Pre-bid RFIs 573-22-103.xlsx
XLSX spreadsheet 28 KB Posted
- Solicitation number
- Not on record
About this file
This file is a Pre-Bid Request for Information (RFI) responses document for Project 573-22-103, the renovation of Interventional Radiology Suites at the Malcolm Randall VA Medical Center in Gainesville, Florida. The document addresses 132 pre-bid questions and government responses covering design clarifications, equipment responsibilities, construction coordination, and regulatory compliance. Key technical clarifications include: structural deck composition to be field-verified; as-built drawings and CAD files to be provided via addendum; equipment manufacturers specified (Siemens DDC controls, Lenel access control, Rauland nurse call, BeaconMedaes medical gas, Simplex fire alarm); commissioning provided by VA with contractor coordination; finishes per AF-100 Finish Legend without separate schedule; and lead shielding thickness of 1/16" for radiation protection. Owner-furnished items include Philips interventional radiology systems, Stryker equipment booms, and Pyxis medication dispensers; contractors must provide room preparation, utilities, and anchorage per vendor requirements and coordinate installation milestones.
Construction execution requirements mandate a dedicated full-time Contractor Quality Control Manager and Safety and Health Officer (meeting OSHA 30 certification and 3-year experience standards); development of a CPM schedule with defined phasing to meet the 2-month Surgical Pathology milestone; Infection Control and Risk Assessment (ICRA) certification and Interim Life Safety Measures (ILSM) compliance prior to mobilization; terminal cleaning by contractor; work in areas affecting hospital operations scheduled after 5:00 p.m. or weekends with 7-day advance notice (15 days for major interruptions); and afterhours coordination for demolition adjacent to operating rooms and imaging spaces. Contractor responsibilities include site logistics planning (staging areas, dumpsters, parking), utility shutdown coordination, temporary HVAC if needed for hospital operations, roofing protection compliance, and negative air/HEPA filtration per 01 35 26 safety requirements. The current wage determination FL20260194 (dated 01/02/2026) applies; all mandatory FAR certifications and clauses must be submitted with proposals; and the drawing set is dated 04/24/2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Reports.zip | ZIP file | |
| RFI Documents.zip | ZIP file | |
| Wage Determination FL20250194 dated 01-02-2026.pdf | ||
| VA 573-22-103 Gainesville - Interventional Radiology - Addendum 01.pdf | ||
| Updated Parking Policy.pdf | ||
| 36C24826R0038 0002 Responses to RFI_s.pdf | ||
| Cutsheets.zip | ZIP file | |
| Elevator Modernization.zip | ZIP file | |
| Basis of Design.zip | ZIP file | |
| 573-22-103 Renovate Interventional Radiology Suites Site Visit Presentation.pptx | PPTX presentation | |
| Stryker CAD.zip | ZIP file | |
| Philips CAD.zip | ZIP file | |
| Mechanical Calculations 100 percent.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| BB - Renovate Interventional Radiology Suites | ||
| PROJ: 573-22-103 | ||
| Questions | Government Response | |
| 1 | Please advise on the existing structure deck composition and thickness as shown on Sheet A-120 (Plan Note 2.02). | Field Verify |
| 2 | Please advise on the existing slab composition and thickness for the 1st level. | Field Verify |
| 3 | Please provide a complete set of as-builts for all work areas including Structural and MEPFP drawings. | |
| COR to provide via addendum | ||
| 4 | Please provide CAD drawings for the Architectural drawings, Philips drawings and Stryker drawings. The Steris rep. is requesting them for coordination purposes with their Clean Suite systems. | COR to provide via addendum |
| 5 | Please advise who is responsible for terminal cleaning. | Contractor is responsible for terminal cleaning |
| 6 | Please advise if the Project Superintendent can serve as a "dual hat" as the Contractor Quality Control Manager (CQCM) on this project | No. Separate CQC Manager required; submit staffing plan and CQC Plan per Div 01. |
| 7 | Please advise if the Project Superintendent can serve as a "dual hat" as the Site Safety and Health Officer (SSHO) on this project | No. SSHO must meet training/experience criteria in 01 35 26 (e.g., OSHA‑30, ≥3 yrs). Provide dedicated SSHO. 1 |
| 8 | Please advise on the following manufacturers for the building - DDC Controls, Security & Access Control, Nurse Call, Medical Gas, Public Address System and Fire Alarm System. | DDC - Siemens |
Access Control - Lenel Nurse Call - Rauland Responder Med Gas - BeaconMedaes Public Address - N/A Fire Alarm: Simplex
| 9 | Please advise if the existing roofing system is under warranty where we have to demolish it on the 2nd Level. And if so, please advise who the subcontractor and/or manufacturer is that installed the existing roofing system. | Facility to confirm warranty status and vendor. Contractor to protect existing roofing and comply with 07 01 50.19 / 07 54 23; if warranty exists, coordinate with warranty holder to maintain coverage. |
| 10 | Please confirm that the commissioning will be provided by the VA |
See Addendum 01 for added 01 91 00 - General Commissiong Req. Spec.
