Preliminary Plans_ID FLAP BONNER 841(1).pdf
PDF 23 MB Posted
- Solicitation number
- 69056725R000015
About this file
This is a Request for Proposals (RFP) for the Trestle Creek Road rehabilitation project in Bonner County, Idaho, located within the Kaniksu National Forest. The project involves approximately 3.81 miles of roadway improvements from mile post 100 to 103.7, including bank stabilization, culvert cleaning and replacement, roadway excavation, aggregate base course, asphalt concrete pavement, and erosion control measures.
The project includes nine proposed turnouts, multiple bank stabilization sites, and extensive drainage and utility work. The U.S. Department of Transportation Federal Highway Administration is overseeing the project, with construction type specified as bank stabilization, culvert replacement, roadway aggregate, and asphalt concrete pavement. The design speed is 30 MPH, and the project will utilize standard specifications for Federal Highway Projects. Key features include geotextile stabilization, riprap placement, streambed material conservation, and fish passage considerations. The project is preliminarily scheduled for construction, with detailed plans showing phased improvements along the entire route through the national forest.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PROJECT DESCRIPTION_ID FLAP BONNER 841(1).pdf | ||
| Preliminary Letter ID FLAP BONNER 841(1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRELIM
IN
ARY
NOT FOR C
ONSTRUCTIO
N
:5
A
M
J u n e
S
H E
E T
I N
D E
X c p w w o r k w f l\ d
\i d a g e n a a a c .d g n
SHEET INDEX
PROJECT
NUMBER
SHEET
A.2
ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
BH TP
CUYD
culv.
CUFT
cubic yard(s) culvert cubic foot (feet) mon.
min.
MGAL
max.
matl.
M.P.
M.L.
monument minimum thousand gallon maximum material mile post main line
W
RIP
DI
G W G WV
CP GPS
36 31
36 31
N
E
N 1000EL. 1234.56
TP
TP
SEC.
SEC.
θs Ø ∆c spiral central angle diameter curve central angle total central angle approach ahead average daily traffic abutment appr.
AH
ADT
abut.
between bearing bridge balance point bench mark back face back btwn brg.
br.
BP
BM
b.f.
BK
ctrs.
CS
cont.
constr. jt.
conn.
conc.
col.
CMP
clr.
cc or c. to c.
centers point of curve to spiral continuous construction joint connection concrete column corrugated metal pipe clear centerline center to center
NO SCALE
NOTE:
1.
on the appropriate plan sheet.
Other symbols used in the plans will be shown in a legend
W west drwg(s).
dist.
diaph.
dia.
DHV
D exp. jt.
exc.
EW
EQ or eq.
EOP
emb.
elev.
El. 94.16 e.f.
e E expansion joint excavation edge of water equation edge of pavement embankment elevation elevation in feet each face superelevation rate east drawing(s) distance diaphragm diameter design hourly volume diameter galv.
ga.
galvanized gage (gauge) jt.
IE
ID
joint invert elevation inside diameter ftg.
flg.
fin.
f.f.
footing flange finish front face
LW
lt. or LT Ls
LPSM
long.
LNFT
lat.
L low water left length of spiral lump sum longitudinal linear foot (feet) latitude length of curve rte.
rt. or RT reqd.
reinf.
rdwy.
R/W R.
R route right required reinforcement roadway right-of-way range radius typ.
Ts
TS
thd.
TBM
T.
T typical tangent distance (spiraled curve) point of tangent to spiral thread temporary bench mark township tangent distance
VPI
vph V vertical point of intersection vehicles per hour design speed (velocity)
STS
struc.
stiff.
stgr.
std.
STA, Sta.
ST
SS
SRS
SQYD
SQFT
spa.
SLRY
shldr.
sect.
SC
SADT
S point of spiral to tangent spiral structural stiffener stringer standard station point of spiral to tangent point of spiral to spiral (no curve) point of spiral to reverse spiral square yard square foot spacing, spaces or spaced slurry unit shoulder section point of spiral to curve seasonal average daily traffic south
KSI
square inch thousand pounds per pvmt.
PT
PST
PSC
PSI
PSF
PS
POT
POS
POC
pl.
PI
PCS
PCC
PC
pavement point of tangent point of spiral to tangent point of spiral to curve pounds per square inch pounds per square foot point of tangent to spiral point on tangent point on spiral point on curve plate point of intersection point of curve to spiral point of compound curve point of curve
OHWM
OG
OD
o. to o.
o.c.
ordinary high water mark original ground outside diameter out to out on center
NC
N normal crown north
A A
DI
National Boundary
State Boundary
County Boundary
City Boundary
Township or Range Line
Section Line
Section Corner (Found, Projected)
Control Point (Terrestrial and GPS)
Gas & Water Meter; Gas & Water Valve
Flagpole; Fire Hydrant
Cooking Grate; Garbage Can; Picnic Table
Boulder; Well; Antenna; Grave
Above Ground Tank; Underground Tank
Spot Elevation; Coordinate Grid Tick
Material Source; Bore Hole; Test Pit
Treeline; Individual Trees
Spring or Seep
Section Line 4
Section Corner (Found, Projected) 4
Section Line 16
Section Corner (Found, Projected)16
Property Line
Parcel Number
National Park Boundary
National Forest Boundary
National Wildlife Refuge Boundary
BLM Lands Boundary
Indian Reservation Boundary
Existing Roadway (Paved, Gravel)
Railroad
Trail
Fiber Roll
Silt Fence
Sandbag
Intermittent Drainage or Small Creek
Large Creek or River
Lake, Pond or Reservoir; Marshland
North Arrow
Slope Stake Limits Top of Cut
Toe of Fill
Construction Limits
Bottom of Ditch
Fence
Gate with Fence
Cattleguard
Guardrail
Concrete Barrier and Guard Wall
Retaining Wall wall face
Signs (single, double post; portable)
Delineators
Pipe Culvert (arrow shows flow)
Pipe Culvert with End Section
Pipe Culvert with Headwall
Pipe Culvert with Drop Inlet
Box Culvert
Underdrain
Overhead/Above Ground Utilities
Underground Utilities
Light, Support w/Anchor) Poles (Power, Telephone, Joint Use, Miscellaneous Utility Features
Building
Right-of-Way Line
Permanent Easement
Construction Easement
Riprap
- no symbol -
Section A-A
EXISTING PROPOSED
STEAM = steam, T = telephone, TV = CATV, W = water P = power, SA = sanitary sewer, SD = storm drain, SS = storm sewer, FM = force main, FO = fiber optic, G = gas, IRR = irrigation, O = oil, UP = transformer or junction box, WF = water fountain EM = electric meter, TP = telephone pedestal, TV = CATV pedestal,
- no symbol -
ABBREVIATIONS
PLAN SYMBOLS AND
101-1W
FP-14
6/2022
WFLHD DETAIL
:5
P
S e p te m b e r
D e t W
-1 p w w o rk w fl \d
\W
-1
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
A.3
IN
ARY
NOT FOR C
0 12
SCALE IN MILES
pits
Gravel
T re s tle C re e k to S a n d p o in t
Tr es tle
Cr ee k Ro ad
RV Park
Boat ramp n a r h c o C w ar
D
Mountain
Grief
NF 275
NF 275
NF 2
re iz al G kee rC
572 F N
Tr es tle
Cr ee k
Tr es tle
C re e k
N
Pend Oreille
Lake
Northern Railroad
Burlington
END PROJECT
BEGIN PROJECT
A p p ro x . 1
.5 m ile s
T re s tle C re e k to M is s o u la , M
T
A p p ro x . 1 m ile s
No Hope Rd
NATIONAL FOREST
KANIKSU
NATIONAL FOREST
KANIKSU
8 10
11 12
15 14 13
21 22 23 24
T 60 N
T 59 N
10+00
TRESTLE CREEK ROAD
211+00
TRESTLE CREEK ROAD
Area
Staging
:4
F e b r u a r y
V ic in it y
M a p p w w o r k w f l\ d
\i d a g e n a a a c .d g n
VICINITY MAP
PROJECT
ID FLAP BONNER 841(1) A.4ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
Existing ground
Varies (7'-13')Varies (7'-13')
/2-inch lifts with tack coat in between 1over 2
4-inch compacted depth, placed in 1 1/2-inch size aggregate, 0.3 to < 3 million ESAL, 1/2-inch nominal maximum
Asphalt concrete pavement, gyratory mix, 8-inch compacted depth
Aggregate base grading D Existing gravel surface
Existing ground
Varies (7'-11')Varies (7'-11')
/2-inch lifts with tack coat in between 1over 2
4-inch compacted depth, placed in 1 1/2-inch size aggregate, 0.3 to < 3 million ESAL, 1/2-inch nominal maximum
Asphalt concrete pavement, gyratory mix, 8-inch compacted depth
Aggregate base grading D
Existing gravel surface
LC
LC
Class 1, Type A (woven)
Separation-stabilization geotextile, Class 1, Type A (woven)
Separation-stabilization geotextile, Existing ground
LC
Select borrow
/2-inch lifts with tack coat in between 1over 2
4-inch compacted depth, placed in 1 1/2-inch size aggregate, 0.3 to < 3 million ESAL, 1/2-inch nominal maximum
Asphalt concrete pavement, gyratory mix, 8-inch compacted depth
Aggregate base grading D
Class 1, Type A (woven)
Separation-stabilization geotextile, Existing ground
LC
Select borrow
/2-inch lifts with tack coat in between 1over 2
4-inch compacted depth, placed in 1 1/2-inch size aggregate, 0.3 to < 3 million ESAL, 1/2-inch nominal maximum
Asphalt concrete pavement, gyratory mix, 8-inch compacted depth
Aggregate base grading D
Class 1, Type A (woven)
Separation-stabilization geotextile, [1]
[1]
Second lift of asphalt
First lift of asphalt
Aggregate base course
Edge of pavement
Ditch reconditioning
Ditch reconditioning
[3] reconditioning
Ditch
[4]
[1]
[1]
[2]
[2]
[2]
[2]
[3]
[4]
[4]
TRESTLE CREEK ROAD
10+00 to 47+00
1:21:
TRESTLE CREEK ROAD
47+00 to 136+00
1:2
1:
136+00 to 211+00
TYPICAL FILL PROPOSED TURNOUT SECTION
m a x
Varies m a x
TYPICAL CUT PROPOSED TURNOUT SECTION
End the top layer of separation-stabilization geotextile, Class 1 Type A (woven) 6 inches before the face of slope to prevent daylighting.
