve organizational efficiency, enhance project delivery performance, strengthen governance and accountability, and establish a scalable foundation for managing its capital development program well into the future.

1.5. Tentative Timeline

Release Project Date: October 26, 2026

Pre-Submittal Meeting (Non-

Mandatory):

November 2, 2026, 11:00am

Microsoft Teams meeting

Join:

https://teams.microsoft.com/meet/2874

92995533230?p=JgHKnsu2EvHcarFzjB

Meeting ID: 287 492 995 533 230

Passcode: Mb2XE7TC

Question Submission Deadline: November 9, 2026, 2:00pm

Question Response (Addendum) Issue

Deadline:

December 1, 2026, 2:00pm

Response Submission Deadline: December 22, 2026, 2:00pm

Evaluation Committee Date: January 26, 2027 https://teams.microsoft.com/meet/287492995533230?p=JgHKnsu2EvHcarFzjB https://teams.microsoft.com/meet/287492995533230?p=JgHKnsu2EvHcarFzjB

Interviews (Optional): February 23, 2027

Conclusion of Negotiaions: March 25, 2027

Evaluation of Respondents' BAFOs by

Committee:

April 5, 2027

Aviation Authority Board Contract

Approval Date:

April 21, 2027

All dates and times are subject to change. All times are EST.

1.6. Characteristics of an ITN

An ITN is a solicitation process to select one or more vendors with which to commence negotiations for the procurement of goods and/or contractual services.

When the Aviation Authority determines that procurement by an Invitation to Bid or other solicitation method is not in the best interest of the Aviation Authority, and that negotiation may be necessary for the Aviation Authority to obtain the Best Value, the

ITN process may be used. In making the determination to utilize the ITN process, the

Aviation Authority may consider, in addition to any other relevant considerations, the following:

a. The simultaneous use of competitive negotiations would be beneficial to achieve the goal of Best Value within the Aviation Authority’s budget.

b. Price is an important factor but not significant enough by itself to justify award to a low bidder.

c. Limited availability of competition.

d. Non-standard products or services are required.

e. Multiple options for achieving the desired results likely exist.

f. A contract of high complexity may be required.

g. Uncertainty of the ability to obtain results within the budget or time requirements.

h. Requirements for needed products or services cannot be specified with certainty.

i. There is an emphasis on new technology with innovative solutions and a range of options are available.

j. Flexibility in determining the Best Value for the Aviation Authority is paramount.

k. Items or services are mission critical to the Aviation Authority’s operation.

l. A process of re-engineering may be required.

m. The marketplace is experiencing constant change and updated solutions are pertinent.

Professional and technical expertise and qualifications of firms are critical to the success of the project or provision of services.

2. GENERAL INFORMATION AND RESPONSE PREPARATION

2.1. Non-Discriminatory Legal Notices

a. The Aviation Authority does not discriminate upon the basis of any individual’s disability status. Anyone requiring reasonable accommodations as provided for in the Americans with Disabilities Act or Section 86.26, Florida Statutes, should contact the ADA Coordinator at 407-825-7105 as soon as possible, or at least one full business day prior to any scheduled meeting.

b. In accordance with Section 287.05701, Florida Statutes, the Aviation Authority may not request documentation of or consider a Respondent's social, political, or ideological interests when determining if the Respondent is a responsible

Respondent.

2.2. Reservation of Rights

a. The Aviation Authority reserves the right, in its sole discretion, to waive any informalities or irregularities of a Response, except that:

i. the Aviation Authority will not waive the requirement that a Response, complete in all material respects, be received by the Aviation Authority by the time and date specified in the Timeline for the receipt thereof, and

ii. the Aviation Authority will not consider any Response which does not conform in all material respects to the terms of this Solicitation including a commitment to execute the Contract by the Respondent, if applicable.

b. The Aviation Authority reserves the right to solicit from available sources relevant information concerning a Respondent’s past performance and may consider such information in its evaluation and selection of Respondents.

c. The Aviation Authority reserves the right to request clarification of information submitted in any Response, to require additional information from any

Respondent, or, in the Aviation Authority's sole discretion, to reject any or all

Respondents for any reason and to re-advertise or not to re-advertise the

Solicitation.

d. The Aviation Authority reserves the right to cancel an award to a Respondent upon due cause—i.e., misrepresentation, negligence, non-performance, etc. via written notice.

e. As the best interest of the Aviation Authority may require, the right is reserved to make award(s) by individual items, group of items, all or none, or a combination thereof.

f. All awards made as a result of this Solicitation shall conform to applicable policies of the Aviation Authority.

g. The Aviation Authority reserves the right at its sole discretion to increase, decrease, or delete any portion of the Scope of Services of the resulting Contract at any time, without cause.

h. The Aviation Authority shall have the right, but not the obligation, to award all or any portion of the services. The extent and Scope of the Services, along with the fees for such services, will be subject to final approval by the Aviation Authority.