11 Please provide section 01 91 00 General Commissioning Requirements since it has been omitted in the Bid Specifications.
See Addendum 01 for added 01 91 00 - General Commissiong Req. Spec.
| 12 | Please confirm that all color selections are per the Finish Legend on Sheet AF-100 and that a Schedule of Finishes section will not be provided in the Bid Specifications. | AF‑100 provides the finish legend (paint codes, flooring systems, bases, rigid wall protection system, etc.), and finishes are directed to be installed per AF‑101‑F plans. No separate “Schedule of Finishes” is required. |
| 13 | Please confirm there are enough licenses available for the Access Control additions. | Facility to confirm with Security/IT; contractor to include licensing to integrate new doors with existing access control system per 28 13 00 and telecom drawings. |
| 14 | Please confirm there are enough licenses available for the CCTV additions. | See #13 provide additional licenses as needed per 28 23 00. |
| 15 | Please confirm there is enough space on the existing nurse call server for new design. | Coordinate with facility; provide capacity upgrades if needed per 27 52 23; telecom drawings govern device counts. |
| 16 | Please confirm if the Contractor or the VA is providing the Pyxis ES Machine (see note #11.19) since it is not clear who is providing it. | |
| VA‑furnished Pyxis units; contractor to provide power/data/anchorage per A/E drawings and vendor requirements. | ||
| 17 | Please provide the Basis of Design for the Toilet and Bath accessories. No information provided on the plans or specifications. | |
| Accessories and mounting are shown throughout A401/A402 interior elevations and Toilet Accessories Schedule with JSN references (e.g., grab bars JSN B‑6806). Master spec 10 28 00 Toilet Accessories is included; use that section and the JSN schedule for product basis/quality. | ||
| 18 | Please provide Basis of Design for the X1100 Cabinet Bin as detailed on the Equipment Schedule since it is indicated as a "CC" item. Also, please confirm that the Contractor is to provide. | Cabinet changed on schedule to be owner provided owner installed per Addendum 01. |
| 19 | Please provide Basis of Design for the X3150 Apron Glove Rack we are to furnish and install. | |
| Equipment Schedule on A100 lists X3150 Rack, Apron‑Gloves, Wall‑Mounted tagged CC (Contractor-provided/installed). Basis not manufacturer‑specific. | ||
| 20 | Please advise if spray-on fireproofing will be required on the structural steel and decking and if so please provide the necessary hour fire rating, thickness and specifications. | |
| RDC/JPA: |
Spray-on fireproofing in not required in the roof enclosure or on the supports for the new equipment in the IR.
| 21 | Please provide the the New Door hardware specifications as noted on Plan Note 2.15 for the existing door that is to remain. No information was provided. | Use 08 71 00 Door Hardware for sets, quality, electrified requirements, etc. The specific set for each door is coordinated on A601 Door Schedule. |
| 22 | Please provide existing finishes that we are to match for the wall and base as stated in Plan Note 9.70. | Contractor to field‑verify adjacent finishes and provide match; submit samples per 01 33 23; repaint/replace base to match per 9.70 notes. |
| 23 | Please provide existing Brick veneer finish (color and specifications) since we are to match the existing as stated in Plan Note 4.01. | Field‑verify brick color/texture; submit manufacturer data and sample panels per 04 20 00 / 07 60 00 for A/E approval. 1 |
| 24 | Please provide existing wall thickness, rating and specifications as stated in Plan Notes 9.71 and 9.74 | For infill at existing openings: match thickness of adjacent wall and maintain rating (use UL U465/U419 assemblies); submit shop drawings identifying wall makeup and continuity of barrier. |
| 25 | Please confirm window mark "C" on the window schedule relates to window elevation Type E7 and Detail #1 on Sheet A-601. Window type "C" is located in Office D337B-1 and shown on the First Floor Floor Plan (A-101). | Yes. Window Schedule on A601 lists mark C as sliding, lockable reception window with laminated glass (H7/J7 frame types). |
| 26 | Please provide specifications, model # and finish for the CG-1, EG-1 and the RWP-1 Wall protection we are to match to existing finishes. | AF‑100 Finish Legend provides basis manufacturers. |
CG‑1 Corner Guard: CS Acrovyn (to match wall paint) EG-1 End Guard: CS Acrovyn (to match wall paint) RWP‑1 Rigid Wall Protection: Inpro (to match wall paint), 52" A.F.F. (and full-height where shown)Finish/color selection per AF‑100 paint schedule.