the geotextile a minimum of 1 foot.
centerline from the back of proposed edge of turnout. If the turnout occurs where geotextile is being placed on the mainline, overlap
On turnouts install the top layer of separation-stabilization geotextile, Class 1 Type A (woven) so that it extends 5 feet towards the
See connection details on Sheets D.4 and D.10 for the taper excavation transitions.
Taper the 12-inch roadway excavation depths to a 4-inch depth that will remain constant from stations 11+20 through 209+00.
At stations 10+00 and 211+00 perform 12-inch of roadway excavation to tie the typical section into the existing roadway surface.
Recondition ditches at the locations shown on the Ditch Reconditioning table.
Class 1 Type A (woven) Mainline Locations table.
Geotextile should be installed on the entire width of the roadway at the stations identified in the Separation-stabilization Geotextile, Install Separation-stabilization geotextile, Class 1 Type A (woven) on top of the subgrade prior to placing pavement structure.
FOOTNOTE:
SAFETY EDGE
1'
M in
1:3
M in
1:3
M in
1:3
[5]
5'
0.5'
5'
0.5'
Placing topsoil limits
Placing topsoil limits
C o n s tr u c ti o n
C o n s tr u c ti o n
L im it
L im it
C o n s tr u c ti o n
L im it
C o n s tr u c ti o n
L im it
C o n s tr u c ti o n
L im it
C o n s tr u c ti o n
L im it C o n s tr u c ti o n
L im it
C o n s tr u c ti o n
L im it
:2
M a y
S h e e t
C .1 p w w o r k w f l\ d
\B o n n e r
T y p ic a lS e c ti o n
.d g n
TYPICAL SECTIONS
PROJECT
NUMBER
C.1
Match existing Match existing
2%
Varies (14'-26')
Varies (14'-22')
-2%
2% slope
2% Crown
2% slope
2% Crown
PRELIM
IN
ARY
NOT FOR C
STATE PLANE COORDINATES GEO COORDINATES
POINT
NUMBER NORTH EAST ORTHOMETRIC
ELEVATION LATITUDE LONGITUDE ELLIPSOID
HEIGHT
COMBINED
FACTOR DESCRIPTION NOTE:
19101 2413012.880 2478607.447 2089.992 48°17'01.427016"N 116°20'59.653282"W 2034.470 0.999860503 5/8" IR W/FHWA ALUM CAP 1.
19102 2413204.149 2479208.685 2107.792 48°17'03.360761"N 116°20'50.785803"W 2052.312 0.999859451 5/8" IR W/FHWA ALUM CAP
19103 2413368.550 2479777.427 2124.283 48°17'05.026693"N 116°20'42.395530"W 2068.843 0.999858473 5/8" IR W/FHWA ALUM CAP
19104 2413511.833 2480338.657 2140.976 48°17'06.483488"N 116°20'34.113763"W 2085.577 0.999857488 5/8" IR W/FHWA ALUM CAP
19105 2413840.910 2480751.626 2158.809 48°17'09.762297"N 116°20'28.045187"W 2103.446 0.999856499 5/8" IR W/FHWA ALUM CAP
19106 2414258.934 2481182.108 2176.624 48°17'13.920087"N 116°20'21.727542"W 2121.302 0.999855505 5/8" IR W/FHWA ALUM CAP
19107 2414585.301 2481643.936 2198.185 48°17'17.175664"N 116°20'14.935735"W 2142.903 0.999854323 5/8" IR W/FHWA ALUM CAP
19108 2414764.973 2482112.987 2213.680 48°17'18.984066"N 116°20'08.020332"W 2158.435 0.999853428 5/8" IR W/FHWA ALUM CAP
19109 2414965.214 2482337.724 2228.832 48°17'20.976981"N 116°20'04.719757"W 2173.608 0.99985263 5/8" IR W/FHWA ALUM CAP
19110 2414955.625 2482536.829 2238.234 48°17'20.897312"N 116°20'01.774529"W 2183.023 0.999852116 5/8" IR W/FHWA ALUM CAP
19111 2414992.625 2482810.857 2240.274 48°17'21.282985"N 116°19'57.726655"W 2185.082 0.999851929 5/8" IR W/FHWA ALUM CAP
19112 2415378.839 2483156.296 2262.037 48°17'25.120053"N 116°19'52.661922"W 2206.889 0.999850776 5/8" IR W/FHWA ALUM CAP
19113 2415654.730 2483635.517 2271.063 48°17'27.878346"N 116°19'45.606352"W 2215.952 0.999850188 5/8" IR W/FHWA ALUM CAP
19114 2415758.067 2483952.571 2282.567 48°17'28.921684"N 116°19'40.929431"W 2227.479 0.999849536 5/8" IR W/FHWA ALUM CAP
19115 2415929.476 2484159.123 2293.521 48°17'30.628515"N 116°19'37.894092"W 2238.450 0.999848946 5/8" IR W/FHWA ALUM CAP
19116 2416052.817 2484573.311 2308.603 48°17'31.876359"N 116°19'31.782876"W 2253.561 0.999848092 5/8" IR W/FHWA ALUM CAP
19117 2416329.139 2484838.808 2325.392 48°17'34.622777"N 116°19'27.887340"W 2270.373 0.999847204 5/8" IR W/FHWA ALUM CAP
19118 2416340.915 2485119.300 2337.808 48°17'34.759681"N 116°19'23.740714"W 2282.807 0.999846521 5/8" IR W/FHWA ALUM CAP
19119 2416396.962 2485540.059 2360.318 48°17'35.343730"N 116°19'17.524680"W 2305.345 0.99984531 5/8" IR W/FHWA ALUM CAP
19120 2416753.662 2485786.097 2380.204 48°17'38.881771"N 116°19'13.925461"W 2325.252 0.999844282 5/8" IR W/FHWA ALUM CAP
19121 2417079.933 2486155.237 2400.065 48°17'42.128513"N 116°19'08.502251"W 2345.141 0.999843215 5/8" IR W/FHWA ALUM CAP
19122 2417270.385 2486699.655 2412.249 48°17'44.047683"N 116°19'00.471843"W 2357.352 0.99984246 5/8" IR W/FHWA ALUM CAP
19123 2417550.819 2487072.130 2438.561 48°17'46.842164"N 116°18'54.993928"W 2383.690 0.999841085 5/8" IR W/FHWA ALUM CAP
19124 2417721.379 2487600.107 2448.622 48°17'48.563585"N 116°18'47.204163"W 2393.783 0.999840438 5/8" IR W/FHWA ALUM CAP
