This is a Federal presolicitation notice for the Gifford Pinchot National Forest Emergency Road and Forest Operations (ERFO) Repairs 2022 project. The work involves excavation, grading, aggregate and roadway reconditioning, drainage, and permanent traffic control on a 0.75-mile section of road located 14 miles southeast of Randle, Washington. The tentative solicitation date is Winter 2026/2027, with a tentative fixed completion date of Fall 2028. The estimated price range is $700,000 to $2,000,000.

The scope of work includes clearing and grubbing (3.87 acres total), excavation and embankment (7,000 cubic yards), roadway obliteration (770 square yards), riprap installation (Class 2 riprap and ditch work), minor crushed aggregate (1,800 cubic yards), road reconditioning (2,000 square yards), reinforcing steel (70 pounds), minor concrete structures (3 cubic yards), and drainage infrastructure including pipe culverts (18-inch and 24-inch), inlets, and corrugated metal spillways. Additional requirements include soil erosion and sediment control measures (fiber roll and check dams), topsoil application (4-inch depth at 9,920 square yards), turf establishment via mulching (14,000 square yards), permanent and temporary traffic control devices, construction survey and staking, contractor quality control and assurance, sampling and testing, and construction schedules. Rental equipment and general labor are specified as required contract line items.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA ERFO FS GIFPN603 2022-1(1), Gifford Pinchot ERFO Repairs 2022

Gifford Pinchot National Forest

The work consists of excavation, grading, aggregate and roadway reconditioning, drainage, and permanent traffic control.

Project length: 0.75 miles

Tentative Fixed Completion Date: Fall 2028

(Once solicitation is issued, see SF1442 Continuation, Block 11 for exact date.)

Tentative Solicitation Date: Winter 2026/2027

Estimated Price Range: $700,000 to $2,000,000

Location: 14 miles SE of Randle, WA

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-24

B as e S ch ed u le

DIVISION 150 – Project Requirements

152 Construction Survey & Staking (yes/no) Yes

153 Contractor Quality Control and Assurance (yes/no) Yes

154 Contractor Sampling & Testing (yes/no) Yes

155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes

157 Soil Erosion & Sediment Control (erosion control devices)

Fiber Roll 8,110 LNFT Check Dam 22 EA

DIVISION 200 – Earthwork

201 Clearing & Grubbing 3.7 ACRE

202 Additional Clearing & Grubbing (clearing & grubbing) 0.17 ACRE

204 Excavation & Embankment Excavation 7,000 CUYD

211 Roadway Obliteration 770 SQYD

DIVISION 250 – Slope Reinforcement and Retaining Walls

251 Riprap Placed Class 2: 25 CUYD Riprap Ditch: 640 LNFT

B as e S ch ed u le

DIVISION 300 – Aggregate and Base Courses

302 Minor Crushed Aggregate 1,800 CUYD

303 Road Reconditioning 2,000 SQYD

DIVISION 550 – Bridge Construction

554 Reinforcing Steel 70 LB

DIVISION 600 – Incidental Construction

601 Minor Concrete Structures (concrete – minor structures) 3 CUYD

602 Culverts & Drains (indicate one or both) 18-inch Pipe Culvert 35 LNFT 24-inch Pipe Culvert 190 LNFT

End Section 10 EA

604 Manholes, Inlets, & Catch Basins(culverts & drains) (indicate which) Inlet, FLH TYPE 7A: 1 EA

605 Underdrains, Sheet Drains & Pavement Edge Drains (culverts & drains) (indicate which)

606 Corrugated Metal Spillways Spillway Assembly 1 EA Pipe Anchor Assembly 3 EA

622 Rental Equipment (yes/no) Yes

623 General Labor (yes/no) Yes

624 Topsoil (landscaping & related items) 4-inch Depth 9,920 SQYD

625 Turf Establishment (indicate seeding or mulching separately) Mulching 14,000 SQYD

633 Permanent Traffic Control (traffic control devices) Sign System 5 EA

635 Temporary Traffic Control Barricade Type 3: 6 EA Construction Sign 168 SQFT