The Aviation Authority intends, but is not obligated, to enter into a non-exclusive agreement with the highest ranked Respondent to perform the required Services described herein.

i. The Aviation Authority reserves its right to award any or all of the advertised services subject to the availability of funding.

2.3. Response Preparation

a. All prospective Respondents shall thoroughly examine and become familiar with the Solicitation package and carefully note the items which must be submitted with the Solicitation as detailed in Section 11: Vendor Questionnaire.

b. Submission of a Response shall constitute an acknowledgment that the

Respondent has read and understands the Solicitation Documents. The failure or neglect of a Respondent to receive or examine any Solicitation Document shall in no way relieve it from any obligations under its Response or the Contract. No claim for additional compensation will be allowed which is based upon a lack of knowledge or understanding of any of the Contract Documents or the scope of work.

c. It is the Respondent’s responsibility to incorporate all pertinent information effectively, to communicate the Respondent’s concept, and meet the requirements listed in the Solicitation. The Respondent should prepare its

Response simply and economically, providing a straightforward, concise description of the Respondent's capability to satisfy the conditions and requirements of this competitive solicitation based on the Evaluation Criteria which are the list of elements that the Aviation Authority deems most important to its evaluation process.

d. Sealed electronic responses will be received for this Solicitation through the

Greater Orlando Aviation Authority e-Procurement Platform located at https://procurement.opengov.com/portal/goaa. Once you have completed the free account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic response. By way of the https://procurement.opengov.com/portal/goaa

Platform, responses will be locked and digitally encrypted until the submission deadline passes.

e. All Responses must be received by the Aviation Authority as noted in the

Section 1: Introduction. All Responses timely received will be listed with the name of the Respondent during the Virtual Announcement of Respondents. The e-Procurement Platform will not allow for late submittals.

f. The time/date stamp clock located in the electronic submittal Platform shall serve as the official authority to determine lateness of any response.

g. If the Aviation Authority determines that it is necessary to change the dates or times prior to the due date, the change will be announced and posted on the e-

Procurement Platform.

h. The Aviation Authority shall not be responsible for delays caused by any occurrence. This shall include any delay as a result of a technology issue. Any late response shall not be accepted.

i. Responses submitted by hard copy, e-mail, or fax shall not be accepted.

Responses submitted outside of the designated Procurement Platform shall be rejected as non-responsive regardless of where and when they were received.

j. Respondents shall not be allowed to modify their responses after the opening time and date.

k. Unless otherwise noted, Respondents shall submit one Response only.

l. Each Respondent shall complete Section 11: Vendor Questionnaire. Please respond to each item individually, as applicable.

m. Unless otherwise directed, all uploaded files must be in PDF format. Do not upload zip files.

n. Regarding narrative responses: please do not include any links to any material, as those will not be reviewed. Additionally, images shall not be added into narrative fields, as those will not be reviewed.

2.4. Pre-Submittal Meeting

a. A Pre-Submittal Meeting will be held virtually for this solicitation.

b. The Teams Link can be found under Section 1: Introduction

c. The purpose of any Pre-Submittal Meeting is to review the solicitation (and any addenda) as published.

d. Attendance is not mandatory, but highly encouraged.

e. Attendees are expected to be familiar with the Solicitation Document.

2.5. Communications; Questions Regarding Specifications or Solicitation

Process and Receiving Responses

a. Any communication during the solicitation process must be submitted to the

Aviation Authority via the e-Procurement

Platform, https://procurement.opengov.com/portal/goaa. prior to the deadline for Questions. In the event of the OpenGov Q&A is not functional, please contact the Procurement Point of Contact specified in Section 1.

b. All answers to inquiries will be posted on the Aviation Authority e-Procurement

Platform. Respondents may also click “Follow” on this Solicitation to receive an email notification when answers are posted. It is the responsibility of the

Respondent to check the website for answers to inquiries.