19125 2417721.345 2488161.275 2461.698 48°17'48.603802"N 116°18'38.904940"W 2406.891 0.999839637 5/8" IR W/FHWA ALUM CAP
19126 2417908.095 2488530.877 2477.436 48°17'50.473302"N 116°18'33.458953"W 2422.653 0.999838769 5/8" IR W/FHWA ALUM CAP
19127 2418101.760 2488891.107 2497.859 48°17'52.410298"N 116°18'28.152206"W 2443.099 0.999837681 5/8" IR W/FHWA ALUM CAP
19128 2418238.133 2489185.093 2506.055 48°17'53.777117"N 116°18'23.818927"W 2451.316 0.999837197 5/8" IR W/FHWA ALUM CAP
19129 2418393.127 2489336.666 2518.528 48°17'55.317469"N 116°18'21.593829"W 2463.799 0.999836554 5/8" IR W/FHWA ALUM CAP
19130 2418506.535 2489591.067 2533.789 48°17'56.454772"N 116°18'17.843433"W 2479.076 0.999835746 5/8" IR W/FHWA ALUM CAP
19131 2418733.640 2489836.089 2542.383 48°17'58.713357"N 116°18'14.243845"W 2487.687 0.99983526 5/8" IR W/FHWA ALUM CAP
19132 2418971.991 2490253.824 2565.802 48°18'01.095161"N 116°18'08.090904"W 2511.133 0.999834012 5/8" IR W/FHWA ALUM CAP
19133 2419087.503 2490769.555 2595.138 48°18'02.271612"N 116°18'00.475378"W 2540.500 0.999832451 5/8" IR W/FHWA ALUM CAP
19134 2419328.685 2491139.569 2621.027 48°18'04.677783"N 116°17'55.028256"W 2566.413 0.999831101 5/8" IR W/FHWA ALUM CAP
19135 2419655.873 2491498.866 2677.024 48°18'07.931852"N 116°17'49.748575"W 2622.434 0.999828316 5/8" IR W/FHWA ALUM CAP
COORDINATE SYSTEM : Idaho West SPCS NAD83 (2011) VERTICAL DATUM : Orthometric elevations based on the NAVD88 GEOID12b
EPOCH DATE : 2010.000
CADD SYSTEM COORDINATE SYSTEM : ID83/2011-WF NSRS11(NAD83/2011) Idaho, West Zone, US Foot
PROJECT : Trestle Creek DATE OF FIELD WORK : Multiple entries
PROJECT UNITS : US SURVEY FOOT
-F eb -2
9:
A M
C
U se rs \a da m
.d av ie s\
D oc um en ts \P ro je ct s_
\I da ho \T re st le C re ek
\p w
Tr es tle
_C re ek _C on tr ol sh ee t.
xl sx
]S he et
To precisely check distances between points as measured on the ground, inverse the state plane coordinates and divide the computed distance by a mean combined factor of the two points.
PROJECT
D.1ID FLAP BONNER 841(1)
SHEET
NUMBER
SURVEY CONTROL
SHEET 1 OF 2
PRELIM
IN
ARY
NOT FOR C
STATE PLANE COORDINATES GEO COORDINATES
POINT
NUMBER NORTH EAST ORTHOMETRIC
ELEVATION LATITUDE LONGITUDE ELLIPSOID
HEIGHT
COMBINED
FACTOR DESCRIPTION NOTE:
19136 2419884.284 2491999.549 2714.757 48°18'10.221021"N 116°17'42.367082"W 2660.199 0.999826361 5/8" IR W/FHWA ALUM CAP 1.
19137 2419833.607 2492339.762 2732.037 48°18'09.744750"N 116°17'37.329691"W 2677.496 0.999825432 5/8" IR W/FHWA ALUM CAP
19138 2419797.019 2492693.644 2739.474 48°18'09.408403"N 116°17'32.091622"W 2684.952 0.999824969 5/8" IR W/FHWA ALUM CAP
19139 2419731.015 2493167.250 2751.132 48°18'08.790030"N 116°17'25.079683"W 2696.635 0.999824269 5/8" IR W/FHWA ALUM CAP
19140 2419800.397 2493670.602 2785.499 48°18'09.509615"N 116°17'17.641869"W 2731.030 0.999822476 5/8" IR W/FHWA ALUM CAP
19141 2419888.404 2494275.723 2828.994 48°18'10.419875"N 116°17'08.700656"W 2774.559 0.999820216 5/8" IR W/FHWA ALUM CAP
19142 2420045.848 2494471.467 2841.577 48°18'11.987042"N 116°17'05.821640"W 2787.155 0.999819557 5/8" IR W/FHWA ALUM CAP
19143 2419924.016 2494692.812 2857.943 48°18'10.799993"N 116°17'02.535155"W 2803.531 0.999818709 5/8" IR W/FHWA ALUM CAP
19144 2420002.230 2495130.866 2863.200 48°18'11.601861"N 116°16'56.063904"W 2808.813 0.999818327 5/8" IR W/FHWA ALUM CAP
19145 2419900.290 2495428.857 2864.836 48°18'10.616269"N 116°16'51.645852"W 2810.455 0.999818161 5/8" IR W/FHWA ALUM CAP
19146 2420115.067 2495776.612 2872.222 48°18'12.759451"N 116°16'46.524121"W 2817.863 0.999817704 5/8" IR W/FHWA ALUM CAP
19147 2420212.751 2496005.450 2882.002 48°18'13.738990"N 116°16'43.149285"W 2827.657 0.999817169 5/8" IR W/FHWA ALUM CAP
-F eb -2
9:
A M
C
U se rs \a da m
.d av ie s\
D oc um en ts \P ro je ct s_
\I da ho \T re st le C re ek
\p w
Tr es tle
_C re ek _C on tr ol sh ee t.
xl sx
]S he et
2) PROJECT : Trestle Creek DATE OF FIELD WORK : Multiple entries
PROJECT UNITS : US SURVEY FOOT
COORDINATE SYSTEM : Idaho West SPCS NAD83 (2011) VERTICAL DATUM : Orthometric elevations based on the NAVD88 GEOID12b
EPOCH DATE : 2010.000
CADD SYSTEM COORDINATE SYSTEM : ID83/2011-WF NSRS11(NAD83/2011) Idaho, West Zone, US Foot
To precisely check distances between points as measured on the ground, inverse the state plane coordinates and divide the computed distance by a mean combined factor of the two points.
PROJECT
D.2ID FLAP BONNER 841(1)
SHEET
NUMBER
SURVEY CONTROL
SHEET 2 OF 2
PRELIM
IN
ARY
NOT FOR C
turnout quantities.
and turnout work. See Sections E and F for approach and
Quantities are for mainline only and do not include approach
FOOTNOTE:
[1]
[2]
Excavated roadway material is unsuitable for backfill.