| 27 | Please provide Glazing specifications for the Control room windows Type A and B. | A601 indicates lead‑lined control windows (A/B types) and laminated safety glazing requirements; coordinate radiation shielding with 13 49 00 Radiation Protection and 08 80 00 Glazing for performance. |
| 28 | Please provide Glazing specfications for the Vision Glass panel on Door Type N. No information was provided. | Provide tempered/laminated safety glazing per 08 80 00; size/type per A601 door schedule and details. |
| 29 | On Sheet A-100, Item #A5180 on the Equipment Schedule states the Contractor is to furnish and install a Track with a curtain. On Sheet AF-100, the Finish Legend states that the PC-1 Privacy Curtain is to be furnished and installed by the VA. Please clarify if the Contractor or the VA is responsible for the privacy curtain. | A5180 Track + accessories = Contractor furnishes and installs (tagged CC on A100). |
PC‑1 Privacy Curtain = VA provided & installed (AF‑100).
| 30 | Please confirm this project will be constructed in one phase. | Drawings include notes calling out critical phasing for Surgical Pathology (“must be completed within a 2‑month period”), and Div 01 requires a CPM schedule with phasing and shutdown coordination. Construction documents do not confirm single‑phase; contractor must propose phasing per 01 32 16.15, subject to VA approval. |
| 31 | Please provide the Model #'s and finish types for the ST-1 Stainless Steel Cabinets. | AF‑100 lists ST‑1 Manufactured Metal Casework basis as OnePoint Solutions (stainless steel base/upper cabinets & counters). Finish is stainless; features (sloped top, kick plate) detailed on A511 casework sections. Submit shop drawings for approval |
| 32 | Per detail #3d on Sheet A-301, please provide the BOD manufacturer, panel pattern, corrugated depth, panel thickness and finish for aluminum wall panels as noted on Plan Note 5.29. |
See Addendum 01 for added 07 40 00 - Roofing & Siding Panels Spec.
33 Please provide an asbestos location plan that aligns with the ACM report findings including the quantities that need to be removed. Quantities are not stated in the ACM report and/or Bid Documents.
ACM report will be included in the spec. It shows quantities. No plan has been produced by the testing lab.
34 Please provide Specifications for the High Performance Coatings noted on the index but not included in the specifications.
The spec was included (between Painting and Signage). The PDF of that spec was formatted slightly different.
| 35 | Per Sheet GN - General Notes (Note 6) of the Phillips equipment drawings, please clarify who is to hire the licensed radiation physicist for the radiation protection testing. | Contractor to retain qualified medical physicist to confirm shielding calcs and perform tests, per 13 49 00; coordinate with OEM installation requirements. |
| 36 | Please confirm if the ICU Doors (D363H and D363J) are to manual or automatic doors. | A601 door schedule: “Prefabricated ICU door with manual swing and two‑part bi‑fold door. |
| 37 | Please specify the lead thickness on the lead lined drywall as indicated on Sheet A-001 per Plan Note 9.23 (Wall types S4.0, S5.0, S6.0 and S7.0) |
A shielding calculations report dated 1/19/2024 demonstrated that 1/16" lead shielding would suffice. Wall types which included lead, have the 1/16" lead built into them.
| 38 | Per Plan Note #5 on Sheet MH-101, please advise who is to provide the Biosafety cabinet (Contractor or VA). | See Adendum 01 for added 11 53 53 Biological Safety Cabinets Spec. Contractor to provide biosafety cabinet L2310 Class II/A2 per A‑100 equipment schedule with 4ft 8" sash opening; provide utilities and anchorage per drawings. Basis of design provided as separate document with RFI responses. |
| 39 | Please provide the proper tieback cabling system for the 10' clear span section of the exhaust duct with anchorage details. |
AHU Exhaust section up exterior wall to 10 ft above top roof is to be braced per details on S203. Additional guy wires are not intended to be required.