c. In accordance with Administration Policies (Sections 180.01 and 180.03) policies, any communication directly or indirectly to seek to encourage any specific result in connection with an Aviation Authority selecting process, including but not limited to, written communications, any and all forms of electronic communications or messaging, including social media, oral communications either in person or by telephone, initiated by a Respondent or through a lobbyist, agent or third person, to any Aviation Authority staff and/or Committee/Board member who is a member of any committee constituted for the purposes of ranking Solicitations, making recommendations or making an award, is prohibited from the time that the Solicitation is released to the time that the award is made. A copy of the Administration Policies (Sections 180.01 and

180.03) is available upon request from the Manager of Board Services.

d. All firms are hereby placed on notice that the Aviation Authority Board and staff shall not be contacted about this Solicitation. Firms and their agents shall not contact members of the Aviation Authority staff and/or Committee/Board member (with the exception of designated Procurement Agent and the office of

Small Business Opportunity and Exchange. An appropriate official or employee of the Aviation Authority may initiate communication with a Respondent in order to obtain information or clarification needed to develop a proper and accurate review of the Response. Any official communication from a Respondent during the solicitation process should be submitted via the e-Procurement Platform as directed during the solicitation process. Failure to adhere to these requirements may result in and Aviation Authority Board action to disqualify your firm from consideration of award.

e. Requests for interpretation, clarification or correction of solicitation documents, forms or other material in the solicitation must be made in writing via the e-https://procurement.opengov.com/portal/goaa

Procurement Platform during the Question-and-Answer period. Questions or issues raised at the Pre-Submittal Meeting or during the Question-and-Answer period, which, in the Aviation Authority's discretion, necessitate changes to the solicitation documents, will be the subject of an addendum to this solicitation at the conclusion of the question period, and will be made available through the e-

Procurement Platform. It is the responsibility of each Respondent to ensure that it has received and reviewed any and all such solicitation(s) or addendum.

f. Per F.S. 287.057 (25): Respondents to this solicitation or persons acting on their behalf may not contact, between the release of the solicitation and the end of the 72-hour period following the agency posting the notice of intended award, excluding Saturdays, Sundays, and state holidays, any employee or officer of the executive or legislative branch concerning any aspect of this solicitation, except in writing to the procurement officer or as provided in the solicitation documents.

Violation of this provision may be grounds for rejecting a response.

2.6. Silence of Specifications

The apparent silence of the specifications and any supplemental specifications as to any details or the omission from same of any detailed description concerning any point, shall be regarded as meaning that only the best commercial practices are to prevail and only materials of first quality be provided.

2.7. Incurred Cost

The Aviation Authority is not liable for any cost incurred by any Respondent prior to an award. Costs for developing a response is entirely the obligation of the Respondent and shall not be chargeable in any manner to the Aviation Authority.

2.8. Lobbying Statement

Do not contact Aviation Authority Board members or Staff concerning this

Solicitation. Public meetings and public deliberations of the Evaluation Committee are the only acceptable forum for the evaluation of any Responses received pursuant to this

Solicitation. Written correspondence concerning questions may be submitted to the Procurement Services Department via the e-Procurement Platform during the specified period. Any official communication from a Respondent during the Solicitation process should be submitted in writing to the Greater Orlando Aviation Authority via the e-Procurement Platform as directed in the Solicitation. Copies of the Administration

Policies (Sections 180.01 and 180.03) are available at https://flymco.com/airport-business/policies/. Failure to adhere to these requirements could result in action to disqualify your firm from consideration of award. Respondents to this Solicitation or persons acting on their behalf may not contact, between the release of the Solicitation and the end of the 72-hour period following the agency posting the notice of intended https://flymco.com/airport-business/policies/ award, excluding Saturdays, Sundays, and state holidays, any employee or officer of the executive or legislative branch concerning any aspect of this Solicitation, except in writing to the procurement officer or as provided in the Solicitation documents. Violation of this provision may be grounds for rejecting a response. (F.S.

287.057 (25))

2.9. Withdrawal of Responses

No Response may be withdrawn after the scheduled Response opening time for a period of 180 days. Any Respondent withdrawing or attempting to withdraw its Response prior to the expiration of the 180 day period shall be obligated to reimburse the Aviation

Authority for all its costs incurred in connection with such withdrawal or attempted withdrawal including, without limitation, any increased costs for procuring the goods or services from another Respondent or all costs of advertising and re-procuring the goods or services, and all attorneys’ fees, in addition to payment of the Aviation Authority’s other damages. A Respondent’s submission shall be deemed the Respondent’s acknowledgment of an agreement to the provisions of this Section.

2.10. Public Meetings

Public meetings are posted on the Aviation Authority's website:

https://flymco.com/airport-business/sunshine-meetings/. Attendance by all interested

Parties is encouraged.

