PROJECT DESCRIPTION_WA ERFO FS GIFPN603 2022-1(1).pdf
PDF 263 KB Posted
- Solicitation number
- 69056726B000013
About this file
This is a Federal presolicitation notice for the Gifford Pinchot National Forest Emergency Road and Forest Operations (ERFO) Repairs 2022 project. The work involves excavation, grading, aggregate and roadway reconditioning, drainage, and permanent traffic control on a 0.75-mile section of road located 14 miles southeast of Randle, Washington. The tentative solicitation date is Winter 2026/2027, with a tentative fixed completion date of Fall 2028. The estimated price range is $700,000 to $2,000,000.
The scope of work includes clearing and grubbing (3.87 acres total), excavation and embankment (7,000 cubic yards), roadway obliteration (770 square yards), riprap installation (Class 2 riprap and ditch work), minor crushed aggregate (1,800 cubic yards), road reconditioning (2,000 square yards), reinforcing steel (70 pounds), minor concrete structures (3 cubic yards), and drainage infrastructure including pipe culverts (18-inch and 24-inch), inlets, and corrugated metal spillways. Additional requirements include soil erosion and sediment control measures (fiber roll and check dams), topsoil application (4-inch depth at 9,920 square yards), turf establishment via mulching (14,000 square yards), permanent and temporary traffic control devices, construction survey and staking, contractor quality control and assurance, sampling and testing, and construction schedules. Rental equipment and general labor are specified as required contract line items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| wa-ef-gifpn2022-1-1_Preliminary PLAN.pdf | ||
| Prelim Letter_WA ERFO GIFPN603 2022-1(1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WA ERFO FS GIFPN603 2022-1(1), Gifford Pinchot ERFO Repairs 2022
Gifford Pinchot National Forest
The work consists of excavation, grading, aggregate and roadway reconditioning, drainage, and permanent traffic control.
Project length: 0.75 miles
Tentative Fixed Completion Date: Fall 2028
(Once solicitation is issued, see SF1442 Continuation, Block 11 for exact date.)
Tentative Solicitation Date: Winter 2026/2027
Estimated Price Range: $700,000 to $2,000,000
Location: 14 miles SE of Randle, WA
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-24
B as e S ch ed u le
DIVISION 150 – Project Requirements
152 Construction Survey & Staking (yes/no) Yes
153 Contractor Quality Control and Assurance (yes/no) Yes
154 Contractor Sampling & Testing (yes/no) Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes
157 Soil Erosion & Sediment Control (erosion control devices)
Fiber Roll 8,110 LNFT Check Dam 22 EA
DIVISION 200 – Earthwork
201 Clearing & Grubbing 3.7 ACRE
202 Additional Clearing & Grubbing (clearing & grubbing) 0.17 ACRE
204 Excavation & Embankment Excavation 7,000 CUYD
211 Roadway Obliteration 770 SQYD
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Riprap Placed Class 2: 25 CUYD Riprap Ditch: 640 LNFT
B as e S ch ed u le
DIVISION 300 – Aggregate and Base Courses
302 Minor Crushed Aggregate 1,800 CUYD
303 Road Reconditioning 2,000 SQYD
DIVISION 550 – Bridge Construction
554 Reinforcing Steel 70 LB
DIVISION 600 – Incidental Construction
601 Minor Concrete Structures (concrete – minor structures) 3 CUYD
602 Culverts & Drains (indicate one or both) 18-inch Pipe Culvert 35 LNFT 24-inch Pipe Culvert 190 LNFT
End Section 10 EA
604 Manholes, Inlets, & Catch Basins(culverts & drains) (indicate which) Inlet, FLH TYPE 7A: 1 EA
605 Underdrains, Sheet Drains & Pavement Edge Drains (culverts & drains) (indicate which)
606 Corrugated Metal Spillways Spillway Assembly 1 EA Pipe Anchor Assembly 3 EA
622 Rental Equipment (yes/no) Yes
623 General Labor (yes/no) Yes
624 Topsoil (landscaping & related items) 4-inch Depth 9,920 SQYD
625 Turf Establishment (indicate seeding or mulching separately) Mulching 14,000 SQYD
633 Permanent Traffic Control (traffic control devices) Sign System 5 EA
635 Temporary Traffic Control Barricade Type 3: 6 EA Construction Sign 168 SQFT