40 Per Elevation 6 on Sheet A-120, please clarify the size and specification of the prefinished metal gutter and downspouts including BOD manufacturer, materials, thickness and size.
Gutter size: 5"W x 4"D Downspout size: 4W" x 3D" 41 Please provide the material type, R value and thickness for the "Acoustic Insulation" per Plan Note 9.80 on Sheet A-001. The insulation occurs in several different wall types.
Insulation is based on thickness of stud. R value is irrelevant on interior walls.
| 42 | Will the contractors have to work in a negative air controlled booth during any phases of construction? | Yes, section 01 35 26 Safety Requirements includes VA PCRA/ICRA processes, negative air, HEPA filtration, barrier requirements, and coordination with the Facility Safety Officer. |
| 43 | Will demolition of lighting and device circuits that share circuitry with areas outside of scope need to be scheduled outside of normal working hours? | Yes, after‑hours or weekends; coordinate outage windows per 01 00 00 and VA Facility Fire/Life Safety procedures. |
| 44 | What are normal working hours for the areas that the project will impact so that we may determine when work outside of normal hours would be scheduled in these areas? | Work affecting hospital operations must occur after 5 p.m. or weekends with timely coordination through VA PM/COR. |
| 45 | Will the project be scheduled in multiple phases? | See #30 |
| 46 | Will building information modeling (BIM) be required on this project? | No however contractor may use BIM for coordination. Maintain as‑builts per 01 33 23/01 00 00 |
| 47 | Will electrical equipment and lighting need to meet BAA standards? | Yes |
| 48 | Can the overcurrent protection device coordination study be performed by a third party? |
Per specification 26 05 73, Study should be performed by Equipment Manufacturer's licensed electrical engineer.
| 49 | Is there a preferred manufacturer for electrical equipment? Specs do not specify. | VA Facility prefers Square D components for electrical installations. See specification section 26 for requirements. |
| 50 | Where will contractors be allowed to park during the construction project. Will contractors be allowed to park along the loading dock? | Contractor is allowed to park on site in marked construction contractor parking granted they have a parking permit supplied by VA Police. There are no fees for parking permit. Current restrictions dictate two numbered parking passes per General Contractor. Off site parking is available at University Inn (1901 SW 13th St, Gainesville, FL 32608) or Aldi (300 SW 16th Ave, Gainesville, FL 32601). Transportation from off-site parking not provided. Facility parking policy provided with RFI responses as separate document. |
| 51 | Where will the contractors lay-down area be set at? Will we be allowed to set dumpsters along the backside of the hospital along the loading dock area? | Submit site logistics plan for temporary facilities, storage, dumpsters per 01 00 00; locations are case‑by‑case with COR approval. Contractor responsible for ensuring security for laydown materials. |
| 52 | The hallways seem very congested with people. The demolition portion of this job will require a lot of trips in and out of the building. Will this work need to take place after normal working hours? | Movement of demolition materials throughout facility can be performed during normal business hours as long as the contractor completely covers the material allowing no debris to escape. ICRA, Patient Safety, Interim Life Safety requirements still apply. Demolition immediately adjacent to Operating Room spaces (including front desk area) or other critical areas to patient or staff operations must be coordianted with COR to be performed after hours. |
| 53 | Are we able to work outside of normal working hours? If so, are there any restrictions on those hours? | See previous responses under #43, 44, 52 |
| 54 | Part of this project will affect the anesthesia and OR areas. Are there any time restrictions or requirements when working in these areas? | See previous responses under #43, 44, 52 Coordinate shutdowns and access with COR; after‑hours windows and ILSM will likely be required per 01 00 00. |
| 55 | Phasing looks to be key with this project. Is there any certain phasing requirements or is this left up to the contractors in how we approach the project? The solicitation references phasing requirements but drawings and specs appear not to address it. | Contractor to develop phasing plan consistent with clinical operations and 2‑month Surgical Pathology milestone; submit CPM schedule and obtain approval. |
| 56 | What are the hospitals notification and approval requirements for a crane lift or helicopter lift to set the chiller on the roof? | Submit lift plan with advance notice of at least one month; coordinate security, traffic, and safety per 01 35 26 and Use of Roadways in 01 00 00; obtain VA approvals |
| 57 | Please confirm that Siemens controls is the proprietary controls for the hospital. | Yes |
| 58 | Is it acceptable to bring the AHU through the hospital in sections to get it to the courtyard? If so then can this activity occur during normal working hours or does it have to be performed after hours? |
Basis of Design is for AHU is to be complete knockdown construction per AHU schedule note #17 and contractor has option to propose other methods.
