Contract Price Schedule Summary
This is a Contract Price Schedule for National Park Service Solicitation 140P5426R0025 for the Replacement and Repair of Plum Orchard Gutters and Flashing project at Cumberland Island National Seashore. Offerors must submit pricing for all base line items and all option line items as a minimum requirement, with failure to do so potentially rendering the proposal unacceptable. For lump-sum line items, offerors provide total price only; for unit-priced line items, both unit price and extended total price are required. In case of calculation errors, unit price governs; in case of summation errors, the total of corrected amounts govern.
The base contract consists of seven line items: (1) Mobilization including equipment transport to the island, remobilization to the mainland, and daily transport to Plum Orchard; (2) Repair and Replacement of Gutters including removal of damaged sections, replacement of 274 linear feet of copper gutter, and installation of gutter hangers at 24-inch on-center spacing around the entire building; (3) Concealed Gutter pitch correction; (4) Welded Wire Mesh Chase covers; (5) General Conditions; (6) Profit; and (7) Overhead. Line items 8 and 9 are blank entries for the total base price calculation. Option 1 is listed as N/A. All prices must be rounded to whole dollars.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Price Schedule National Park Service (NPS)
Solicitation : 140P5426R0025 Cumberland Island National Seashore
Project Title: Replacement and Repair of Plum Orchard Gutters and Flashing
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
Contract Line Item Number
(CLIN)
Contract Line Item (CLI) Title
Quantity
Unit of
Measure
Unit Price
Total Price
Mobilization:
1) Mobilization of equipment to the Island.
2) Remobilization to the Mainland.
3)Daily transport to Plum Orchard
Each
Repair and Replacement of Gutters:
1) Removal of Damaged and Deformed Gutter Sections.
2) Replacement of 274 L.F. of Copper Gutter.
3) Installation of Gutter Hangers to meet 24" O.C. requirement around entire building.
Concealed Gutter pitch correction. 1 Each
Welded Wire Mesh Chase covers
5 General Conditions 1 Each
6 Profit 1 Each
7 Overhead 1 Each
8 1 Each
9 1 Each
TOTAL BASE PRICE (Contract Line Item Number 1 through 7-----------------------------
10 Option 1: N/A 1 Each
TOTAL PRICE FOR ALL OPTIONS BASE PRICE (Contract Line Item Number 9)-----------