This is a Price Schedule template for grounds maintenance services at Ft. Sill National Cemetery. The document serves as the pricing submission format for the Request for Quotation (RFQ) solicitation number 36C78626Q50235, issued by the Department of Veterans Affairs National Cemetery Administration. The solicitation is a 100% Set Aside for Service-Disabled Veteran Owned Small Businesses, with a NAICS code of 561730 (Landscaping Services) and a business size standard of $9.5 million in revenue.

The contract covers grounds maintenance services at Ft. Sill National Cemetery in Elgin, Oklahoma, with a base performance period from December 1, 2026, through November 30, 2027, followed by four optional one-year renewal periods extending through November 30, 2031. The solicitation was posted on August 24, 2026, with an original response date of September 25, 2026, at 3:00 PM EST. Contractors must submit pricing according to the schedule format provided in this attachment, and all submissions must comply with the applicable U.S. Department of Labor Wage Determination 2015-5313. The Price Schedule template is designed to align with the Performance Work Statement (Attachment A) to ensure consistent pricing for all required grounds maintenance tasks and services throughout the contract period.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule of Services Base Year: December 1, 2026 or Date of Award through November 30, 2027

CLIN

No.

Services
Est. Qty
Unit
Unit Cost
Total Cost
0001
Mow all improved turf areas. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 41.99 acres.
35
Week
$ ___________
$ ___________
0002
String trim grass in improved turf areas inaccessible to mowing equipment to include all sidewalks, curbs, driveways, trees, planting beds, monuments, buildings, walls, fences, signs, other vertical surfaces. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 41.99 acres.
35
Week
$ ___________
$ ___________
0003
String trim headstones in conjunction with every mowing. Remove and replace graveside flowers and associated items. Remove grass clippings, debris, and trash from headstones and flat markers. Est 7,857 headstones increasing by approx 355 annually.
35
Week
$ ___________
$ ___________
0004
Blade Edge all curbing, sidewalks, and roads. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est 24,219 LF.
15
Job
$ ___________
$ ___________
0005
Broadcast Pre-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 41.99 acres.
4
Job
$ __________
$ __________
0006
Broadcast Post-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 41.99 acres.
4
Job
$ __________
$ __________
0007
Fertilizer Application: Hybrid Bermudagrass. Est 41.99 acres.
4
Job
$ __________
$ __________
0008
Optional - Post Emergent Spot Herbicide application: Hybrid Bermudagrass. Est 41.99 acres.
3
Job
$ __________
$ __________

Total Cost For the Base Year:

Option Year 1: December 1, 2027 through November 30, 2028:

CLIN

No.

Services
Est. Qty
Unit
Unit Cost
Total Cost
1001
Mow all improved turf areas. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 41.99 acres.
35
Week
$ ___________
$ ___________
1002
String trim grass in improved turf areas inaccessible to mowing equipment to include all sidewalks, curbs, driveways, trees, planting beds, monuments, buildings, walls, fences, signs, other vertical surfaces. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 41.99 acres.
35
Week
$ ___________
$ ___________
1003
String trim headstones in conjunction with every mowing. Remove and replace graveside flowers and associated items. Remove grass clippings, debris, and trash from headstones and flat markers. Est 8,212 headstones increasing by approx 355 annually.
35
Week
$ ___________
$ ___________
1004
Blade Edge all curbing, sidewalks, and roads. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est 24,219 LF.
15
Job
$ ___________
$ ___________
1005
Broadcast Pre-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 41.99 acres.
4
Week
$ ___________
$ ___________
1006
Broadcast Post-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 41.99 acres.
4
Job
$ ___________
$ ___________
1007
Fertilizer Application: Hybrid Bermudagrass. Est 41.99 acres.
4
Job
$ __________
$ __________
1008
Optional - Post Emergent Spot Herbicide application: Hybrid Bermudagrass. Est 41.99 acres.
3
Job
$ __________
$ __________
1009
Optional - Mow all improved turf areas. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 7.18 acres EXPANSION AREA.
30
Job
$ __________
$ __________
1010
Optional - String trim grass in improved turf areas inaccessible to mowing equipment to include all sidewalks, curbs, driveways, trees, planting beds, monuments, buildings, walls, fences, signs, other vertical surfaces. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 7.18 acres EXPANSION AREA.
30
Job
$ __________
$ __________
1011
Optional - Blade Edge all curbing, sidewalks, and roads. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est 882 LF EXPANSION AREA.
12
Job
$ __________
$ __________
1012
Optional - Broadcast Pre-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 7.18 acres EXPANSION AREA.
4
Job
$ __________
$ __________
1013
Optional - Broadcast Post-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 7.18 acres EXPANSION AREA.
4
Job
$ __________
$ __________
1014
Optional - Fertilizer Application: Hybrid Bermudagrass. Est. 7.18 acres EXPANSION AREA.
4
Job
$ __________
$ __________
1015
Optional - Post Emergent Spot Herbicide application: Est. 7.18 acres EXPANSION AREA.
3
Job
$ __________
$ __________
Total Cost for Option Year 1:
$ __________