2.11. Public Records / Confidential and Exempt Information

The Greater Orlando Aviation Authority (“Aviation Authority”) is subject to Chapter 119, Florida Statutes, and Article I, section 24 of the Florida Constitution. Accordingly, all materials submitted in response to this Invitation to Negotiate (“ITN”) are subject to public disclosure unless confidential or exempt under applicable law.

If the Respondent contends that any portion of its bid, proposal, response, or submission contains confidential or exempt information, including trade secret information, the Respondent shall provide:

a. one complete, unredacted copy clearly identifying and conspicuously labeling all information claimed to be confidential or exempt; and

b. one redacted copy of the identical submission suitable for public records production.

For each redaction or claim of exemption, the Respondent shall cite the specific legal authority supporting the asserted exemption. Generalized claims of confidentiality or proprietary status are insufficient and will not be considered properly identified by the

Respondent.

https://flymco.com/airport-business/sunshine-meetings/

Pricing and other financial terms are generally not confidential or exempt from public disclosure following bid or proposal opening or notice of intended award, except as otherwise provided by law.

The Aviation Authority will endeavor in good faith to maintain information properly identified by the Respondent as confidential or exempt; however, the Aviation Authority shall independently determine whether any submitted information is subject to disclosure under applicable law.

The Aviation Authority shall not be liable for the disclosure of information that:

a. was not properly identified by the Respondent;

b. is not confidential or exempt under applicable law; or

c. the Aviation Authority determines must be disclosed pursuant to law, court order, or administrative determination.

If the Aviation Authority relies upon the Respondent’s asserted claim of confidentiality or exemption in withholding or redacting records responsive to a public records request, the Respondent shall, upon request, provide legal and factual support for the asserted exemption and shall indemnify, defend, and hold harmless the Aviation Authority, its board members, officers, employees, agents, and representatives from and against any claims, damages, penalties, costs, or attorneys’ fees arising from the Aviation

Authority’s reliance on the Respondent’s asserted exemption or confidentiality claim.

Nothing herein obligates the Aviation Authority to assert or defend any claimed exemption from disclosure on behalf of the Respondent.

2.12. Proprietary Information

Any work product produced as part of the Agreement will become the exclusive property of the Aviation Authority.

2.13. Independent Consultant Status and Compliance with the Immigration

Reform and Control Act

Respondent is and shall remain an independent Consultant and is neither agent, employee, partner, nor joint venture of Aviation Authority. Respondent acknowledges that it is responsible for complying with the provisions of the Immigration Reform and

Control Act of 1986 located at 8 U.S.C. 1324, et seq. and regulations relating thereto, as either may be amended from time to time. Failure to comply with the above provisions shall be considered a material breach of the Agreement.

2.14. Code of Ethics and Business Conduct Policy

The Aviation Authority has adopted a Code of Ethics and Business Conduct Policy #

101-02, which addresses the obligation of the Aviation Authority’s Board members and employees to follow the Florida Statutes in reference to these issues. This includes, but is not limited to, the obligations of the Aviation Authority’s Board members and employees with respect to having an interest in business entities, outside employment, gratuities, divulgence of information, unauthorized compensation and acceptance of gifts. Please be aware that any violation of this policy by a Respondent and/or any attempt to influence an Aviation Authority Board member or employee to violate the policy is sufficient cause for the denial of the right of the Respondent to Respond on any

Contract or sell any materials, supplies, equipment, or services to the Aviation

Authority for a period of time that is determined by the Chief Executive Officer. A copy of this policy (101.02) is available on the Aviation Authority’s website: https://flymco.com/airport-business/policies/

2.15. Performance Management System (Procurated/Canary)

a. The Aviation Authority shall, at regular intervals, monitor the performance of

Respondent to determine whether the work to be performed under the Contract has in fact been accomplished to Aviation Authority’s satisfaction and/or completed in a timely manner.

b. The Aviation Authority shall notify the Respondent of any specific services that are unsatisfactory to the Aviation Authority, and if the Respondent has not addressed such item or items set forth in the notice to the Aviation Authority’s satisfaction within the time frame set forth in the Aviation Authority’s notice, the

Aviation Authority in addition to all other rights provided under this Contract or by law or equity, may either remedy such unsatisfactory services itself or through a third party and the cost of providing the remedial services shall be deducted from the Respondent’s invoice.

c. The Aviation Authority is implementing a structured vendor performance management process to support continuous improvement, accountability, and strong supplier relationships. The Aviation Authority has partnered with

