This document contains the Principal Items of Work for a state and local contract opportunity titled "4400-2024 Fall Maintenance (rebid)" issued by the state of Alabama. The contract includes four "Lump Sum" items of work related to subsidence and vertical opening repairs at various locations, as well as "Variable Quantity" items for overseeding and topdressing on multiple acreages. The contractor must provide unit pricing for each item and the total contract bid price. Failure to provide the pricing details may result in bid rejection.

The total contract bid price must be entered in the Unit Price on the Alabama Buys Bid Proposal Form. Pricing for the "Variable Quantity" items is based on estimated acreages, while the "Lump Sum" items have no specified quantities. The pricing provided will be used for the evaluation of bids, and the successful contractor will be required to complete the work outlined in the scope.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AML 2024 Fall Maintenance Package Principal Items of Work*

Description of Work

"Lump Sum" Items Unit(s) Qty. Unit Price Extended Price

Mobilization LS 1 @ $ - = $ -

1500 Urban Center Dr. Subsidence Emerg LS 1 @ $ - = $ -

Cordova Gorgas Rd. Vertical Opening LS 1 @ $ - = $ -

New Oak Grove Church Subsidence LS 1 @ $ - = $ -

"Variable Quantity" Items Unit(s) Qty. Unit Price Extended Price

Overseeding

Walker County Agriculture Restoration Acres 15.50 @ $ - = $ -

Topdressing

New Oak Grove Church Acres 12.00 @ $ - = $ -

Piper Mine Acres 59.00 @ $ - = $ -

Poplar Springs North Acres 6.25 @ $ - = $ -

Walker County Agriculture Restoration Acres 15.50 @ $ - = $ -

Materials - 1500 Urban Center Dr. Subsidence Emergency & New Oak Grove Church

Class I Riprap Tons 550 @ $ - $ -

Contractor

By:

Subtotal, Variable Quantity Items

Total Contract Bid Price

(For evaluation of bids only)

Date:

* Note: Vendor must list the pricing for each principal items of work and their total contract bid price below. The total bid price must also be listed on the Unit Price, Line 1 of the Request for Bid. Failure to provide and attach copies of the principal items of work pricing as outlined above may result in the rejection of your bid.

** THE TOTAL CONTRACT BID PRICE MUST BE ENTERED IN THE UNIT PRICE IN ALABAMA

BUYS

Subtotal, Lump Sum Items

Bid Proposal Form Page 1 of 1