Option Year 2: December 1, 2028 through November 30, 2029:

CLIN

No.

Services
Est. Qty
Unit
Unit Cost
Total Cost
2001
Mow all improved turf areas. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 49.17 acres.
35
Week
$ ___________
$ ___________
2002
String trim grass in improved turf areas inaccessible to mowing equipment to include all sidewalks, curbs, driveways, trees, planting beds, monuments, buildings, walls, fences, signs, other vertical surfaces. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 49.17 acres.
35
Week
$ ___________
$ ___________
2003
String trim headstones in conjunction with every mowing. Remove and replace graveside flowers and associated items. Remove grass clippings, debris, and trash from headstones and flat markers. Est 8,567 headstones increasing by approx 355 annually.
35
Week
$ ___________
$ ___________
2004
Blade Edge all curbing, sidewalks, and roads. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est 25,101 LF.
15
Week
$ ___________
$ ___________
2005
Broadcast Pre-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 49.17 acres.
4
Week
$ ___________
$ ___________
2006
Broadcast Post-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 49.17 acres.
4
Job
$ ___________
$ ___________
2007
Fertilizer Application: Hybrid Bermudagrass. Est 49.17 acres.
4
Job
$ __________
$ __________
2008
Optional - Post Emergent Spot Herbicide application: Hybrid Bermudagrass. Est 49.17 acres.
3
Job
$ __________
$ __________
Total Cost for Option Year 2:
$ __________

Option Year 3: December 1, 2029 through November 30, 2030:

CLIN

No.

Services
Est. Qty
Unit
Unit Cost
Total Cost
3001
Mow all improved turf areas. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 49.17 acres.
35
Week
$ ___________
$ ___________
3002
String trim grass in improved turf areas inaccessible to mowing equipment to include all sidewalks, curbs, driveways, trees, planting beds, monuments, buildings, walls, fences, signs, other vertical surfaces. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 49.17 acres.
35
Week
$ ___________
$ ___________
3003
String trim headstones in conjunction with every mowing. Remove and replace graveside flowers and associated items. Remove grass clippings, debris, and trash from headstones and flat markers. Est 8,922 headstones increasing by approx 355 annually.
35
Week
$ ___________
$ ___________
3004
Blade Edge all curbing, sidewalks, and roads. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est 25,101 LF.
15
Job
$ ___________
$ ___________
3005
Broadcast Pre-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 49.17 acres.
4
Job
$ ___________
$ ___________
3006
Broadcast Post-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 49.17 acres.
4
Week
$ ___________
$ ___________
3007
Fertilizer Application: Hybrid Bermudagrass. Est 49.17 acres.
4
Job
$ __________
$ __________
3008
Optional - Post Emergent Spot Herbicide application: Hybrid Bermudagrass. Est 49.17 acres.
3
Job
$ __________
$ __________
Total Cost For Option Year 3:
$ __________

Option Year 4: December 1, 2030 through November 30, 2031:

CLIN

No.