Procurated to utilize its vendor performance management platform, Canary, a tool designed to collect meaningful feedback, improve supplier performance, and enhance customer satisfaction. The Aviation Authority will use the vendor performance management platform to collect feedback regarding Supplier performance. Performance evaluations may be conducted quarterly, annually, or as needed, based on contract duration, scope of work, and operational requirements.

d. Supplier performance may be evaluated across multiple categories (Customer

Service, Pricing and Value, Quality of Goods or Services, Timeliness and

Responsiveness).

e. The Aviation Authority may consider a Respondent’s past performance, including references and any available performance ratings or feedback from other agencies, including those reflected in vendor performance management platforms such as Canary in determining future contracting opportunities, contract renewals, amendments, extensions, and overall supplier relationship management. The Aviation Authority will use performance feedback to:

o Identify strengths and opportunities for improvement o Address performance concerns during business review meetings o Initiate corrective action discussions when immediate or material performance issues arise

Supplier Registration Requirement:

a. As a condition of award, the Respondent shall be required to register for and maintain an active account in the Aviation Authority’s designated vendor performance management platform, Procurated’s Canary platform, for the duration of the performance period. Supplier registration and use of the platform will be provided at no cost to the Supplier.

b. The Respondent will be required to create a profile on Procurated so you can log in to see your feedback. We also recommend that you use the Review Requester feature in Canary. It allows you to easily request feedback from the people who use your products and services every day. These insights give you a clear view of your performance, while also helping you showcase your strengths to current and future customers. Please note that the information and data uploaded to

Canary may be subject to Florida’s public records laws.

c. Suppliers may learn more about the Canary platform and its benefits at:

https://home.procurated.com/resources/suppliers-your-government-customers-are-using-canary/

d. For questions related directly to the Procurated platform, Suppliers may contact:

suppliersupport@procurated.com

2.16. Appeal of Solicitation Requirements

Any potential Respondent that is adversely affected by the requirements or specifications of this Solicitation may file an appeal in writing to the Senior Vice

President of Procurement Services, Kelly.loll@goaa.org, within 72 hours after the https://urldefense.com/v3/__https:/www.loom.com/share/df21afeaff4d406b9f0cbab7a8420150?sid=666d10c5-5f3e-4c3f-b1f7-b1840faea36c__;!!LBFcHN3WCgnqDQ!ij61DzodHPxDdLaAy6vlFfK_3vZWCWo4DzGBgmAbLULu1UWz_NrD87IVwxBsXAvBUn97p2oNpvYiiudy2iSuuz4E15DZkQ$ https://urldefense.com/v3/__https:/home.procurated.com/resources/suppliers-your-government-customers-are-using-canary/__;!!LBFcHN3WCgnqDQ!ij61DzodHPxDdLaAy6vlFfK_3vZWCWo4DzGBgmAbLULu1UWz_NrD87IVwxBsXAvBUn97p2oNpvYiiudy2iSuuz7syhoGnw$ https://urldefense.com/v3/__https:/home.procurated.com/resources/suppliers-your-government-customers-are-using-canary/__;!!LBFcHN3WCgnqDQ!ij61DzodHPxDdLaAy6vlFfK_3vZWCWo4DzGBgmAbLULu1UWz_NrD87IVwxBsXAvBUn97p2oNpvYiiudy2iSuuz7syhoGnw$ mailto:suppliersupport@procurated.com posting of the Solicitation. Failure to do so shall constitute a waiver of all rights to appeal the contents of the Solicitation.

3. SCOPE OF WORK / SPECIFICATIONS

3.1. Overview

a. The Greater Orlando Aviation Authority (GOAA) seeks a cloud-based Project

Management Information System (PMIS) to oversee its Capital Improvement

Plan (CIP). The Contractor shall deliver a turnkey solution that is configurable, integrates with GOAA’s existing systems, and enables the Authority to establish a single source of truth/accountability for managing multiple portfolios, programs and projects. The system will enhance planning, execution, monitoring, reporting, risk mitigation, financial control, and strategic alignment through integrated modules.

b. The Contractor shall deliver a fully functional PMIS that:

1. Enhances visibility into portfolio, program, and project performance.

2. Provides real time analytics and enterprise dashboards.

3. Enables cross departmental collaboration and workflow-driven execution.

4. Drives accountability through automated workflows and task notifications.

5. Supports lifecycle management of all project types.

6. Enables data driven decision making.

7. Ensures compliance with financial, regulatory, and governance requirements.

8. Integrates seamlessly with GOAA’s Oracle ERP, other major ERPs and airport systems

9. Supports multi source funding and financial controls.

10. Eliminates manual, file based processes.

3.2. Statement of Needs and Objectives

a. GOAA seeks a comprehensive PMIS to support the planning, execution, monitoring, control, and reporting of its multi-year CIP for the Orlando

