This document is a comprehensive Procurement Planning guide detailing the procurement procedures and timelines for Collin College's purchasing processes. The guide provides a structured overview of procurement workflows based on purchase order value ranges, from under $10,000 to $100,000 and over, with estimated business days required to process each order category. The document outlines specific requirements for different procurement scenarios, including cooperative contracts, sole source purchases, and board approval processes.
Key procedural highlights include the need for multiple quotes depending on purchase value, specific requisition types for sole source purchases, and mandatory board approvals for purchases exceeding $100,000. The guide emphasizes that procurement timelines can vary based on complexity, evaluation processes, and number of responses received. Notable administrative details include board meetings typically held on the fourth Tuesday of each month (except July and November), board agenda submission deadlines, and specific requirements for cooperative contracts and purchase order processing. The document also provides eight additional notes to consider, such as the requirement for board re-approval if a purchase will exceed initially approved amounts and special handling for orders with supplier agreements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Roofing_and_Waterproofing_Consultant.pdf | ||
| Roofing_and_Waterproofing_Consultant_Specifications.docx | DOCX document | |
| Legal_Review_of_Contracts.docx | DOCX document | |
| Review_and_Signatory_Authority.docx | DOCX document | |
| Yearly_Purchasing_Training_December_2022.pptx | PPTX presentation | |
| Standard_Addendum_to_Agreement.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Procurement Planner - Estimated
Business Days to Process an Order
Under $10,000 2 Days
$10,000 to $49,999 2-5 days
$50,000 to $99,999
5-90 Days
$100,000 & over up to 120 days
One current price is required
Purchases under a cooperative contract must include cooperative contract number on quote and quote must be attached to the requisition.
Three quotes required to be attached to requisition
Only one quote needed if purchased under an existing contract or a cooperative contract. Quote must reference the cooperative contract and include the contract number.
If under an existing contract or a cooperative contract, should take around 5 days
If not under an existing or a cooperative contract then formal solicitation is required.
Formal Solicitations must be advertised for at least 2 weeks.
If under an existing contract or a cooperative contract that has already been approved by the
Board, should take around 5 days.
If not under an existing or a cooperative contract then formal solicitation is required.
Board approval is required for purchases of $100,000 and over if not already approved.
Formal Solicitations must be advertised for at least 2 weeks.
Procurement Planning - In order to assist everyone in preparing items to be purchased that will require Board approval, the following estimated timel ine for submission has been developed as a guideline. All timelines are estimated and may be longer depending on complexity, number of bids/RFPs received, timeliness of departments in providing required information and timeliness of evaluation team in completing evaluations. If it is determined that the aggregate purchases during the fiscal year for a class of items exceeds $100,000, Board approval will be required for those items prior to a purc hase order being issued. If you are not sure if the 12-month aggregate will apply to your purchase, please contact Purchasing and we will check the total expenditure for the period . Any requisitions that do not have to be bid, but will need Board approval, must be received by the Purchasing one week prior to the Board Agenda Due Date. A requisition and specifications are required before any items to be purchased will be put out to bid or placed on the Board Agenda.
Procurement Planning - In order to assist everyone in preparing items to be purchased that will require Board approval, the following estimated timel ine for submission has been developed as a guideline. All timelines are estimated and may be longer depending on complexity, number of bids/RFPs received, timeliness of departments in providing required information and timeliness of evaluation team in completing evaluations. If it is determined that the aggregate purchases during the fiscal year for a class of items exceeds $100,000, Board approval will be required for those items prior to a purc hase order being issued. If you are not sure if the 12-month aggregate will apply to your purchase, please contact Purchasing and we will check the total expenditure for the period . Any requisitions that do not have to be bid, but will need Board approval, must be received by the Purchasing one week prior to the Board Agenda Due Date. A requisition and specifications are required before any items to be purchased will be put out to bid or placed on the Board Agenda.
Notes to Consider:
1. Cooperative contracts over
$100,000 annually, Procurement takes to the August Board meeting for approval.
2. Any purchase that will go over the amount approved by the
Board has to go back to Board for approval.
3. Punchout orders under $5,000 only require budget check and cost center manager approval then go directly to supplier.
4. Board meetings are held the fourth Tuesday of the month and generally not held in July and
November. Board meetings in
December are usually held earlier in the month.
5. Board agendas are due to the
President's Office approximately two weeks prior to the Board meeting. Buyers are required to have agenda items to the
Purchasing Administrative
Assistant by noon on the first business day of the month.
6. Sole source purchases of
$10,000 or more must be in accordance with the District's
Sole Source Procurement Policy and must be submitted using a
Sole Source Requisition type and questionnaire completed. 7. The time it takes to complete a solicitation depends on the complexity, time for evaluations to be completed, number of responses received, time of year and other factors that can effect the timelines.
8. Orders with supplier agreements attached may take longer for review and approval of changes.
Notes to Consider:
1. Cooperative contracts over
$100,000 annually, Procurement takes to the August Board meeting for approval.
2. Any purchase that will go over the amount approved by the
Board has to go back to Board for approval.
3. Punchout orders under $5,000 only require budget check and cost center manager approval then go directly to supplier.
4. Board meetings are held the fourth Tuesday of the month and generally not held in July and
November. Board meetings in
December are usually held earlier in the month.
5. Board agendas are due to the
President's Office approximately two weeks prior to the Board meeting. Buyers are required to have agenda items to the
Purchasing Administrative
Assistant by noon on the first business day of the month.
6. Sole source purchases of
$10,000 or more must be in accordance with the District's
Sole Source Procurement Policy and must be submitted using a
Sole Source Requisition type and questionnaire completed. 7. The time it takes to complete a solicitation depends on the complexity, time for evaluations to be completed, number of responses received, time of year and other factors that can effect the timelines.
8. Orders with supplier agreements attached may take longer for review and approval of changes.
Sole Source Requisition Type must be selected for
Sole Source Purchases and Quesionnaire Completed
Depending on the complexity, it could take up to 90 days to formally bid, evaluate and award the contract.
Depending on the complexity, it could take up to 120 days to formally bid, evaluate and award the contract.