| 59 | Can a crane be set up in the loading dock area to set materials and supplies on the roof? | Submit lift plan with advance notice of at least one month; coordinate security, traffic, and safety per 01 35 26 and Use of Roadways in 01 00 00; obtain VA approvals |
| 60 | Are there any specific requirements for using scaffolding in the courtyard area where the new mechanical room and AHU will be installed? | Submit scaffolding plan per 01 35 26; maintain egress and ILSM. |
| 61 | Please confirm whether the Government will provide a dedicated on-site area for material laydown and staging. If so, please identify the location(s), size limitations, access routes, and any restrictions on duration of use. | See #51. On‑site storage and dumpster locations granted case‑by‑case; coordinate locations with COR and submit logistics plan for approval. Maintain continuous secured perimeter around storage/dumpster/trailer |
| 62 | Please confirm whether on-site parking will be provided for contractor personnel, including subcontractors. If parking permits are required, please clarify the quantity available, designated parking areas, and any associated fees or approval process. | See #50 |
| 63 | Please confirm approved delivery times, loading/unloading locations, and designated haul routes within the campus, considering the facility remains operational 24/7. | Delivery times depending on method of shipment. For contractor delivered items, use back loading dock at south east end of facility next to CLC. No delivery time restrictions unless movement of material will impede patient/staff operations. If so, coordinate for after hours delivery. For third party delived items that must be received by VA warehouse, use front loading dock at south west end of facility. Items delivered by third party requiring VA receipt of package must be delivered during loading dock hours 0800-1430. Both loading docks are on basement level with acess to service elevator. Coordinate with COR for all large deliveries and equipment movements through facility. |
| 64 | Will temporary contractor facilities (trailers, storage containers, dumpsters) be permitted on campus? If yes, please identify approved locations and utility availability. | See #51. On‑site storage and dumpster locations granted case‑by‑case; coordinate locations with COR and submit logistics plan for approval. Maintain continuous secured perimeter around storage/dumpster/trailer |
| 65 | Please confirm whether the project will require formal construction phasing beyond what is shown in the contract documents. If phasing is required, will the Government provide an approved phasing plan, or is the contractor responsible for developing and submitting one for review? | See previous RFIs regarding phasing. Contractor to develop and submit phasing plan per 01 32 16.15; VA will review/approve to maintain operations. |
| 66 | Please clarify whether work areas will be turned over all at once or in phases, and identify any anticipated milestones tied to clinical operations or equipment installation. | Turnovers will align with CPM phasing and clinical milestones (e.g., Surgical Pathology 2 month window, Philips install windows); include milestone dates in schedule; VA/COR will coordinate vendor access with contractor. |
| 67 | Are after-hours or weekend work windows permitted or required to support uninterrupted medical operations? If so, please clarify approval procedures and any premium time restrictions. | Yes. Submit requests ≥7 days in advance; major interruptions ≥15 days per 01 00 00. |
| 68 | Please confirm required lead times and allowable windows for utility shutdowns (electrical, medical gas, HVAC, fire alarm, fire protection), and whether shutdowns must occur after normal business hours. | 7‑day minimum notice; 15‑day for major interruptions; outages typically after‑hours; coordinate through COR per 01 00 00. |
| 69 | Have all existing above-ceiling utilities, structural elements, and medical systems been fully verified, or should the contractor anticipate concealed conditions and include allowance for investigative demolition? | Contractor shall anticipate concealed conditions and include investigative demolition and field verification per 01 00 00. |
| 70 | Please confirm approved roof access routes, staging limitations, and protection requirements for existing roofing during installation of the new rooftop mechanical enclosure. | Submit roof access plan; protect roofing; comply with 07 54 23 and 01 00 00 restoration; staging not to impede with hospital operations or ILSM |
| 71 | Please confirm the Infection Control Risk Assessment (ICRA) and Interim Life Safety Measures (ILSM) requirements applicable to this project and whether templates or hospital-specific procedures will be provided. | Prior to mobilization, Infection Control Construction Permit and Interim Life Safety Measures certification are required; implement PCRA/ICRA per VA procedures. |
| 72 | Please clarify the anticipated processing time for badging and background checks for contractor and subcontractor personnel. | All vendor/contract personnel must report to Police Service and comply with PIV requirements; carry ID at all times. |
