Price_Schedule_-_Roof_Replacement.pdf
PDF 140 KB Posted
- Attached to
- Roof Replacement @ CUVA Federal contract opportunity
- Solicitation number
- 140P6425Q0035
About this file
This document is a Price Schedule for a Roof Replacement project at Cuyahoga Valley National Park in Brecksville, Ohio. The pricing template provides a detailed breakdown of construction items including mobilization/demobilization, demolition of existing roof components, installation of new synthetic cedar shake shingles, gutters, and downspouts, with line items for materials, labor, overhead, profit, and bonds. The schedule allows for a 20% decking replacement as necessary and requires the contractor to verify all quantities and measurements to provide a firm fixed price covering the entire project's completion. The quantities are listed as lump sum (LS) with spaces for unit prices and subtotals, though no specific dollar amounts are filled in on this template.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site_Visit_Attendees_List_0001.pdf | ||
| Sol_140P6425Q0035_Amd_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Wage_Determination_-_Cuyahoga_Co.pdf | ||
| Attachment_-_Provisions_to_be_Completed.pdf | ||
| Sol_140P6425Q0035.pdf | ||
| Technical_Questionnaire.docx | DOCX document | |
| Attachment_-_Construction_Contract_Administration.pdf | ||
| Price_Schedule_-_Roof_Replacement.xlsx | XLSX spreadsheet | |
| Specifications_-_Roof_Replacement.pdf | ||
| Technical_Questionnaire.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Unit Quantity Price/ Unit Subtotal
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
-$ Grand Total (Roof Replacement + Decking Replacement)
Overhead Profit Bonds
Grand Total (Decking Replacement)
Install: Installation of new synthetic cedar shake shingles/gutters/downspouts and all associated work/items
- Labor
** It is the responsibility of the contractor to verify all the quantities/measurements and to provide a price that will cover the completion of the entire project for this firm fixed price contract. **
- Materials
Grand Total
Overhead
Subtotal
Bonds Profit
Decking Replacement: 20% decking replacement as necessary
- Materials/Labor
- Labor
Mobilization/Demobilization
- Mob/Demob Costs
Demolition: Removal and disposal of the existing shingles/gutters/downspouts and all associated work/items
- Materials
Construction Items
National Park Service U.S. Department of Interior
Cuyahoga Valley National Park
15610 Vaughn Rd Brecksville, OH 44141
PRICE SCHEDULE
PROJECT: Roof Replacement
Sheet1
File details come from the government source that posted it. Updated .