[2]
:5 u ly
T a b u la ti o n o f Q u a n ti ti e s p w w o r k w f l\ d \B o n n e r D
S h e e ts
.d g n
TABULATION OF QUANTITIES
PROJECT
NUMBER
D.3
IN
ARY
NOT FOR C
CABIN
GPS
GPS
CP
N
19101
19102
19103
1 1
2 1 3 1
4 1 5 1 6 1 7 1
CP
CP
N
10+00 to 11+22
1/2-inch lifts with tack coat in between. over 2
4-inch compacted depth, placed in 1 1/2-inch size aggregate, 0.3 < 3 million ESAL
1/2-inch nominal maximum
Asphalt concrete pavement, gyratory mix,Sawcutting pavement
8-inch compacted depth
Aggregate base grading D, aggregate base
Existing pavement
Existing
BEGIN PROJECT
Edge of pavement
Edge of pavement
Cleaning culvert in place
Cleaning culvert in place
Approach 4
Approach 5
Approach 6
Ditch reconditioning
Ditch reconditioning
Ditch reconditioning
Approach 3
Approach 2
Approach 1
Existing ROW
Existing ROW
Tapered roadway excavation
19104
19105
7 2
E= 2478581.24
N= 2413031.84 10+00.00
CONNECTION DETAIL
excavation roadway 12-inch excavation roadway 4-inch
NOTE:
1. Stationing and proposed work locations are approximate. Verify locations with CO.
2. Match existing roadway connections from SH-200 to Trestle Creek Road.
S H
:2
M a y
D
.4 p w w o r k w f l\ d \B o n n e r D
S h e e ts
.d g n
10+00 TO 39+00
PLAN AND PLAN
PROJECT
D.4
IN
ARY
NOT FOR C
Y T I L I T U
D E I R U B
G N I N R A W
CP
CP
CP
CP
N
19106
19107
19108
19109
5 4 6 4 7 4 8 4 9 5
W
ATER TOW
ER
CP
CP
CP
CP
N
Edge of pavement
Edge of pavement
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Ditch reconditioning
Approach 7
Turnout 1
Approach 8
Cleaning culvert in place
Proposed Turnout 1 easement
Proposed
Proposed easement
Proposed easement
Existing ROW
Existing ROW 19109
19110
19111
19112
7 5
5 6
1. Stationing and proposed work locations are approximate. Verify locations with CO.
NOTE:
2. See Right of Way Plan in Physical Data for details
:5
M a y
.5 p w w o r k w f l\ d \B o n n e r D
S h e e ts
.d g n
39+00 TO 68+00
PLAN AND PLAN
PROJECT
NUMBER
D.5
IN
ARY
NOT FOR C
CP
CP
CP
CP
N
19113
19114
19115
19116
19117
9 7 0 7
1 7
4 7 5 7
6 7
CP
CP
CP
CP
N
Edge of pavement
Edge of pavement
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Installation of 18-inch pipe culvert
Cleaning culvert in place
Turnout 2
See Section G
Site 1A
Bank Stabilization
Installation of 18-inch pipe culvert
Removal of pipe culvert and
Removal of pipe culvert
See Section G
Site 1B
Bank Stabilization
Approach 9
Proposed Turnout 2
See Section G
Site 2A
Bank Stabilization
See Section G
Site 2B
Bank Stabilization
Ditch reconditioning
See Section G
Site 3A-1
Stabilization
Bank
See Section G
Site 3A-2
Bank Stabilization
Installation of 18-inch pipe culvert
Removal of pipe culvert
Ditch reconditioning
See Section G
Site 3B
Bank Stabilization
Proposed easement
Proposed easement
Proposed easement
Proposed easement
Existing ROW
Existing ROW Ditch reconditioning
Approach 10
Ditch reconditioning
19117
19118
19119
19120
NOTE:
1. Stationing and proposed work locations are approximate. Verify locations with CO.
2. See Right of Way Plan in Physical Data for details.
:5
M a y
.6 p w w o r k w f l\ d \B o n n e r D
S h e e ts
.d g n
68+00 TO 97+00
PLAN AND PLAN
PROJECT
NUMBER
D.6
IN
ARY
NOT FOR C
A
P P L E
S
P R
U C
E
A
L D
E R
C
E D
A R
F I R
F I R
CP
GPS
CP
N
19121
19122
19123
0 1 1 1
CP
Edge of pavement
Edge of pavement
Cleaning culvert in place
Cleaning culvert in place
Approach 11 Approach 12
Proposed Turnout 3
Approach 13
Approach 14
Existing ROW
Existing ROW
19124
19125
19126
7 1 8 1
9 1
1. Stationing and proposed work locations are approximate. Verify locations with CO.
NOTE:
:5
M a y
.7 p w w o r k w f l\ d \B o n n e r D
S h e e ts
.d g n
97+00 TO 126+00
PLAN AND PLAN
PROJECT
NUMBER
D.7
IN
ARY
NOT FOR C
W
G
PS
CP
CP
CP
CP
N
19127
19128
19129
19130
19131
CP
CP
CP
N
Edge of pavement
Edge of pavement
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Proposed Turnout 4
See Section G
Site 4
Bank Stabilization
Approach 15 Approach 16
Proposed Turnout 5
Proposed Turnout 6
Approach 17
Approach 18
Proposed easement
Proposed easement
Existing ROW
Existing ROW
Protect existing tree existing tree
Protect
19131
19132
19133
19134
6 1 7 1
8 1
NOTE:
1. Stationing and proposed work locations are approximate. Verify locations with CO.
2. See Right of Way Plan in Physical Data for details.1 :5 u ly
.8 p w w o r k w f l\ d \B o n n e r D
S h e e ts
.d g n
126+00 TO 155+00
PLAN AND PLAN
PROJECT
D.8
IN
ARY
NOT FOR C
CP
N
19135
19136
19137
CP
CP
CP
N
Edge of pavement
Cleaning culvert in place Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Edge of pavement
Approach 19
Proposed Turnout 7
Proposed Turnout 8
Proposed easement
Proposed easement
Existing ROW
19138
19139
19140
2 1 3 1
1. Stationing and proposed work locations are approximate. Verify locations with CO.
NOTE:
2. See Right of Way Plan in Physical Data for details.
:0
M a y
.9 p w w o r k w f l\ d
\B o n n e r
D
S h e e ts
.d g n
155+00 TO 184+00
PLAN AND PLAN
PROJECT
NUMBER
D.9
IN
ARY
NOT FOR C
CP
CP
N
19141
19142
19143
191441
2 1
6 1
CP
209+00 to 210+88.79
.7
END PROJECT
tack coat in between placed in 1 1/2-inch over 2 1/2-inch lifts with
4-inch compacted depth, size aggregate, 0.3<3 million ESAL
1/2-inch nominal maximum
Asphalt concrete pavement, gyratory mix, 8-inch compacted depth
Aggregate base grading D, Excavation limit
Edge of pavement
Edge of pavement
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Cleaning culvert in place
Proposed Turnout 9 reconditioning
Ditch
Ditch reconditioning
Approach 20
Turnout 3
Approach 21
Existing ROW
Existing aggregate surfacing
19145
19146
19147
0 2
210+88.79
E= 2,496,424.4813
N= 2,420,314.6523
CONNECTION DETAIL
excavation roadway 12-inch excavation roadway 4-inch
NOTE:
1. Stationing and proposed work locations are approximate. Verify locations with CO.
Approx. 39,000 SQFT
Staging Area
:1
M a y
D
.1 p w w o r k w f l\ d
\B o n n e r
D
S h e e ts
.d g n
184+00 TO 211+00
PLAN AND PLAN
PROJECT
NUMBER
D.10
IN
ARY
NOT FOR C
NOTE:
1. See Sheet E.2 for layout information.
:0 e c e m b e r
T a b u la ti o n o f Q u a n ti ti p w w o r k w f l\ d \B o n n e r e a .d g n
TABULATION OF QUANTITIES
PROJECT
NUMBER
E.1
IN
ARY
NOT FOR C
Centerline Edge of pavement
Centerline with tack coat in between.
1/2-inch lifts1 1/2-inch over 2 compacted depth, placed in
0.3 < 3 million ESAL, 4-inch maximum size aggregate, gyratory mix, 1/2-inch nominal
Asphalt concrete pavement, depth varies
Aggregate base grading D, S t a r t
Existing aggregate surface
8-inch compacted depth
Aggregate base grading D
E n d
E d g e o f m a in li n e
1 2
NOTE:
or as approved by CO.
