Pre-Bid+Tour.pdf

PDF 9 MB Posted

Attached to
2025 Lehigh Road Phase X and Scranton Phase IV Material Testing AML Project
Solicitation number
408.25.03.002
Issued by
Stark County, North Dakota

About this file

This is a Pre-Bid Virtual Tour Guide for the 2025 Lehigh Road Phase X and Scranton Phase IV AML (Abandoned Mine Land) Project issued by the North Dakota Public Service Commission. The project involves drilling and grouting activities across two site locations, with a performance period from May 19 to August 8, 2025. The bid opening is scheduled for Tuesday, April 8, 2025, at 10:00 A.M. Central Time, with a bid bond or cashier's check requirement of 5%. Potential contractors must complete a pre-construction workshop, provide utility locates, manage dust control, and follow specific work plans for drilling, grout pumping, and site access road installation. The project requires detailed documentation, including daily drill logs and grout injection forms.

The contract includes specific requirements for material testing, with a Material Testing Contractor responsible for aggregate gradations, concrete strength testing, structural surveys, and on-site documentation. Contractors must coordinate closely with the project manager and material testing team, providing timely notifications and maintaining precise records. Payment terms are structured with invoices submitted on the 1st and 15th of each month, with payments processed on the 10th and 25th. The project emphasizes careful ground movement monitoring, especially near roads, railroads, and structures, with work to be halted if any movement is detected. No additional compensation will be provided for increased expenses or unexpected field conditions, and all project quantities are considered estimates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-bid Virtual Tour Guide 2025 Lehigh Road Phase X and Scranton Phase IV AML Project

The Pre-bid, Virtual Tour replaces the mandatory pre-bid, onsite meeting that was required in the past for AML drilling and grouting projects. This document does not replace or take precedence over the Invitation for Bid (IFB) or any other project documents.

• The 2025 Lehigh Road Phase X and Scranton Phase IV AML Project IFB can be found by searching the State Procurement Office (SPO) website at:

https://apps.nd.gov/csd/spo/services/bidder/main.htm

Bidding Information (Section 1 of IFB)

1. Bid opening: Tuesday, April 8, 2025, at 10:00 A.M., Central Time (CT). Read the IFB completely, bidder’s instructions are included. Late bids will not be accepted.

2. Include a 5% bid bond or cashier’s check with bid package.

3. Deadline for questions is March 27, 2025, at 5:00 P.M., CT. Questions must be submitted in writing. Emailed questions are accepted at bjob@nd.gov

4. All attached forms must be completed with the bid.

2025 IFB Points to Highlight

1. Performance Period: May 19 to August 8, 2025. The contractor is expected to start soon after the start date. Weather delays must be documented by GROUT CONTRACTOR and reviewed by Commission’s Project Manager.

2. All Quantities are Estimated: No allowance will be made for any increased expense, loss of expected reimbursement, or loss of anticipated profits suffered or claimed by GROUT CONTRACTOR resulting from either field conditions or unbalanced bid prices or any other cause.

3. Pre-Construction Requirements:

a. Pre-construction workshop: GROUT CONTRACTOR shall plan and conduct an informational pre-construction workshop at the site at least 3 business days prior to beginning work.

b. Aggregate source(s) with NDDOT Material Source Certificate(s) of Approval and initial gradation.

c. Schedule of Construction: start and completion dates for mobilization, drilling, grouting; list of all equipment needed to complete the job; method of grout formulation and delivery; safety plans.

d. Utility Locates: The 2025 Lehigh Road Phase X and Scranton Phase IV AML Project sites will require both private and public utility locates. The locate https://apps.nd.gov/csd/spo/services/bidder/main.htm requests and renewals must be sent to the project manager as they become available.

Once these items are completed and approved, a Notice to Proceed (NTP) will be issued. If work cannot begin as specified on the NTP, GROUT CONTRACTOR shall provide a written explanation of the delay and request an alternate firm start date. The Performance Period will remain unchanged.

4. Fugitive Dust Control

5. Payments - Invoices may be submitted no later than the 1st and 15th of each month for payment on the 10th & 25th of the month. Payments are only made on the 10 and 25th. Submit signed invoices to the Commission’s Project Manager.

6. Traffic Control

7. Clean-Up Provisions

Work Plans: Drilling and Grout Pumping

1. The Commission’s Project Manager will determine the drilling and grout pumping sequences. Please see the preliminary drilling paths and existing cased holes to be pumped on the project maps (pages 4-5). Drilling must be available during grout pumping. Scranton Phase IV will be completed before Lehigh Phase X can commence.

