Questions_and_Answers_0001.pdf

PDF 108 KB Posted

Attached to
Fence Replacement @ MEVE Federal contract opportunity
Solicitation number
140P6426Q0032
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This is a Questions and Answers document (Amendment 0001) for Solicitation #140P6426Q0032, a fence replacement project at Mesa Verde National Park (MEVE).

The project involves replacing approximately 1.35 miles of existing barbed wire fence in-kind with woven wire fence and installing 0.25 miles of new fence marked with lathe and flagging. The work includes repairing an existing barbed wire washout fence structure under 50 feet in length. Contractors are responsible for ensuring adequate materials to complete the full scope, as listed materials are estimates only. The woven wire design with an 18-inch clearance at the bottom to facilitate wildlife movement is the only approved design; alternatives such as barbed wire or reduced strand configurations are not acceptable. Wire attachment to the park side of posts is appropriate where topography and access demands it, though contractors may not work on Ute Mountain Ute Reservation land. Steel gates are preferred over barbed wire gates for ease of use by park staff, with the only requirement being passage of livestock when open and prevention of egress/ingress when closed. Staging areas will be identified with the Contracting Officer Representative (COR) after contract award, with at least one area accommodating a 24-foot gooseneck trailer. Pack animal day use may be authorized only with certified weed-free hay; no overnight animal containment is permitted. The project area is never more than 1,000 meters from a paved road; camping is available at Morefield Campground for a fee. No water sources are available on-site. The Wetherill Mesa area is accessed via a two-lane paved road used by the public, though the remainder of the project area is not publicly accessible. Contractors are not responsible for surveys, as the fence line has been marked; MEVE staff do not have bandwidth for additional pre-bid site visits beyond the standard offering.

View the file

Other files for this federal contract opportunity

Other files attached to Fence Replacement @ MEVE, newest first.
File Type Posted
Sol_140P6426Q0032_Amd_0001.pdf PDF
Technical_Questionnaire.docx DOCX document
Technical_Questionnaire.pdf PDF
Sol_140P6426Q0032.pdf PDF
Site_Visit_Map.pdf PDF
Wage_Determination_-_Montezuma_Co.pdf PDF
Attachment_-_Construction_Contract_Administration.pdf PDF
Price_Schedule_-_Fence_Replacement.xlsx XLSX spreadsheet
Specifications_-_Fence_Replacement.pdf PDF
Attachment_-_Notice_to_Contractors.pdf PDF
Price_Schedule_-_Fence_Replacement.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: 140P6426Q0032

Amendment #: 0001

Fence Replacement – MEVE

Questions and Answers listed below:

QUESTIONS:

Question # Question Answer/Response 1.

1) We may or may not be able to make the official site tour as we have a wedding to attend across the state. If we can't make the official tour, we're going to go look at it on our own. Is it possible to get coordinates/detailed maps of the fenceline?

2) If pack mules were used for tramming new/old materials, how would the park like them to be contained at night (for example high lined between trees, pickets, electric fence, etc) There likely wouldn't be enough natural feed for grazing, so supplementing weed free food would be assumed.

3) Are there any water sources available in the area or would we need to haul water for stock kept at our camp site?

4) Where will the staging area for material be?

5) Is there good enough road access to the staging area for a 24ft gooseneck trailer?

6) Can contractors camp onsite or relatively near?

Most of the project area is not accessible to the public, though you can see roughly half of the project area from a public road. The map provided in the specifications shows the exact location of the project.

Pack mules are not identified in the Specifications on purpose. Pack animal use MAY be authorized for day use only and certified weed free hay must be utilized. Pack animal use was not analyzed during the NEPA process for this project, so day use MAY be possible.

No water sources are available.

Staging areas will be identified working with the COR once the contract is awarded.

Multiple staging areas may be utilized on Wetherill Mesa, but there will be at least one area that can accommodate a 24 foot trailer.

Camping is available at the Morefield Campground for a fee.

The project area is never more than 1000 meters from a paved road.

7) What is the current existing fence? barbed wire?

woven wire?

8) Has the fence line been surveyed by the park or reservation? if not is the contractor responsible for obtaining a survey?

9) Is the new fenceline following the exact old fence line?

10) Will the Wetherill Trailhead/trail remain open to the public or will it be shut down during contractor operations?

11) With the bottom of the fence being 18 inches off the ground to facilitate wildlife movement under the fence, would the agency consider altering the specs to go with 4- 6 strands of barbed/smooth wire instead? this would SIGNIFICANTLY reduce material costs, labor costs, and construction time, resulting in an over-all win for the agency.

12) Is it possible to coordinate with the tribe to where the contractor could camp on the tribal side of the fence during operations? I realize this would be the responsibility of the contractor overall but I assume the park has decent working relations with the tribe and may be able to help facilitate that.

13) What are the steel gate specs? Is it possible to go with a barbed wire gate instead?

Current fence is a barbed wire fence.

Per specifications, 1.35 miles of the fence is being replaced in-kind.

0.25 miles of the fence is NEW and will be marked with lathe and flagging. Contractors are NOT responsible for any additional surveys.

See response above.

TheWetherill Mesa area is accessed via a two lane paved road that is used by the visiting public. The rest of the project area is not open to the public, though located adjacent to public paved road.

The woven wire design per specifications is the only approved design.

No camping is authorized as this project is accessed via a paved road.

No specifics as long as gate allows passage of livestock when open and prevents livestock egress/ingress when closed. A steel gate is more user friendly to park staff who may be unfamiliar with barbed wire gates.

14) What are the requested material for the floodgate? suspended PVC, panels? a barbed wire washout fence?

15) How long does the floodgate/washout need to be?

Barbed wire washout fence. This is just a repair to the existing structure (wire and log washout).

Under 50 feet. The site may be visiting during pre-bid site visit.

2.

The scope of work says to place the wire on the outside of the posts. The outside of the post in my opinion would put us unrolling the wire on the Ute reservation land. To unroll these large roll of wires we would to trim some brush etc. Do we have permission to work on their side?

Or can we unroll and attach The Wire on the National Park side of the posts?

Attaching the wire to the park side is appropriate where topography and access demands it. The park does not have permission to work on the Ute Mountain Ute Reservation in the Project Area.

3.

There are significant concerns with the topography of this fence placement – can there be a more thorough site visit so contractors can walk the entire line to annotate each of the difficult areas this fence is to be installed as outlined in the specifications?

MEVE staff do not have the bandwidth to accommodate another pre-bid site visit at this time.

4.

The materials listed do not seem to be enough materials to complete the project in totality. Please advise.

As stated in the project specifications “ALL MATERIALS

IN THE LIST ARE AN

ESTIMATE OF NEEDS

ACCORDING TO PROVIDED

SPECIFICATIONS” – the contractor is in charge of ensuring they acquire enough materials to complete the project in its totality.

It is incumbent upon the contractor to ensure there is enough materials to complete the fence replacement project as outlined in the project specifications.

File details come from the government source that posted it. Updated .