International Airport and Executive Airport. The PMIS shall provide integrated portfolio, program, and project management capabilities to manage interdependent processes, projects, and stakeholders, and shall include the following functional requirements:

1. Enable GOAA to move away from highly manual, local file management;

2. Drive team collaboration and efficiencies across departments and stakeholders through streamlined processes;

3. Drive accountability through task-based notifications and workflows;

4. Provide high visibility of program and project status to appropriate members of the organization.

5. Streamline project, program, and portfolio lifecycle management.

6. Provide real-time visibility into performance metrics via enterprise level performance dashboards and reporting

7. Enable data-driven decision-making and strategic alignment.

8. Ensure regulatory and financial compliance.

9. Integrate financial data with Oracle ERP for budget control and forecasting.

10. Able to track funding source down to the PO line.

11. Track and manage various funding and financial sources.

12. Integrate with existing airport tools and systems as necessary.

b. The Contractor shall design, configure, integrate, test, and deploy a PMIS that:

1. Serves as the authoritative system of record for all project data.

2. Supports project intake, prioritization, planning, execution, monitoring, control, and closeout.

3. Enables enterprise portfolio management and capital improvement program

(CIP) oversight.

4. Provides transparent financial visibility, including budget, actuals, forecasts, and funding source tracking.

5. Facilitates consistent governance and standardized business processes.

6. Supports GOAA employees, consultants, contractors, and external stakeholders as required.

3.3. Scope of Services

a. Requirements Gathering & Analysis

1. Stakeholder interviews and workshops

2. Documentation of functional and technical requirements

3. Assessment of existing systems and integration needs

b. System Design & Architecture

1. Scalable, modular, and secure architecture

2. Workflow definitions for projects, programs, and portfolios

3. Role-based access and permissions

4. Infrastructure compatibility

c. Development & Configuration

1. Core PMIS modules to include but not be limited to:

i. Project Management

ii. Program Management

iii. Portfolio Management

iv. Risk Management

v. Financial Integration with Oracle ERP

vi. Planning & Scheduling

vii. Procurement Management

viii. CIP Development

ix. Budgeting & Cost Management

x. Resource Management

xi. Performance Management and Reporting

xii. Design Management

xiii. Document Control

xiv. Quality Management

xv. Health, Safety, and Environment

xvi. Reporting & Dashboards

d. Integration

1. Oracle ERP Integration:

i. Sync project budgets, actuals, and forecasts

ii. Automate cost tracking and invoice reconciliation

iii. Enable real-time financial reporting and variance analysis to include multiple funding sources

2. Geographic Information System

3. Enterprise Asset Management system (Maximo)

4. Building Information Modeling system

e. Testing & Quality Assurance

1. Functional, performance, and security testing

2. User acceptance testing (UAT)

3. Compliance validation

f. Training & Change Management

1. Development of training materials

2. End-user training sessions

3. Change management support for adoption

g. Deployment & Support

1. Production deployment

2. Post-deployment support and maintenance

3. Helpdesk and technical support services

3.4. Project Management Module

a. Objectives

1. Provide robust tools for managing the GOAA’s portfolio of projects, programs and initiatives, and individual projects from project intake/initiation to closeout.

2. Ensure executive level visibility and consistent execution across all airport operations projects.

b. Features

1. Project Lifecycle Management: Initiation, planning and forecasting, execution, monitoring, and closeout.

2. Work Breakdown Structures (WBS)

3. Task and Milestone Tracking

4. Gantt Charts and Timeline Views

5. Resource Assignment and Utilization

6. Budget and Cost Tracking

7. Change Management and Issue Tracking

8. Collaboration Tools: Comments, file sharing, and notifications

9. Project Templates and Standardization

c. Integration

1. Link projects to portfolios, risks, and financial data

2. Sync with Oracle ERP for budget and cost control

3. Align with strategic planning and capital improvement programs

3.5. Project Intake and Demand Management Module

a. The Contractor shall configure a centralized project intake and demand management capability that serves as the authoritative entry point for all project requests.

b. The PMIS shall provide configurable intake forms to capture:

1. Business justification

2. Strategic alignment

3. Estimated cost, funding source, and timeline

4. Risk and operational impact

c. Include a prioritization and scoring engine based on configurable criteria such as:

1. Strategic alignment

2. Regulatory requirements

3. Risk mitigation

4. Financial impact

d. Enable pipeline visibility for all submitted, approved, deferred, and rejected projects.

e. Support scenario planning and prioritization modeling for portfolio decision-making.