| 73 | Are there specific noise, vibration, or imaging-sensitive work restrictions associated with adjacent clinical spaces that may impact means and methods? | Yes, limit noise/vibration or schedule after‑hours; coordinate with adjacent imaging/OR; comply with 01 00 00 |
| 74 | Please confirm which imaging equipment, booms, shielding, or specialty systems are Owner-Furnished/Owner-Installed (OFOI) versus contractor-installed, and identify required coordination milestones. | Philips IR systems = OFOI (VA purchase/install), contractor provides room prep per vendor drawings; Stryker booms = OFOI, contractor provides room prep per per drawings; include vendor coordination milestones in CPM schedule. |
| 75 | Will the Government coordinate directly with OEM vendors (e.g., imaging equipment suppliers), or is the contractor responsible for scheduling, access, and rough-in coordination? | Contractor to coordinate rough‑ins, access, and schedule with OEMs; VA/AE will attend vendor coordination meetings. |
| 76 | Please confirm the extent of contractor responsibility for commissioning, testing, and documentation for HVAC, electrical, fire protection, and medical gas systems. | See #10 |
| 77 | Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO? | See #7 |
| 78 | If no to the question above, will the SSHO need to be full-time for this project? | Yes, full‑time SSHO on site whenever work is occurring. |
| 79 | Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC? | See #6 |
| 80 | If no to the question above, will the QA/QC need to be full time for this project? | Yes, full‑time CQC during active work phases. |
| 81 | Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC? | No, must be separate roles |
| 82 | Please confirm the issued drawing set, dated 04/24/2025, is the latest and complete set. | Yes |
| 83 | Please confirm the current construction documents meet current VA TIL guidelines | Yes, however project construction documents do not exempt Contractor from meeting VA TIL requirements. If there is a discrepancy between project construction documents the VA TIL, inform COR immediately. |
| 84 | Please confirm the wage determination, dated 09/05/2025, is the current wage determination to be used by contractors in this pursuit. | The current Wage Determination FL20260194 dated 01/02/2026 is to be used by contractors in pursuit. The latest Wage Determinations can be found on www.SAM.gov. |
| 85 | Is the use of temporary plastic wall panels (such as Edgeguard panels) acceptable? | 01 35 26 requires fire‑rated barriers, PCRA/ICRA controls, negative air, and HEPA filtration. If panel systems meet fire rating and infection control requirements, they are acceptable |
| 86 | Who is responsible for the terminal clean of the project area? | Contractor |
| 87 | Who is responsible for contracting the commissioning agent? | Contractor, see #10 |
| 88 | Please confirm order of precedence for the contract documents. Does SOW prevail over the specifications and construction drawings? | Follow FAR/VA standard: Contract, Addenda, Specs, Drawings; if conflict, seek CO/COR or AE clarification. |
| 89 | The hardware sets in 08 71 00-18 of the specifications and the door schedule on A601 of the drawing package indicate four (4) access control doors with electrified hardware. However, the telecom drawings on TN101 indicate twelve (12) access control doors. Please clarify which is the correct count? |
The only doors with card readers are C264-1, D366A, D366B and D366C.
90 Please clarify if the eight additional doors are to receive readers and what locking hardware is specified for each door. The additional doors are D364, D364A, D364B, D364C, D365, D365A, D365B, and D337A.
The lock housing and cores are provided at the end of spec 08 71 00 where the hardware sets are listed.
| 91 | Will the elevator modernization project overlap in duration with this project? | It is possible that the elevator contract will reach the area first. Latest schedule shows July 2, 2026 start date and September 18, 2026 end date. Elevator Modernization drawings will be provided with RFI package as separate document to deconflict scope. Elevator project number: 573-23-109 |
| 92 | Are the service elevators expected to be out of service (as part of the elevator modernization project on campus) for any portion of this project’s duration? | Latest schedule for elevator project shows service elevator demolition starting April 14, 2026 and completion of modernization on July 1, 2026. During this time, the Bed Tower Service Elevators will be available. These serve the same floors as the Building 1 Service Elevators and are located down the hall just north of the Building 1 Service Elevators. |
| 93 | There are (2) windows in the courtyard where the new mechanical room will go. Are those to be bricked in or covered? | Brick veneer to match existing. |
| 94 | There is a drain existing in the courtyard under/near the footprint for the mechanical room. Will this remain existing or will it require relocation? |
Existing drain is to be demolished and new roof drain is provided. See PD121 for demo and PS121 for new roof drains.
