This is a project description document detailing work requirements for a pavement preservation project across multiple National Park sites in Oregon and Washington. The work spans 3.85 miles across Fort Vancouver National Historic Site (Vancouver, WA), Lewis and Clark National Historic Park (near Astoria, OR), and Oregon Caves National Monument and Preserve (near Cave Junction, OR).
The project includes rack sealing, patching, micro surface treatments, and pavement marking, with an estimated price range of $2-5 million and completion date of Summer 2026. The work is divided into a Base schedule plus two Options (X and Y), with specific quantities detailed for each component. Key requirements include 116,000 SQYD of micro surfacing Type 2 for the base, extensive pavement markings (160,000 LNFT), temporary traffic control measures including 1,750 flagger hours, and various pavement maintenance tasks such as crack filling/sealing and asphalt concrete patching. The project involves standard construction requirements like mobilization, contractor quality control, and sampling/testing across all schedule options.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Prelim Letter_OR WA 2025.pdf | ||
| 01_OR WA NP MULTI PMS(1) Pre Final Plans_PRESOLICITATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OR WA NP MULTI PMS(1), Pavement Preservation Oregon and
Southern Washington
The work consists of rack sealing, patching, application of micro surface treatments, and pavement marking.
Project length: 3.85 Miles
Tentative Fixed Completion Date: Summer 2026
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
Estimated Price Range: $2 million to $5 million
Location: Fort Vancouver National Historic Site in Vancouver, WA, Lewis and
Clark National Historic Park (10 miles West of Astoria, OR), and Oregon Caves
National Monument and Preserve (15 miles South of Cave Junction, OR)
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-14
B as e
O p ti o n X
O p ti o
Y
DIVISION 150 – Project Requirements
151 Mobilization (yes/no) Yes Yes Yes
152 Construction Survey & Staking (yes/no) No No No
153 Contractor Quality Control and Assurance (yes/no)
Yes Yes Yes
154 Contractor Sampling & Testing (yes/no) Yes Yes Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no)
Yes No No
DIVISION 400 – Asphalt Pavements & Surface Treatments
406 Fog Seal 1.8 TON
407 Blotter 40 TON
409 Micro surfacing,Type 2
116,000 SQYD
4,600
SQYD
3,500
SQYD
414 Cracks, Cleaning and Filling 105 LNFT
414 Cracks, Cleaning and Sealing 4.40 MILE 0.35 MILE 0.27 MILE
418 Asphalt Concrete Pavement Patching, Type 1 40 SQYD
418 Asphalt Concrete Pavement Patching, Type 2 2,000 SQYD 700 SQYD 230 SQYD
B as e
O p ti o
X
O p ti o
Y
DIVISION 600 – Incidental Construction
609 Reset Wheelstop 230 EACH
622 Rental Equipment (yes/no) Yes
623 General Labor (yes/no) Yes
634 Pavement Markings (Type B)
160,000 LNFT
3,500
LNFT
2,850 LNFT
634 Pavement Markings, Symbols (Type B) 135 EACH 3 EACH
635 Temporary Traffic Control, Cone 220 EACH
635 Temporary Traffic Control, Portable Changeable Message Sign 2 EACH
635 Temporary Traffic Control, Pavement Markings 11,000 LNFT
635 Temporary Traffic Control, Construction Sign 229 SQFT
635 Temporary Traffic Control , Flagger 1,750 HOUR 20 HOUR 20 HOUR
635 Temporary Traffic Control, Pilot Car 30 HOUR
635 Temporary Traffic Control, Traffic Control Supervisor 45 DAY