3.6. Program Management Module

a. Features

1. Program Dashboard

2. Program Roadmaps

3. Performance Analytics

4. KPI Reporting

3.7. Risk Management Module

a. The Contractor shall implement:

1. Risk register and categorization.

2. Impact and likelihood scoring.

3. Mitigation planning and responsibility assignment.

4. Alerts, notifications, and audit trails.

5. Risk dashboards and reporting.

3.8. Contract and Vendor Management Module

a. The contractor shall implement:

1. Vendor change order management,

2. Vendor contract lifecycle and performance through the life of a project

3.9. Deliverables

a. Requirements Specification Document

b. System Design Blueprint

c. Configured PMIS with Project, Portfolio, Risk, and Financial Modules

d. Integration Interfaces (Oracle ERP)

e. Test Plans and Results

f. User Training, Training Materials, and User Manuals

g. Final Deployment Report

3.10. System Timeline for System Intergration

It is the Aviation Authority's desire to have the selected PMIS to achieve a successful

Go-Live within the suggested timeline below:

Timeframe Request

Month 1-2 Requirements & Design

Month 3-6 Development & Integration

Month 7-8 Testing & Training

Month 9-12 Deployment & Support

3.11. Roles and Responsibilities

a. Vendor: End-to-end delivery of PMIS

b. Airport Project Management Office: Oversight, stakeholder engagement, and approvals

c. IT Department: Infrastructure and integration support

d. Finance Department: Oracle ERP coordination and validation

e. Executive Leadership: Portfolio governance and strategic alignment

3.12. Deliverables

a. The Contractor shall provide the following minimum deliverables:

1. Requirements Specification Document

2. System Design Blueprint

3. Fully Configured PMIS Platform

4. Project, Portfolio, Risk, and Financial Modules

5. Oracle ERP Integration Interfaces

6. Test Plans, Scripts, and Final Testing Results

7. User Manuals, Training Materials, Configuration Documentation

8. Final Deployment and Transition Report

3.13. PMIS Turnkey Delivery Scope

a. Turnkey Delivery & Teaming

b. The enterprise Project Management Information System (PMIS) shall be delivered on a fully turnkey basis by a proposing team consisting of the PMIS software OEM and an authorized, OEM-certified System Integrator. The OEM and

Integrator shall submit as a single, unified team and shall be jointly responsible for all aspects of PMIS delivery.

c. The OEM–Integrator team shall provide end-to-end responsibility for solution architecture, environment provisioning, configuration, workflow design, integration, reporting, data migration, security configuration, testing, deployment, training, documentation, post-go-live stabilization, and warranty support.

d. Single Point of Accountability

1. The proposing team shall designate a single prime contractor and a single executive point of accountability responsible for all contractual obligations, deliverables, schedule adherence, quality, system performance, and outcomes.

2. Under no circumstances shall the Owner be required to manage, coordinate, or arbitrate responsibilities between the OEM and the System Integrator. Any division of responsibilities between team members shall be fully transparent to the Owner and shall not diminish the team’s collective accountability.

e. OEM Commitment & Certification

1. The PMIS OEM shall be an active, named participant on the proposing team and shall provide written certification confirming:

2. Authorization of the Integrator to implement the proposed PMIS platform(s)

3. Product licensing and subscription rights

4. Upgrade and patch eligibility

5. Product roadmap alignment

6. Technical escalation and support commitment for the duration of implementation and warranty

f. Platform Configuration & Functional Readiness

1. The PMIS solution shall be configured, not merely installed, to meet the

Owner’s business processes, governance standards, and reporting requirements. The system shall be delivered in a state of operational readiness, not as a generic or out-of-the-box configuration.

g. Integration & Data Management

1. The OEM–Integrator team shall design, build, test, and support all required integrations between PMIS platforms and external systems, which may include ERP, financial systems, document management systems, GIS, asset management systems, and scheduling tools.

2. All data migration activities—including legacy data assessment, cleansing, transformation, validation, and reconciliation—shall be included as part of the turnkey scope unless explicitly excluded.

h. Testing, Acceptance, and Go-Live

1. The OEM–Integrator team shall support all phases of system testing, including system testing, integration testing, and user acceptance testing

(UAT). Go-live shall not occur until the PMIS has successfully met agreed-upon acceptance criteria and received written Owner approval.