4. Keep maximum grade change to 8% construction.
3. Verify in the field with the CO prior to approximate 3 ft buffer of ROW lines.
approaches and turnouts within an
2. Lengths are measured to keep
1. Match the existing approach widths.1 2
LT APPROACHES AND TURNOUTS RT APPROACHES AND TURNOUTS
Direction of stationing Direction of stationing
W
W
DETAIL
APPROACH AND TURNOUT
W
:3
A p r il
E x is ti n g A p p r o a c h a n d T u r n o u t L a y o u t D e ta il p w w o r k w f l\ d \B o n n e r e a .d g n
TURNOUT LAYOUT DETAILS
EXISTING APPROACH AND
PROJECT
NUMBER
E.2
IN
ARY
NOT FOR C
4. Topsoil quantities estimated for a 4-inch depth.
3. See Sheet F.2 for locations and layout information.
2. Tack coat estimated at 0.008 GAL/SQFT and 240 GAL/TON.
1. Asphalt pavement concrete estimated at 1.94 TON/CUYD.
FOOTNOTE:
Excavated roadway material is unsuitable for backfill.
:0
M a y
T a b u la ti o n o f Q u a n ti ti p w w o r k w f l\ d \B o n n e r f s h e e ts
.d g n
TABULATION OF QUANTITIES
PROJECT
NUMBER
F.1
IN
ARY
NOT FOR C
LT
Centerline
T
W
2 3
1 4
NOTE:
2. Keep maximum grade change to 8% or as approved by CO.
1. Widths to be verified in the field with the CO prior to construction.
:4
M a y
P
R O
P O
S E
D T
U R
N O
U T
L A
Y O
U T
D E
T
IL
p w w o r k w f l\ d \B o n n e r f s h e e ts
.d g n
DETAIL
PROPOSED TURNOUT LAYOUT
PROJECT
F.2
IN
ARY
NOT FOR C
from the CO.
conserved from the work site, local streambed material, fish passage boulders, and rootwads may be used upon approval
2. If additional quantities of streambed material, fish passage boulders, and rootwads are needed outside of what has been
1. Place conserved streambed material below the ordinary high water mark.
:4 u n e
T a b u la ti o n o f Q u a n ti ti p w w o r k w f l\ d
\B o n n e r g a .d g n
TABULATION OF QUANTITIES
PROJECT
NUMBER
G.1
IN
ARY
NOT FOR C
52.8'
12'
63.
1'
.9
12'
.9
7 7
N
Removal of pipe culvert
Existing ground geotextile, Class 1, Type D (non-woven)
Separation-stabilization
OHW (Q1.5 Water surface elevation)
Q100 Water surface elevation
28.8 LNFT
18-inch pipe culvert
74+44.30
Placed riprap, Method A, Class 2
Site 1A Profile
Removal of pipe culvert
Removal of pipe culvert
Method A, Class 4
Placed riprap, Method A, Class 2
Placed riprap, geotextile, Class 1, Type D (non-woven)
Separation-stabilization
29 LNFT
18-inch pipe culvert
74+44.30
18-inch pipe culvert, 28.8 LNFT
74+48.30
(See Sheet G.3 for details)
Site 1B Profile
Site 1B Bank Stabilization Proposed edge of pavement
Method A, Class 2
Placed riprap, Placed riprap, Method A, Class 2
Site 1A Bank Stabilization
See Sheet G.12 for riprap detail
Placed riprap, Method A, Class 4
Channel thalweg
Approx. existing ROW limit
Approx. proposed easement limit
Construction limit
0+30 0+40 0+50 0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30 1+40 1+50 1+60 1+70
2,275 2,275
2,280 2,280
2,285 2,285
2,290 2,290
2,295 2,295
2,300 2,300
2,305 2,305
2,310 2,310
1.75:1
2'
'1
1.
:1
3.1'
NOTE:
2. Do not dispose of any natural material encountered on site. Reuse the material or leave it on site.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along
8.6'
:5
J u n e
[S
H E
E T
F
.2
S it e A
P la n P ro fi le p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
73+74.00 - 75+05.90
SITE 1A, BANK STABILIZATION
PROJECT
G.2ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
7 7
N
Placed riprap, Method A, Class 4
Mitigation, streambed material (conserved) Existing ground
Cuttings, willow pole (see Sheet G.11 for placement)
Class 1, Type D (non-woven) geotextile, Separation-stabilization
OHW (Q1.5 Water surface elevation)
Q100 Water surface elevation
Site 1B Profile
Bank Stabilization
Site 1B
Channel thalweg
(See Sheet G.2 for details)
Site 1A Profile
Riprap Crest El. 2299.3' edge of pavement
Proposed
Excavation limit
Proposed terrain
Approx. proposed easement limit
Site 1A Bank Stabilization
Construction limit
0+00 0+10 0+20 0+30 0+40 0+50 0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30 1+40 1+50
2,280 2,280
2,285 2,285
2,290 2,290
2,295 2,295
2,300 2,300
2,305 2,305
2,310 2,310
2,315 2,315
2,320 2,320
See Sheet G.11
Roughened toe, boulder clusters
1.5:1 :1
120 LNFT
3. Backfill placed riprap with conserved streambed material to the approximate thalweg elevation.
2. Set the top of the revetment toe below historic scour elevation, or to refusal, as described in Sheet G.10.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along
.5
15.6'
.5 '1 leave it on site.
5. Do not dispose of any natural material encountered on site. Reuse the material or irregularity and habitat complexity. See Sheet G.11 for locations.
4. Place fish passage boulders along the revetment toe, 30 ft. o.c., to increase bank line
NOTE:
:0
J u n e
[S
H E
E T
F
.3
S it e
B
P la n
P ro p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
76+08.00 - 77+28.00
SITE 1B, BANK STABILIZATION
PROJECT
G.3ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
Placed riprap, Method A, Class 4
Mitigation, streambed material (conserved)
Q100 Water surface elevation
OHW (Q1.5 Water surface elevation)
Class 1, Type D (non-woven) geotextile, stabilization
Separation and
Existing ground
Site 2A Profile
(See Sheet G.5 for details)
Site 2B
(See Sheet G.6 for details)
Site 3A-1
(See Sheet G.7 for details)
Site 3A-2
Bank Stabilization
Site 2A existing log jam
Preserve and protect
See Sheet G.11
Roughened toe, boulder clusters the Ordinary High Water
Backfill riprap in between trees above
Placed riprap, Method A, Class 4
Cuttings, willow pole (see Sheet G.11 for placement)
Proposed edge of pavement
Proposed terrain
Excavation limit
Approx. proposed easement limit
Stabilization
Site 2B Bank
Bank Stabilization
Site 3A-1
Bank Stabilization
Site 3A-2
Construction limit
0+80 0+90 1+00 1+10 1+20 1+30 1+40 1+50 1+60 1+70 1+80 1+90 2+00 2+10 2+20
2,300 2,300
2,305 2,305
2,310 2,310
2,315 2,315
2,320 2,320
2,325 2,325
2,330 2,330
2,335 2,335
81+00.00 - 81+85.00
SITE 2A, BANK STABILIZATION
1.5:1
3. Backfill placed riprap with conserved streambed material to the approximate thalweg elevation.
2. Set the top of the revetment toe below historic scour elevation, or to refusal, as described in Sheet G.10.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along
18'
.1
:1 leave it on site.
5. Do not dispose of any natural material encountered on site. Reuse the material or irregularity and habitat complexity. See Sheet G.11 for locations.
4. Place fish passage boulders along the revetment toe, 30 ft o.c., to increase bank line
NOTE:
:0
J u n e
S h e e t_
F .4
S it e A
R e v
S p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
PROJECT
NUMBER
SHEET
G.4ID FLAP BONNER 841(1)
PRELIM
IN
ARY
NOT FOR C
Method A, Class 4
Placed riprap, Mitigation, streambed material (conserved)
Q100 Water surface elevation
OHW (Q1.5 Water surface elevation)
Class 1, Type D (non-woven) geotextile, Stabilization-separation
(See Sheet G.4 for details)
Site 2A
Bank Stabilization
Site 2B log jam protect existing
Preserve and
(See Sheet G.6 for details)
Site 3A-1
(See Sheet G.7 for details)
Site 3A-2
Site 2B Profile
Existing surface transiton. Do not fill below OHW level.
and fish passage boulder (15 CUYD) along
Place Mitigation, rootwad (3 EACH) the Ordinary High Water
Backfill riprap in between trees above
Placed riprap, Method A, Class 4
Cuttings, willow pole (See Sheet G.11 for placement)
See Sheet G.11
Roughened toe, boulder clusters limit
Excavation
Approx. proposed easement limit
Bank Stabilization
Site 2A
Bank Stabilization
Site 3A-1
Bank Stabilization
Site 3A-2
Construction limit
0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30 1+40 1+50 1+60 1+70 1+80 1+90 2+00
2,300 2,300
2,305 2,305
2,310 2,310
2,315 2,315
2,320 2,320
2,325 2,325
2,330 2,330
2,335 2,335
2,340 2,340
3. Backfill placed riprap with conserved streambed material to the approximate thalweg elevation.
2. Set the top of the revetment toe below historic scour elevation, or to refusal, as described in Sheet G.10.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along
LNFT
leave it on site.
