Preliminary Bid Results~17.xlsx
XLSX spreadsheet 16 KB Posted
- Attached to
- Hwy 2 Over Herman Creek Conn Deck Resurfacing
- Solicitation number
- S-73000-00011491
- Issued by
- Hood River County, Oregon
About this file
This document is a bid tabulation sheet for the Hwy 2 Over Herman Creek Conn Deck Resurfacing project, an Invitation to Bid (ITB) issued by the Oregon Department of Transportation (ODOT) for the benefit of Hood River County.
The project involves replacing the failing waterproof membrane and asphalt on a bridge deck. The bid tabulation sheet lists 16 bid items with estimated quantities, unit prices, and total prices submitted by two bidders. Key bid items include mobilization, temporary traffic control, erosion control, bridge deck cold plane pavement removal, polymer membrane application, and asphalt paving. The bid closing date was September 20, 2024. This bid tabulation is not an indicator of award, but rather a summary of the bids received for consideration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment D - Standard Drawings~4.pdf | ||
| Attachment C - Bid Pricing Form~29.xlsx | XLSX spreadsheet | |
| 00 Marion Center Low Slope Roof RFP 9.2024.pdf | ||
| 00011491_Invitation to Bid~1.docx | DOCX document | |
| Attachment B - Special Provisions~16.pdf | ||
| Attachment A - Plans~38.pdf | ||
| 00011312_Addendum One.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 9/20/24 | |||
| ITB No. | S-73000-00011491 | BIDDER | ||
| NAME: | settje sons paving | Oregon State Bridge Construction | ||
| Bid Closing: | September 20, 2024 | CITY/STATE: | ||
| Description: | Hwy 2 Over Herman Creek Conn Deck Resurfacing | CCB#: | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1 | LS | $ 15,000.00 | $ 15,000.00 | $ 70,600.00 | $ 70,600.00 |
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | 1 | LS | $ 50,000.00 | $ 50,000.00 | $ 287,500.00 | $ 287,500.00 |
| 3 | EROSION CONTROL | 1 | LS | $ 1,000.00 | $ 1,000.00 | $ 20,000.00 | $ 20,000.00 |
| 4 | INLET PROTECTION, TYPE 3 | 2 | EACH | $ 1,000.00 | $ 2,000.00 | $ 500.00 | $ 1,000.00 |
| 5 | POLLUTION CONTROL PLAN | 1 | LS | $ 1,500.00 | $ 1,500.00 | $ 20,000.00 | $ 20,000.00 |
| 6 | CONSTRUCTION SURVEY WORK | 1 | LS | $ 5,600.00 | $ 5,600.00 | $ 12,000.00 | $ 12,000.00 |
| 7 | BRIDGE DECK COLD PLANE PAVEMENT REMOVAL, 1-2 INCHES DEEP | 1,013 | SQYD | $ 20.00 | $ 20,260.00 | $ 21.00 | $ 21,273.00 |
| 8 | BRIDGE APPROACH SLAB COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP | 331 | SQYD | $ 20.00 | $ 6,620.00 | $ 21.00 | $ 6,951.00 |
| 9 | CLASS 2 PREPARATION | 50 | SQYD | $ 350.00 | $ 17,500.00 | $ 300.00 | $ 15,000.00 |
| 10 | POLYMER MEMBRANE | 9,113 | SQFT | $ 10.00 | $ 91,130.00 | $ 6.00 | $ 54,678.00 |
| 11 | COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP | 3,000 | SQYD | $ 20.00 | $ 60,000.00 | $ 21.00 | $ 63,000.00 |
| 12 | LEVEL 4, 1/2 INCH LIME TREATED ACP | 410 | TON | $ 260.00 | $ 106,600.00 | $ 255.00 | $ 104,550.00 |
| 13 | PG 70-22 ASPHALT IN LEVEL 4, 1/2 INCH ACP | 25 | TON | $ 1.00 | $ 25.00 | $ 1.00 | $ 25.00 |
| 14 | CORE CORRELATION OF NUCLEAR GAUGE READINGS | 1 | EACH | $ 3,500.00 | $ 3,500.00 | $ 3,000.00 | $ 3,000.00 |
| 15 | MONO-DIRECTIONAL WHITE TYPE IAR MARKERS, RECESSED | 20 | EACH | $ 1,000.00 | $ 20,000.00 | $ 350.00 | $ 7,000.00 |
| 16 | METHYL METHACRYLATE, WET WEATHER, GROOVED, NON-PROFILED | 1,500 | FOOT | $ 19.50 | $ 29,250.00 | $ 13.25 | $ 19,875.00 |
| TOTAL | $ 429,985.00 | $ 706,452.00 |
File details come from the government source that posted it. Updated .