| 95 | Will Phillips perform their own inspection of the electrical system prior to the install of their equipment? | Yes, vendor typically inspects rough‑in power/data/grounding prior to equipment install; contractor to schedule and correct deficiencies. |
| 96 | Please clarify whether a factory witness test is required for the new air handler? |
Contractor needs to follow 23 73 00 for factory testing requirements.
| 97 | Please confirm the prime contractor will be given the entire project area upon NTP. | Contractor will be given entire project area upon NTP, however VA staff must be allowed access to project area for inspections, maintenance, or emergencies. Hospital remains fully operational; maintain fire exits and utilities; coordinate turnovers and ILSM per SOW. |
| 98 | Please confirm the project will be completed in one phase. | See RFI #30 |
| 99 | Sheet AD100, note 2.04, references removal of an existing elevator shaft. Please clarify whether the elevator equipment (car, cables, hydraulic cylinder, etc) has been removed previously. | Existing equipment has not been removed previously |
| 100 | Please provide a detail for the infill of the elevator shaft referenced on sheet AD100, note 2.04. |
See Addendum 01 updated structural drawings by Pennoni.
| 101 | Please confirm the new Pyxis ES machine (referenced on sheet A100, note 11.19) and the new Pyxis double tower (referenced on sheet A100, note 11.20) are to be provided by the VA. | Yes, Pyxis units to be provided by VA |
| 102 | On sheet MH101 coded note 3 references a Steris HVAC ceiling system. On sheet M801 the air distribution schedule references a Price system. Please confirm the correct system that will be used. |
Steris Cleansuite is basis of design, however, any proposed system must meet performance requirements and specifications listed in 23 37 00, including Price Ultrasuite.
| 103 | Please confirm if the fire sprinkler system in the mechanical AH room be a wet or dry system. | Wet‑pipe per NFPA 13 is typical unless subject to freezing; drawings indicate enclosure within courtyard—assume wet unless A/E notes otherwise. |
| 104 | Please confirm if temporary fire sprinklers will be required or if the use of heat detectors will be acceptable. | During construction impairments, ILSM applies; typically heat detectors are required when sprinkler system disabled; Follow section 01 35 26 for full requirements and coordinate with VA Safety. |
| 105 | Are shutoffs expected to only be available during after hours? | Shutdowns affecting hospital spaces adjacent to or outside the project area are required to be performed after hours. |
| 106 | Please clarify the Basis of Design and specifications for the headwall shown on Sheet A401/ Note 10.07. |
There are two headwalls (1 in each Patient Recovery Bay). See detail 14 on sheet A401 note 10.07. The BOD has been included in spec 10 25 13 section 2.1 part G.