6. Do not dispose of any natural material encountered on site. Reuse the material or
5. Rootwad - 18" ± 6" diameter, 22' - 26' length, 5' ± 6" rootwad diameter.
irregularity and habitat complexity. See Sheet G.11 for locations.
4. Place fish passage boulders along the revetment toe, 30 ft. o.c., to increase bank line
1.5:1
:1
16.9'
.5
NOTE:
:0
J u n e
[S h e e t_
F .5
S it e B
B a c k fi ll R v p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
81+85.00 - 82+72.22
SITE 2B, BANK STABILIZATION
PROJECT
NUMBER
SHEET
G.5ID FLAP BONNER 841(1)
PRELIM
IN
ARY
NOT FOR C
Placed riprap, Method A, Class 4
Mitigation, streambed material (conserved)
Riprap toe
Existing ground
(See Sheet G.7 for details)
Site 3A-2
(See Sheet G.8 for details)
Site 3B Bank Stabilization
Site 3A-1
Q100 Water surface elevation
OHW (Q1.5 Water surface elevation)
Class 1, Type D (non-woven)
Separation-stabilization geotextile, G.5 for details)
(See Sheet
Site 2B
Site 3A-1 profile transition. Do not fill below OHW level.
and boulder balast (15 CUYD) along
Site 2B place rootwad (3 EACH)
Removal of pipe culvert
See Sheet G.11
Roughened toe, boulder clusters
18-inch pipe culvert, 30 LNFT
84+07.00
Cuttings, willow pole (See Sheet G.11 for placement) along top of bank, above OHW.
Place riprap, method A, Class 4
Method A, Class 2
Placed riprap, (See Sheet G.4 for details)
Site 2A
See Sheet G.12
Method A, Class 2
Placed riprap, Infiltration Basin
Proposed terrain
Excavation limit
Approx. proposed easement limit
Site 2A Bank Stabilization
Construction limit
0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30 1+40 1+50 1+60 1+70 1+80 1+90
2,310 2,310
2,315 2,315
2,320 2,320
2,325 2,325
2,330 2,330
2,335 2,335
2,340 2,340
2,345 2,345
2+0+50
(2 EACH)
spaced at 5'
Mitigation, rootwad
3. Backfill placed riprap with conserved streambed material to the approximate thalweg elevation.
2. Set the top of the revetment toe below historic scour elevation, or to refusal, as described in Sheet G.10.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along leave it on site.
8. Do not dispose of any natural material encountered on site. Reuse the material or
7. Rootwad - 18" ± 6" diameter, 22' - 26' length, 5' ± 6" rootwad diameter.
the bank line.
6. Maximize trunk embedment, but allow the rootwad end to project into flow from irregularity and habitat complexity. See Sheet G.11 for locations.
5. Place fish passage boulders along the revetment toe, 30 ft o.c., to increase bank line
1.5:1
.6
NOTE:
12'
.9
12'
.9
1.5:1
:0
J u n e
[S
H E
E T
F
.6
S it e A
P la n P ro fi le L o g R p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
82+72.22 - 84+27.61
SITE 3A - 1, BANK STABILIZATION
PROJECT
G.6ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
(See Sheet G.5 for details)
Site 2B
(See Sheet G.6 for details)
Site 3A - 1
Removal of pipe culvert
Bank Stabilization
Site 3A-2
Site 3A-2 profile
Placed riprap, Method A, Class 4
Mitigation, streambed material (conserved)
Class 1, Type D (non-woven) geotextile, Separation-stabilization
Q100 Water surface elevation
OHW (Q1.5 Water surface elevation)
Existing ground
See Sheet G.11
Roughened toe, boulder cluster
Cuttings, willow pole (See Sheet G.11 for placement)
18-inch pipe culvert, 30 LNFT
84+07.00
Proposed edge of pavement
Method A, Class 2
Placed riprap, Method A, Class 2
Placed riprap, Infiltration Basin
Proposed terrain
Excavation limit
Approx. proposed easement limit
Construction limit
Bank Stabilization
Site 2B
Bank Stabilization
Site 3A-1
Bank Stabilization
Site 3B
1+00 1+10 1+20 1+30 1+40 1+50 1+60 1+70 1+80 1+90 2+00 2+10 2+20 2+30 2+40
2,310 2,310
2,315 2,315
2,320 2,320
2,325 2,325
2,330 2,330
2,335 2,335
2,340 2,340
2,345 2,345
2,350 2,350
145 LNFT
3. Backfill placed riprap with conserved streambed material to the approximate thalweg elevation.
2. Set the top of the revetment toe below historic scour elevation, or to refusal, as described in Sheet G.10.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along
1.5:1
18.8'
:1 leave it on site.
5. Do not dispose of any natural material encountered on site. Reuse the material or irregularity and habitat complexity. See Sheet G.11 for locations.
4. Place fish passage boulders along the revetment toe, 30 ft. o.c., to increase bank line
NOTE:
12'
.9
12'
.9
:1
J u n e
[S
H E
E T
F
.7
S it e
A
P la n
P ro fi le
R p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
84+27.61 - 85+73.18
SITE 3A - 2, BANK STABILIZATION
PROJECT
G.7ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
Place riprap, Method A, Class 4 Mitigation, streambed material (conserved)
Q100 water surface elevation
OHW (Q1.5 water surface elevation)
Existing ground
Class 1, Type D (non-woven)
Stabilization-separation geotextile, Bank Stabilization
Site 3B
Site 3B Profile
(See Sheet G.7 for details)
Site 3A-2
See Sheet G.11
Roughened toe, boulder clusters immediately upstream of Site 3B
Relocate large 8' boulder to right bank
Remove and set boulder
Site 3B
Cuttings, willow pole (See Sheet G.11 for placement)
Excavation limit
Approx. proposed easement limit
Bank Stabilization
Site 3A-2
Construction limit
0+90 1+00 1+10 1+20 1+30 1+40 1+50 1+60 1+70 1+80 1+90 2+00 2+10 2+20 2+30
2,320 2,320
2,325 2,325
2,330 2,330
2,335 2,335
2,340 2,340
2,345 2,345
2,350 2,350
2,355 2,355
3. Backfill placed riprap with conserved streambed material to the approximate thalweg elevation.
2. Set the top of the revetment below historic scour elevation, or to refusal, as described in Sheet G.10.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along
180 LNFT
1.5:1
20.6'
:1
NOTE:
leave it on site.
5. Do not dispose of any natural material encountered on site. Reuse the material or irregularity and habitat complexity. See Sheet G.11 for locations.
4. Place fish passage boulders along the revetment toe, 30 ft. o.c., to increase bank line
:1
J u n e
[S
H E
E T
F
.8
S it e B
P la n P ro fi le R p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
86+53.86 - 88+35.25
SITE 3B, BANK STABILIZATION
PROJECT
G.8ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
W
TP
TP
JB
IR
I
R W
Y P
C
N
Bank Stabilization
Site 4
Site 4 Profile
(36-inch diameter well)
Removal of structures and obstructions
Placed riprap, Method A, Class 4
Mitigation, streambed material (conserved)
Class 1, Type D (non-woven)
Separation-stabilization geotextile, Existing ground
Q100 Water surface elevation
OHW (Q1.5 Water surface elevation)
(existing log sill)
Removal of structures and obstructions
See Sheet G.11
Roughened toe, boulder clusters
Protect and preserve existing log jam
Cuttings, willow pole (See Sheet G.11 for placement)
Proposed edge of pavement Approach 15
Proposed terrain Excavation limit
Approx. proposed easement limit
Construction limit
0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30 1+40 1+50 1+60 1+70 1+80 1+90 2+00
2,480 2,480
2,485 2,485
2,490 2,490
2,495 2,495
2,500 2,500
2,505 2,505
2,510 2,510
2,515 2,515
.5
3.5'
15.8' 1.2' 4'
3. Backfill placed riprap with conserved streambed material to the approximate thalweg elevation.
2. Set the top of the revetment toe below historic scour elevation, or to refusal, as described in Sheet G.10.
the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stabilization in the field. Protect existing trees along
125'
1.5:1
NOTE:
leave it on site.
