This is a Price Schedule for a firm fixed price federal construction contract issued by the National Park Service, U.S. Department of Interior, for a Fence Replacement project at Mesa Verde National Park.
The contract encompasses two primary construction phases: demolition and installation. The demolition phase requires removal and disposal of the existing fence and all associated work items, with separate line items for materials, equipment, and labor costs. The installation phase covers installation of the new fence and all associated work items, also broken down into materials, equipment, and labor categories. The contract structure includes a mobilization/demobilization phase with associated costs. Contractors are required to complete pricing for all line items using a lump sum (LS) basis with a quantity of one for each section. The price schedule provides for overhead, profit, and bonds to be applied as percentages to the subtotal, with all costs culminating in a Grand Total. The contractor bears full responsibility for verifying all quantities and measurements to ensure the price provided covers complete project completion under this firm fixed price contract arrangement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers_0001.pdf | ||
| Sol_140P6426Q0032_Amd_0001.pdf | ||
| Sol_140P6426Q0032.pdf | ||
| Site_Visit_Map.pdf | ||
| Wage_Determination_-_Montezuma_Co.pdf | ||
| Attachment_-_Notice_to_Contractors.pdf | ||
| Attachment_-_Construction_Contract_Administration.pdf | ||
| Price_Schedule_-_Fence_Replacement.xlsx | XLSX spreadsheet | |
| Specifications_-_Fence_Replacement.pdf | ||
| Technical_Questionnaire.docx | DOCX document | |
| Technical_Questionnaire.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Unit Quantity Price/ Unit Subtotal
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
LS 1 -$ -$
- Materials
Construction Items
National Park Service U.S. Department of Interior
Mesa Verde National Park
PRICE SCHEDULE
PROJECT: Fence Replacement
- Labor
Mobilization/Demobilization
- Mob/Demob Costs
Demolition: Removal and disposal of the existing fence and all associated work/items
- Equipment
Install: Installation of new fence and all associated work/items
- Equipment
- Labor
** It is the responsibility of the contractor to verify all the quantities/measurements and to provide a price that will cover the completion of the entire project for this firm fixed price contract. **
- Materials
Grand Total
Overhead
Subtotal
Bonds Profit
Sheet1