| 107 | FAR 52.209‑7 – Information Regarding Responsibility Matters (OCT 2018) | Yes the Clause needs to be completed and submitted. |
| Although this clause is contained within the solicitation, it is not specifically requested as part of the proposal submission. Does this clause need to be completed and submitted, and if so, do you want it included in the Price response or the Technical response? | It is a mandatory element of the overall offer and therefor must be completed as part of the total proposal. The FAR does not differentiate between technical or price proposal. In this case, we prefer it be included with the price proposal but will also be accepted as part of the technical proposal. | |
| 108 | FAR 52.209‑13 – Violation of Arms Control Treaties or Agreements—Certification (NOV 2021). This certification is included within the solicitation but not expressly required for submission. Does this clause need to be completed and submitted, and if so, do you want it included in the Price response or the Technical response? | Yes the Clause needs to be completed and submitted. Please see instructions in the previous Question 107. |
| 109 | FAR 52.219‑28 – Post‑Award Small Business Program Rerepresentation (JAN 2025) | Yes the Clause needs to be completed and submitted. Please see instructions in the previous Question 107. |
| 110 | Although included in the solicitation, this clause is not identified as a required submission. Does this clause need to be completed and submitted, and if so, do you want it included in the Price response or the Technical response? | Yes the Clause needs to be completed and submitted. Please see instructions in the previous Question 107. |
| 111 | 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (NOV 2023) ALTERNATE I (NOV 2023) This clause is included but not specifically noted as requiring completion. Does this clause need to be completed and submitted, and if so, do you want it included in the Price response or the Technical response? | Yes the Clause needs to be completed and submitted. Please see instructions in the previous Question 107. |
| 112 | Use of CPARS in Place of Questionnaire. May a CPARS report be submitted in lieu of a completed Past Performance Questionnaire/Survey to satisfy the requirements for Factor 1: Relevant and Recent Past Performance? | Yes. |
| 113 | Use of Previously Completed Past Performance Questionnaires. To avoid placing additional workload on VA personnel, may previously completed Past Performance Questionnaires be submitted instead of requesting new responses from project references? | Yes. |
| 114 | What is the badging and background check lead time? | See RFI 72; plan several business days; coordinate early with Police Service per 01 00 00. |
| 115 | What are the allowed work hours, noise restrictions, and weekend/after-hours requirements? | See RFI 44/53; after‑hours work and restrictions per 01 00 00 with PCRA/ICRA compliance. |
| 116 | Are material staging areas available on site? | See RFI 61; submit logistics plan; approval by COR per 01 00 00. |
| 117 | What are restrictions on elevators, corridors, or patient pathways? | Maintain clear egress and operations; minimize corridor use; coordinate with COR and plan off‑peak move of very large equipment; comply with 01 00 00. |
| 118 | Are there unknown utilities above ceilings or in walls to anticipate? |
Note extent of utility demolition required by construction documents and space this will leave for new work.
| 119 | What is the expectation for patching/refinishing to match existing adjacent surfaces? | Restore finishes to match adjacent undisturbed per 01 00 00 Restoration. |
| 120 | Who coordinates temporary shutdowns for utilities serving adjacent spaces? | Contractor submits requests to COR who coordinates with facility; |
| 121 | Are slab reinforcements or load testing required for imaging equipment, booms, or lifts? |
Slab reinforcing, load testing, and structural inspection is not required for the new equipment installation.
122 Are structural inspections required prior to equipment installation?
Slab reinforcing, load testing, and structural inspection is not required for the new equipment installation.
| 123 | Who coordinates delivery, staging, storage, and protection of Philips / Stryker equipment. | Philips and Stryker to coordinate delivery, staging and storage of vendor equipment. |
| 124 | Will vendors provide on-site supervision for installation of Philips and Stryker equipment. | Yes, OEMs provide supervision during install; contractor schedules and supports access. |
| 125 | Is existing HVAC capacity adequate for the renovated suite? |
New HVAC systems are to be provided, see mechanical drawings. Existing steam capacity is adequate. Contractor needs to perform test and balance provisions for verification per plans and specifications prior to demolition.
126 Are temporary HVAC systems required during construction?
Areas within scope of work will be unoccupied, temporary HVAC will not be required for unoccupied spaces. Areas outside of scope of work must be maintained in operation with appropriate demolition and test and balance of existing systems. If necessary to maintain hospital operations/conditions, provide temporary HVAC per 01 00 00 and ICRA; coordinate with COR.
| 127 | What shutdown durations are permitted for electrical tie-ins? | Per 01 00 00, submit outage requests; durations approved by COR; plan after‑hours. |
| 128 | Are spare breakers/conduits/capacity required beyond drawings? |
Confirmed that spare breakers and capacity as shown on construction documents is to be provided, no known other future demands are anticipated.
129 Is third-party electrical testing required (IR scan)?
See 01 91 00 for additional information.
| 130 | Confirm crane access, staging, and pick times (night/day). | See RFI 56/59; lifts typically after hours depending on impact to facility operations or roadways; submit plan and obtain approvals per 01 35 26/01 00 00. |
| 131 | 11 73 00 Ceiling Mounted Patient Lift System – Drawings indicate 2 lifts systems (rooms D363J and D363H). Please confirm these are the only 2 rooms receiving new lifts. | Yes. A110 Plan Notes include 11.22 Patient lift (dual‑axis) and show lifts in D363J and D363H. |
| 132 | Can the Government provide points of contact for Philips and for Stryker? The Philips point of contact listed on their drawings does not appear to work there any longer. | VA will provide updated OEM contacts via addendum; contractor to coordinate meetings. |