2. Post-go-live stabilization support shall be included to ensure continuity of operations, defect resolution, and knowledge transfer.

i. Training, Documentation & Knowledge Transfer

1. Comprehensive role-based training shall be provided for administrators, power users, and end users across all PMIS platforms. Training materials, system configuration documentation, integration diagrams, and administrative guides shall be delivered in formats suitable for long-term

Owner use and system sustainability.

2. The Contractor shall ensure the PMIS is intuitive, accessible, and designed for enterprise-wide adoption.

j. The PMIS shall:

1. Provide role-based user interfaces tailored to different user groups

(executives, project managers, field staff, finance, etc.)

2. Support mobile access for field personnel and remote users

3. Minimize manual data entry through automation and integrations

4. Provide user adoption tracking metrics, including system usage and workflow completion rates

5. Include ongoing user support and optimization recommendations

k. Joint and Several Responsibility

1. The OEM and System Integrator shall be jointly and severally liable for the successful delivery of the PMIS solution. Any failure of the PMIS to meet contractual requirements shall be the responsibility of the proposing team, regardless of internal role delineation.

l. No Owner Dependency

1. The solution shall not rely on Owner-provided resources, custom development, or third-party tools unless explicitly identified, approved, and contractually documented.

m. Configuration Ownership

1. All configured objects, workflows, reports, and integrations shall become the property of the Owner upon acceptance.

n. Upgrade Compatibility

1. All configurations and integrations shall be compatible with OEM-supported upgrades and patches without requiring re-implementation.

2. All configured objects, workflows, reports, and integrations shall become the property of the Owner upon acceptance.

o. Service Levels & Performance Requirements

1. The Contractor shall meet defined service-level requirements for system performance, support, and delivery.

p. At a minimum, the Contractor shall:

1. Provide system availability of ≥ 99.9% uptime (excluding approved maintenance windows)

2. Meet defined incident response and resolution times, including:

3. Critical issues: response within 1 hour

4. High priority: response within 4 hours

5. Provide performance benchmarks for system responsiveness and data processing

6. Establish implementation success metrics, including schedule adherence and system functionality

7. Be subject to performance-based penalties or service credits for failure to meet SLAs

q. Cybersecurity & Compliance

1. The Contractor shall ensure that the PMIS meets all applicable cybersecurity and regulatory requirements.

r. The PMIS shall:

1. Comply with NIST cybersecurity framework and applicable TSA security directives

2. Support Multi-Factor Authentication (MFA) and Single Sign-On (SSO) integration

3. Encrypt data in transit and at rest

4. Maintain comprehensive audit logs of all system activity

5. Support regular security testing, vulnerability management, and patching

s. Success Criteria:

1. Full functionality including project, program, portfolio, risk, and financial integration

2. High user adoption and satisfaction

3. Seamless Oracle ERP integration

4. Flexible configurations

5. On-time, on-budget delivery

6. Strategic alignment and measurable performance improvement

3.14. Data Handling, Artificial Intelligence and Innovation

Any use of the Aviation Authority data for product training, benchmarking, artificial intelligence, machine learning, analytics unrelated to the Aviation Authority’s use of the

System, or other secondary purposes shall require the Aviation Authority’s prior written approval. All the Aviation Authority data, operational data, system configuration data, content, logs, reports, metadata, and information generated by or processed through the System shall remain the property of the Aviation Authority unless otherwise agreed in writing.

Artificial Intelligence, Automation, and Emerging Technology Governance

a. If Respondent proposes artificial intelligence, machine learning, generative AI, translation AI, predictive analytics, automated content generation, automated decision-making, anomaly detection, optimization models, or similar capabilities, Respondent shall clearly describe the proposed use case, business value to the Aviation Authority, data used, level of human review, ability to configure or disable the capability, and associated cybersecurity, privacy, operational, accessibility, intellectual property, and governance considerations.

b. The Aviation Authority welcomes innovative capabilities that improve passenger communication, operational awareness, accessibility, content management, disruption response, multilingual communication, analytics, and system performance. However, any such capability must be implemented in a manner that is secure, explainable, auditable, governed, and aligned with the Aviation

Authority policies. The Aviation Authority may negotiate specific governance requirements, testing requirements, approval workflows, human review requirements, data usage restrictions, publication controls, and disablement rights for any artificial intelligence, automation, or emerging technology capability.

Cybersecurity…