Services
Est. Qty
Unit
Unit Cost
Total Cost
4001
Mow all improved turf areas. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 49.17 acres.
35
Week
$ ___________
$ ___________
4002
String trim grass in improved turf areas inaccessible to mowing equipment to include all sidewalks, curbs, driveways, trees, planting beds, monuments, buildings, walls, fences, signs, other vertical surfaces. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est. 49.17 acres.
35
Week
$ ___________
$ ___________
4003
String trim headstones in conjunction with every mowing. Remove and replace graveside flowers and associated items. Remove grass clippings, debris, and trash from headstones and flat markers. Est 9,277 headstones increasing by approx 355 annually.
35
Week
$ ___________
$ ___________
4004
Blade Edge all curbing, sidewalks, and roads. Remove grass clippings, debris, trash and clean sidewalks, patios, roadways, curbs, and parking areas. Est 25,101 LF.
15
Job
$ ___________
$ ___________
4005
Broadcast Pre-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 49.17 acres.
4
Job
$ ___________
$ ___________
4006
Broadcast Post-Emergent Herbicide Applications: Hybrid Bermudagrass. Est. 49.17 acres.
4
Week
$ ___________
$ ___________
4007
Fertilizer Application: Hybrid Bermudagrass. Est 49.17 acres.
4
Job
$ __________
$ __________
4008
Optional - Post Emergent Spot Herbicide application: Hybrid Bermudagrass. Est 49.17 acres.
3
Job
$ __________
$ __________
Total Cost for Option Year 4:
$ __________

PRICE SUMMARY TOTALS:

Total Cost

Base Year: December 1, 2026 or Date of Award through November 30, 2027
$_______________________
Option Year 1: December 1, 2027 through November 30, 2028
$ ______________________
Option Year 2: December 1, 2028 through November 30, 2029
$ ______________________
Option Year 3: December 1, 2029 through November 30, 2030
$ ______________________
Option Year 4: December 1, 2030 through November 30, 2031
$ ______________________
Grand Total (Base + all OPTION: Years):
$ ______________________

PRICE SCHEDULE: Contractor shall provide all labor, supervision, material, equipment, tools and supplies to complete grounds maintenance services to maintain Fort Sill National Cemetery, 2648 NE Jake Dunn Road, Elgin, OK 73538, following National Cemetery Administration standards. The contract period will consist of a base period from date of contract award through November 30, 2027, with up to four (4) one-year OPTIONs to extend the term of the contract through November 20, 2031. Units and services to be in accordance with Performance Work Statement, Technical Specifications, Performance Requirements Summary, and terms and conditions contained in this solicitation.

The schedule price shall be all-inclusive, including all labor, equipment, materials, and supplies to complete the Contract Line Item (CLIN(s)). Offerors shall enter unit cost and total amounts for each CLIN as indicated in the schedule. In the event there is a difference between a unit price and the extended total amount, the unit price will be held to be the intended bid price and the total of the CLINs will be recomputed accordingly.

All quantities indicated in the Price Schedule are estimated and not purchased by this contract. Should extreme weather conditions result in excessive or minimal turf growth, the Government reserves the right to allow mowing, trimming, and/or edging events required by this contract. In addition, the Government may limit the number of acres to be mowed, headstones/markers trimmed, or linear feet of edging during any given event due to other cemetery projects.

Offerors shall enter the Total Cost for each year in the “Summary Totals” where indicated. Offeror shall calculate the Grand Total for all years and enter where indicated.

Offeror is to understand the quantities stated in the schedule are estimates for pricing purposes only. Acreage or linear feet stated in the schedule may not be exact.

NOTE: The cemetery expansion is scheduled to be completed mid FY28. The CLIN structure is constructed to allow the government flexibility to have services if completed on time. Please note the optional CLINS for the expansion area services have been include in the primary CLIN’s starting in option year two (2).

POST AWARD CONFERENCE: Prior to commencement of work, a contract awardee is required to make an appointment for a conference with the COR and/or Contracting Officer to assure you that all parties understand all contractual obligations and the role that each party serves.