The file's text, extracted by GovTribe without its formatting.
Price Schedule for Houston NC Landscaping Materials
Base Year: November 1, 2025 through October 31, 2026
CLIN
No.
Description:
Material/Product:
| Est. Qty |
| Unit |
| Unit Cost |
| Est. Total Cost |
| 0001 |
| Screened Planting Topsoil |
| 2,100 |
| CY |
| $_________ |
| $___________ |
| 0002 |
| Dark Brown Hardwood Mulch |
| 1000 |
| CY |
| $_________ |
| $___________ |
| 0003 |
| Drainage Rock, 1-1/2” |
| 40 |
| Ton |
| $_________ |
| $___________ |
| 0004 |
| Pea Gravel, 3/8" |
| 140 |
| Ton |
| $_________ |
| $___________ |
| 0005 |
| Decomposed Granite (1/4" to minus) |
| 160 |
| Ton |
| $_________ |
| $___________ |
| 0006 |
| Screened Fill Sand |
| 60 |
| CY |
| $_________ |
| $___________ |
| Total Estimated Cost: |
| $___________ |
Option Year 1: November 1, 2026 through October 31, 2027
CLIN
No.
Description:
Material/Product:
| Est. Qty |
| Unit |
| Unit Cost |
| Est. Total Cost |
| 1001 |
| Screened Planting Topsoil |
| 2,100 |
| CY |
| $_________ |
| $___________ |
| 1002 |
| Dark Brown Hardwood Mulch |
| 1000 |
| CY |
| $_________ |
| $___________ |
| 1003 |
| Drainage Rock, 1-1/2” |
| 40 |
| Ton |
| $_________ |
| $___________ |
| 1004 |
| Pea Gravel, 3/8" |
| 140 |
| Ton |
| $_________ |
| $___________ |
| 1005 |
| Decomposed Granite (1/4" to minus) |
| 160 |
| Ton |
| $_________ |
| $___________ |
| 1006 |
| Screened Fill Sand |
| 60 |
| CY |
| $_________ |
| $___________ |
| Total Estimated Cost: |
| $___________ |
Option Year 2: November 1, 2027 through October 31, 2028
CLIN
No.
Description:
Material/Product:
| Est. Qty |
| Unit |
| Unit Cost |
| Est. Total Cost |
| 2001 |
| Screened Planting Topsoil |
| 2,100 |
| CY |
| $_________ |
| $___________ |
| 2002 |
| Dark Brown Hardwood Mulch |
| 1000 |
| CY |
| $_________ |
| $___________ |
| 2003 |
| Drainage Rock, 1-1/2” |
| 40 |
| Ton |
| $_________ |
| $___________ |
| 2004 |
| Pea Gravel, 3/8" |
| 140 |
| Ton |
| $_________ |
| $___________ |
| 2005 |
| Decomposed Granite (1/4" to minus) |
| 160 |
| Ton |
| $_________ |
| $___________ |
| 2006 |
| Screened Fill Sand |
| 60 |
| CY |
| $_________ |
| $___________ |
| Total Estimated Cost: |
| $___________ |
Option Year 3: November 1, 2028 through October 31, 2029
CLIN
No.
Description:
Material/Product:
| Est. Qty |
| Unit |
| Unit Cost |
| Est. Total Cost |
| 3001 |
| Screened Planting Topsoil |
| 2,100 |
| CY |
| $_________ |
| $___________ |
| 3002 |
| Dark Brown Hardwood Mulch |
| 1000 |
| CY |
| $_________ |
| $___________ |
| 3003 |
| Drainage Rock, 1-1/2” |
| 40 |
| Ton |
| $_________ |
| $___________ |
| 3004 |
| Pea Gravel, 3/8" |
| 140 |
| Ton |
| $_________ |
| $___________ |
| 3005 |
| Decomposed Granite (1/4" to minus) |
| 160 |
| Ton |
| $_________ |
| $___________ |
| 3006 |
| Screened Fill Sand |
| 60 |
| CY |
| $_________ |
| $___________ |
| Total Estimated Cost: |
| $___________ |
Option Year 4: November 1, 2029 through October 31, 2030
CLIN
No.
Description:
Material/Product:
| Est. Qty |
| Unit |
| Unit Cost |
| Est. Total Cost |
| 4001 |
| Screened Planting Topsoil |
| 2,100 |
| CY |
| $_________ |
| $___________ |
| 4002 |
| Dark Brown Hardwood Mulch |
| 1000 |
| CY |
| $_________ |
| $___________ |
| 4003 |
| Drainage Rock, 1-1/2” |
| 40 |
| Ton |
| $_________ |
| $___________ |
| 4004 |
| Pea Gravel, 3/8" |
| 140 |
| Ton |
| $_________ |
| $___________ |
| 4005 |
| Decomposed Granite (1/4" to minus) |
| 160 |
| Ton |
| $_________ |
| $___________ |
| 4006 |
| Screened Fill Sand |
| 60 |
| CY |
| $_________ |
| $___________ |
| Total Estimated Cost: |
| $___________ |
B.2 PRICE SUMMARY TOTALS
Total Price
| Base Year – November 1, 2025 through October 31, 2026 |
| $___________ |
| Option Year 1 - November 1, 2026 through October 31, 2027 |
| $___________ |
| Option Year 2 - November 1, 2027 through October 31, 2028 |
| $___________ |
| Option Year 3 - November 1, 2028 through October 31, 2029 |
| $___________ |
| Option Year 4 - November 1, 2029 through October 31, 2030 |
| $___________ |
| Grand Total (Base + all Option Years): |
| $___________ |
PRICE SCHEDULE: Contractor shall provide all labor, supervision, material, equipment, tools, and supplies to deliver bulk materials (topsoil, mulch, drainage rock, pea gravel, decomposed granite and sand) to Houston National Cemetery is located at 10410 Veterans Memorial Drive, Houston, TX 77038. The contract period will consist of a base period from November 1, 2025 (or date of contract award), through October 31, 2026, with up to four (4) one-year options to extend the term of the contract through October 31, 2030. Units and services to be in accordance with Statement of Need and terms and conditions contained in this solicitation.
The schedule price shall be all-inclusive, including all labor, equipment, materials, and supplies to complete the Contract Line Item (CLIN(s)). All the quantities are estimates only and no guarantee of actual amounts.