2. Excess grout must be cleaned up daily and hauled off-site as soon as possible.

Once a hole is filled the casing must be removed immediately.

3. All casing used as a conduit for grout must be removed immediately upon refusal or completion of pumping that hole. PVC casing must be removed as soon as possible on holes filled by adjacent pumping, but not more than 24 hours after the hole is completed.

The North Dakota Public Service Commission will be performing a before and after certified railroad inspection of the track adjacent to drilling and grouting construction in Scranton. The Grout Contractor must use a laser level and provide skilled personnel to monitor ground movement continuously during pumping operations near all paved roads, railroads, and within 250 feet of structures. Work must be halted if movement is detected.

Work Plans: Scranton Site Access Road Installation

1. Access road installation must be completed prior to drilling operations. Please see Figures 11-16 to see current surface conditions and topography.

2. The road will be approximately 160 feet long, 10 feet wide, and contain 12 inches of Class 5 gravel. The road must be installed in two 6” lifts with the specified geotextile fabric underneath.

3. The contractor will maintain this road until project is completed.

Documentation

1. The GROUT CONTRACTOR is expected to complete a drill log form for every hole and to submit drill log forms to the Commission’s Project Manager daily. The required form is in Section 7 Attachments of the IFB.

2. Provide grout injection forms to Commission’s Project Manager daily. The required form is in Section 7 Attachments of the IFB.

Contractor Cooperation

1. It is the GROUT CONTRACTOR’S responsibility to ensure the Material Testing Contractor is given timely notification regarding pumping activities. The GROUT CONTRACTOR must give the Material Tester a fixed firm start date for grout pumping at least 3 workdays prior to pumping. The Material Tester will be required to be available on that date and for any pumping activities until the end of the project during the standard work week. During grouting, the GROUT CONTRACTOR must notify the material tester of any stoppages in pumping as specified in the IFB.

2. Bills of lading for all aggregate, fly ash, and cement shall be given to the Material Testing Contractor.

Material Testing Contractor

1. Material Testing Contractor will be responsible for performing six fine aggregate gradations and 110 series of concrete strength testing. Each series will contain three individual specimen breaks.

2. Material Testing Contractor will be responsible for providing sufficient storage for grout samples. This initial curing of concrete must comply with ASTM C31 for standard curing and transportation.

3. Materials Testing Contractor representative will be required to be on-site at all times during grouting operations. They will be required to collect all concrete tickets and record ready-mix truck arrival and departure times. These tickets will be given to the Commission’s Project Manager or designated person daily.

4. Material Testing Contractor will be responsible for performing six (6) structural surveys (Pre-construction and Post-construction). These surveys will take place on three (3) separate buildings in Scranton.

2025 Lehigh Road Phase X and Scranton Phase IV AML Project information and photographs are included in this document for CONTRACTOR reference.

Lehigh Road Phase X Project Map (Dickinson)

Scranton Phase IV Project Map (Scranton)

Figure 1 – Lehigh Road, Stark County Right of Way

Figure 2 – Lehigh Road, Stark County Right of Way

Figure 3 – Lehigh Drive, Stark County Right of Way

Figure 4 – 38th St SW, Stark County Right of Way

Figure 5 – 38th St SW, Stark County Right of Way

Figure 6 – Lehigh Road, Stark County Right of Way

Figure 7 – Lehigh Road, Stark County Right of Way

Figure 8 – Lehigh Road, Stark County Right of Way

Figure 9 – Landfill Access Road, Scranton Equity Exchange

Figure 10 – HWY 67, Bowman County ROW

Figure 11 – Private Rail Spur, Access Road Location

Figure 12 – Private Rail Spur, Access Road Location

Figure 13 – Private Rail Spur, Access Road Location

Figure 14 – Private Rail Spur, Access Road Location

Figure 15 – Private Rail Spur, Access Road Location

Figure 16 – Private Rail Spur, Access Road Location

Figure 17 – HWY 67, Bowman County ROW

Figure 18 – Landfill Access Road, Scranton Equity Exchange

Figure 19 – Landfill Access Road, Scranton Equity Exchange

Figure 20 – Farmstead Access Road

Figure 21 – Farmstead Outbuilding

Figure 22 – Farmstead Driveway and Buildings

Figure 23 – Farmstead Outbuilding and Driveway

Figure 24 – 133rd Ave SW, Bowman County Right of Way

Figure 25 – 133rd Ave SW, Bowman County Right of Way