PROJECT DESCRIPTION_WA FLAP JEFFER 134309(2).pdf

PDF 154 KB Posted

Attached to
WA FLAP JEFFER 134309(2), Two Trout Creek Culvert Replacement
Solicitation number
69056725B000014
Issued by

About this file

This document is a project specification for the WA FLAP JEFFER 134309(2), Two Trout Creek Culvert Replacement project located in Jefferson County, Washington State. The project involves constructing an Aquatic Organism Passage (AOP) Culvert at Oil City Road MP 0.5 to replace a failing culvert that blocks fish passage in a tributary to the Hoh River. The project is 0.1 miles long, with an estimated price range between $2,000,000 and $5,000,000, and is tentatively scheduled for solicitation in Fall/Winter 2025 with a fixed completion date in Winter 2026.

The project scope includes multiple divisions of work: Project Requirements (construction survey, quality control, sampling, and testing), Earthwork (clearing, grubbing, excavation, geotextile stabilization), Slope Reinforcement, and Incidental Construction. Specific tasks include installing 1,200 linear feet of silt fence, 2,600 linear feet of fiber roll, 52 linear feet of reinforced concrete box culvert, 200 linear feet of guardrail, turf establishment, environmental design elements like root wads and streambed material, and temporary traffic control measures. The project will use FP-24 specifications and US Customary Units.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: WA FLAP JEFFER 134309(2), Two Trout Creek Culvert Replacement

WA FLAP JEFFER 134309(2), Two Trout Creek Culvert Replacement Jefferson County, Washington State

This work consists of constructing an Aquatic Organism Passage (AOP) Culvert at Oil City Road MP 0.5 to replace a failing culvert that blocks fish passage in a tributary to the Hoh River

Project Location: This project is located approximately 16 Miles South of Forks city, Jefferson County, Washington State.

Project Length: 0.1 Miles

Estimated Price Range: Between $2,000,000 and $5,000,000

Tentative Solicitation Date: Fall/Winter 2025

Tentative Fixed Completion Date: Winter 2026

DESCRIPTION OF WORK in US CUSTOMARY UNITS

USING FP-24 SPECS

O ne

Sc he du le h

N am e DIVISION 150 – Project Requirements

152 Construction Survey & Staking (yes/no) Yes

153 Contractor Quality Control and Assurance (yes/no) Yes

154 Contractor Sampling & Testing (yes/no) Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no)

Yes

157 Soil Erosion Control (Silt Fence) 1200 LNFT

157 Soil Erosion Control (Fiber Roll) 2,600 LNFT

157 Soil Erosion Control, Check Dam (Fiber Roll) 12 EACH DIVISION 200 – Earthwork 201 Clearing & Grubbing 1,000 SQYD

204 Roadway Excavation 1,770 CUYD

207 Stabilization Geotextile 2,200 SQYD DIVISION 250 – Slope Reinforcement and Retaining Walls

Project Name: WA FLAP JEFFER 134309(2), Two Trout Creek Culvert Replacement

251 Riprap, Class 4 70 CUYD

O ne he du le h

N am e

251 Riprap Ditch, Class 1 550 LNFT 30201-2000 Roadway Aggregate, Method 2 650 CUYD DIVISION 600 – Incidental Construction

602 Reinforced Concrete Box Culvert (18' Span, 12' Rise) 52 LNFT

617 Guardrail System G4, Type 4, Class B Steel Post 200 LNFT

617 Terminal System, Type MGS Tangent 4 EACH

622 Rental Equipment (yes/no) No

623 General Labor (yes/no) No

625 Turf Establishment 900 SQYD

626 Plants LPSM

635 Temporary Traffic Control – Portable Changeable Message Signs 1 EACH

635 Temporary Traffic Control – Construction Sign 4 EACH

647 Environmental Design, Root Wad 14 EACH

647 Environmental Design, Streambed Material 340 CUYD