5. Do not dispose of any natural material encountered on site. Reuse the material or irregularity and habitat complexity. See Sheet G.11 for locations.
4. Place fish passage boulders along the revetment toe, 30 ft. o.c., to increase bank line
:2
J u n e
[S
H E
E T
F
.9
S it e P la n P ro p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
130+15.35 - 131+39.60
SITE 4, BANK STABILIZATION
PROJECT
NUMBER
SHEET
G.9ID FLAP BONNER 841(1)
PRELIM
IN
ARY
NOT FOR C
material (conserved)
Mitigation, streambed
Mitigation, streambed material (conserved) riprap to design thickness.
before backfilling and keying in
Clean boulder of debris and vegetation riprap D100 buried in embankment.
Existing large undercut boulder (tree), greater than Class 4 and keying in riprap to design thickness.
and vegetation before backfilling riprap D100. Clean boulder of debris
Existing large boulder, greater than Class 4
Existing ground
Existing ground
Placed riprap, Method A, Class 4
Placed riprap, Method A, Class 4
Placed riprap, Method A, Class 4
4. Bury and backfill placed riprap with conserved streambed material to match existing ground.
3. Wash in smaller gradation streambed material, after compacting mass, to fill voids according to Subsection 647.06.
2. To the extent practicable, tamp down riprap rock with buckets or approved equipment to ensure a stable solid mass surround existing boulders remain in place.
backfill, place and compact riprap to design thickness (4 feet).
If substrate material exceeds riprap D100, field fit the bank stabilization structure and verify placement with CO prior to construction. Clean vegetation and debris around large boulders,
1. Excavation limits will vary depending on site substrate conditions. Excavate to scour mark, approximately 3 feet below thalweg, or presence of solid substrate material larger than 27-inches.
embankment (Site 3) boulder buried in undercut
Example of large
BOULDER (TREE) EMBANKMENT
NOTE:
GREATER THAN 27-INCHES
EMBEDDED BOULDER
OWH (Q1.5 Water surface elevation)OWH (Q1.5 Water surface elevation)
Q100 Water surface elevation Q100 Water surface elevation
:2
J u n e
[S
H E
E T
F
.1
D
E T
A
IL
p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
EXCAVATION DETAILS
PROJECT
G.10
IN
ARY
NOT FOR C
Road shoulder
Boulder cluster
Boulder cluster
30' ± 5'
A B
A
B
Roughened toe
Road shoulder
Riprap crest
Roughened toe
Stream bottom
Placed riprap, method A, class 4
OHW
Road shoulder Riprap crest
OHW
Stream bottom
Placed riprap, method A, class 4
Flow direction
Revetment limit
Revetment crest
Revetment key toe
Varies see plan and profile sheets
Riprap revetment key toeRiprap revetment key toe
Water table
Pole planting
Cuttings
Class 1, Type D (non-woven) Separation-stabilization geotextile, Boulder cluster
Class 1, Type D (non-woven) Separation-stabilization geotextile,
3. Cuttings: Cuttings, Willow Pole, live cuttings at random spacing of 2 per SQYD. Do not plant within 3 feet from the riprap crest.
2. Roughened toe: Mitigation, Streambed Material (Conserved Bank Stone), loosely placed along toe between boulder clusters.
1. Boulder cluster: Fish Passage Boulder, loosely placed 5-6 each, spaced 30 feet ± 5 feet along bank toe.
SECTION A-A SECTION B-B
PLAN
NOTE:
NO SCALE
:1
M a y
[S
H E
E T
F
.1
D E
T A
IL
S
C o p y p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
DETAILS
CLUSTER
ROUGHENED TOE / BOULDER
PROJECT
G.11
IN
ARY
NOT FOR C
Class 1, Type D (non-woven)
Separation-stabilization geotextile, Protext existing trees along the embankment as directed by the CO.
1. The CO will determine the exact limit of bank stablization in the field.
NOTE:
(12 CUYD)
:3
J u n e
R
IP
R
A P
T Y
P
IC
A L
S E
C T
IO
p w w o r k w f l\ d \B o n n e r G
S h e e ts
C le a n .d g n
RIPRAP TYPICAL SECTIONS
PROJECT
G.12
IN
ARY
NOT FOR C
:3
D e c e m b e r
T A
B U
L A
T
IO
N O
F Q
U A
N T
IT
IE
p w w o r k w f l\ d
\i d a h a .d g n
TABULATION OF QUANTITIES
PROJECT
H.1
IN
ARY
NOT FOR C
CABIN
1 1
2 1 3 1
4 1 5 1 6 1 7 1
N
Fiber roll
Fiber roll
BEGIN PROJECT
Fiber roll
Fiber roll
Proposed edge of pavement
Proposed edge of pavement
Approach 1
Approach 2
Approach 3
Approach 3
Approach 4
Approach 5
Approach 6
7 2
10+00
:3
F e b r u a r y
S
E C
S E
C
S h e t] p w w o r k w f l\ d \B o n n e r H
S h e e ts
.d g n
10+00 TO 39+00
PLAN AND PLAN
EROSION CONTROL
PROJECT
NUMBER
H.2
IN
ARY
NOT FOR C
5 4 6 4 7 4
8 4 9 5
W
ATER TOW
ER
N
Fiber roll
Fiber roll
Fiber roll Fiber roll
Fiber rollFiber roll
Fiber roll
Fiber roll
Fiber roll
Proposed edge of pavement
Proposed edge of pavement
Approach 7
Turnout 1
Approach 8
Proposed Turnout 1
7 5
5 6
:2
F e b r u a r y
S
E C
S E
C
S h e p w w o r k w f l\ d \B o n n e r H
S h e e ts
.d g n
39+00 TO 68+00
PLAN AND PLAN
EROSION CONTROL
PROJECT
NUMBER
H.3
IN
ARY
NOT FOR C
9 7 0 7
1 7
4 7 5 7
6 7
N
Silt fence
Silt fence Silt fence
Silt fence
Silt fence
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Site 1A
Bank stabilization
Site 2A
Bank stabilization
Site 2B
Bank stabilization
Site 3A-1
Bank stabilization
Site 3A-2
Bank stabilization
Site 1B
Bank stabilization
Silt fence
Silt fence
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Proposed edge of pavement
Proposed edge of pavement
Turnout 2
Approach 9
Proposed Turnout 2
Site 3B
Bank stabilization
Fiber roll
Fiber roll
Fiber roll
Approach 10
Fiber roll
:2
F e b r u a r y
S
E C
S E
C
S h e p w w o r k w f l\ d \B o n n e r H
S h e e ts
.d g n
68+00 TO 97+00
PLAN AND PLAN
EROSION CONTROL
PROJECT
H.4
IN
ARY
NOT FOR C
0 1 1 1
N
Fiber roll
Fiber roll
Fiber roll
Silt fence
Fiber roll
Fiber roll
Proposed edge of pavement
Proposed edge of pavement
Approach 11 Approach 12
Proposed Turnout 3
Approach 13
Approach 14
7 1 8 1
9 1
:2
F e b r u a r y
S
E C
S E
C
S h e p w w o r k w f l\ d \B o n n e r H
S h e e ts
.d g n
97+00 TO 126+00
PLAN AND PLAN
EROSION CONTROL
PROJECT
NUMBER
H.5
IN
ARY
NOT FOR C
N
Silt fence
Fiber roll
Fiber roll
Silt fence Fiber roll
Fiber roll
Site 4
Bank stabilization
Silt fence
Silt fence
Fiber roll
Silt fence
Silt fence
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Proposed edge of pavement
Proposed edge of pavement
Proposed Turnout 4
Approach 15 Approach 16
Proposed Turnout 5
Approach 17
Approach 18Proposed Turnout 6
6 1 7 1
8 1
:3
F e b r u a r y
S
E C
S E
C
S h e p w w o r k w f l\ d \B o n n e r H
S h e e ts
.d g n
126+00 TO 155+00
PLAN AND PLAN
EROSION CONTROL
PROJECT
NUMBER
H.6
IN
ARY
NOT FOR C
N
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Silt fence
Silt fence
Silt fence
Silt fence
Fiber roll
Fiber roll
Fiber roll Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Proposed edge of pavement
Proposed edge of pavement
Approach 19
Proposed Turnout 7
Proposed Turnout 8
2 1 3 1
:3
F e b r u a r y
S
E C
S E
C
S h e p w w o r k w f l\ d \B o n n e r H
S h e e ts
.d g n
155+00 TO 184+00
PLAN AND PLAN
EROSION CONTROL
PROJECT
H.7
FLAP BONNER 841(1)ID
IN
ARY
NOT FOR C
2 1
6 1
N
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Silt fence
Silt fence
Fiber roll
Fiber roll
Fiber roll
Fiber roll
Proposed edge of pavement
Proposed edge of pavement
Approach 20
Approach 21
Proposed Turnout 9
Turnout 3
END PROJECT
Existing staging area 1
0 2
211+00
:0
F e b r u a r y
S
E C
S E
C
S h e p w w o r k w f l\ d \B o n n e r H
S h e e ts
.d g n
184+00 TO 211+00
PLAN AND PLAN
EROSION CONTROL
PROJECT
NUMBER
H.8
IN
ARY
NOT FOR C
NO SCALE
POST AND GEOTEXTILE INSTALLATION DETAIL
SILT FENCE INSTALLATION AT TOE OF FILL
Fi ll slo pe
T o e o f s lo p e
PLAN
ELEVATION
4.
3.
2.
1.
T o e o f s lo p e
Fi ll sl op e
ELEVATION
PLAN
PLAN
PLAN
END DETAIL
END POSTS DETAIL
POSTS AT JOINTS
Geotextile
Steel or wood post
Backfilled and compacted soil f o r s p a c in g
S e e N o te
Limits of clearing
(undisturbed)
Existing ground
Silt fence reinforcement
NOTE:
Staple or tie
Section B
Geotextile fabric, Tie top of posts together driven tightly together.
Steel or wood posts
Steel or wood post
Staple or tie
Geotextile fabric
Fasten fabric to posts around each post one full turn.
Fold geotextile fabric See Note 3
End Posts Detail
End posts, see
End Posts Detail
End posts, see
See Note 3 fabric, Section A
Geotextile
Flow
Flow
Flow running around the ends.
Curve ends of silt fence upgrade to prevent water from as possible.
Install silt fence to follow the ground contours as closely does not slide down, supporting posts.
All types must ensure silt fence remains attached to, and manufacturer's recommendations for installation procedures.
as long as specified dimensions are satisfied. Follow
Alternate preassembled silt fence options will be allowed m in m in m in
6-foot (max.) spacing without silt fence reinforcement.
10-foot (max.) spacing with silt fence reinforcement.
4" min.
6" min. trench
DETAIL APPROVED FOR USE 10/2016
REVISED:
157-1W
WFLHD DETAIL
SILT FENCE
:1
S e p te m b e r
D e t
W p w w o r k w f l\ d \W
.d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
H.9ID FLAP BONNER 841(1)
IN
ARY
NOT FOR C
Spacing Slope
STAKES REQUIRED
1:1
1:2
1:3
1:4 or flatter for each roll
Stakes required
FIBER ROLL SPACING
Fiber roll length
Fl ow
T o e o f fi ll s lo p e
ELEVATION
PLAN
disturbed areas
Runoff from
INSTALLATION BEYOND TOE OF SLOPE
INSTALLATION ALONG SLOPES
FIBER ROLL STAKING DETAIL
PROPERLY STAKED AND ENTRENCHED FIBER ROLL
Existing ground (typ.)
Fiber roll
Flow direction
Slope
Direction of runof f from distur bed area s sp ac in g ch ar t
S ee F ib er R ol l
Fiber roll ff o n ur f o n oi t c er i
D along contours
Install fiber rolls
Fiber roll
Slope
Fi ll slo pe
Direction of runoff ground
Existing soil to match ground level
Backfilled and compacted
Flow larger than fiber roll wood stakes. See Note 2.
Pay lim its
Pay lim its
SLOPE PROTECTION INSTALLATION
ALTERNATE FIBER ROLL JOINT DETAIL
FIBER ROLL LAPPING DETAIL
on uphill side of fiber roll
Place excavated material Stagger joints (typ.)
2.
1.
permanent installations. Do not crush fiber roll while staking.
roll is secure to slope. Live stakes may be used for and install fiber rolls
Step 1: Excavate trench Step 2: Backfill soil against fiber rolls
FIBER ROLL
(FT)
(FT)
2" (min.) Excavate trench 2"
1" x 1" or 1" Ø ove rlap
12" (m in.)
t o m in m in
1" x 1" Wood stake as specified in plans
3' min. or
3' (min.)
Drive stakes at each end and at 4-foot spacing until fiber fiber roll and space stakes at 4-foot max.
6-inches from fiber roll end angles towards the adjacent
Overlap fiber rolls 12-inch minimum. Drive stakes at
NOTE:
WFLHD DETAIL
DETAIL APPROVED FOR USE 10/2014
7/2016 REVISED:
157-21W
:3
S e p te m b e r
D e t
W p w w o r k w f l\ d \W
.d g n
DETAIL
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
PROJECT
NUMBER
SHEET
ID FLAP BONNER 841(1) H.10
PRELIM
IN
ARY
NOT FOR C
10.4 x 16 20301 -1900
60201 -0600
60704 -0000
Station E S T
IM
A T E D
M A X
IM
U M
C O
V E R
S T R U
C T U
R A L
E X C
A V A T
IO
N
R E M
O V A L
O F
PI
PE
C U
LV
E R T
-I
N C H
P
IP
E C
U
LV
E R T
C
LE
A N
IN
G
C U
LV
E R T I
N P
LA
C E
S K E W
A N
G
LE
A llo w ab le P ip e
M at er ia l (S ee k ey b el o w
B E V E
LS
V :n
H
B E V E
LS
V :n
H
REMARKS
See below for numbered notes
FEET CUYD EACH LNFT EACH Lt Rt 10+25 1 37+82 1 46+74 1 60+12 1 62+88 1 62+90 1 64+78 1 70+54 1 74+44 2 14 1 28.8 6 CMP Note 1 and 2 74+48 2 14 1 28.8 0 CMP Note 1 and 2 80+57 1 84+07 2 14 1 30 16 CMP Note 1 and 2 90+03 1 94+16 1 102+23 1 124+38 1 129+66 1 136+10 1 138+84 1 144+98 1 152+47 1 159+29 1 164+83 1 165+63 1 168+12 1 170+53 1 173+64 1 175+61 1 180+13 1 185+99 1 190+06 1 197+93 1 202+42 1 204+42 1 207+48 1
PROJECT TOTAL 42 3 88 32
Allowable Pipe Material
NOTE: CMP Corrugated Metal Pipe
1. Structural excavation quantity based on material excavated inside the vertical planes located 18 inches outside and parallel to the limits of footings or foundations.
2. See Section G for riprap placement at culverts.
PAY ITEM NUMBER
-M a y-
:5 A
M c:
\p w w o rk w fl \d
C u lv er ts
.x ls x] S h ee t
TABULATION OF DRAINAGE QUANTITIES
PROJECT
I.1ID FLAP BONNER 841(1)
SHEET
NUMBERNote: The quantities shown hereon are approximate and are subject to field adjustments.
PRELIM
IN
ARY
NOT FOR C
COVER
MINIMUM
DIAMETER
VALENT
EQUI-
RADIUS
CORNER
MINIMUM
COVER
MINIMUM
COVER
MINIMUM
COVER
MINIMUM
DIAMETER
VALENT
EQUI-
RADIUS
CORNER
MINIMUM
142 x 91
137 x 87
128 x 83
117 x 79
112 x 75
103 x 71
95 x 67
87 x 63
83 x 57
81 x 59
77…