This is a Statement of Work (SOW) for the fabrication, assembly, testing, inspection, packaging, and delivery of one Target Service Shield for the Material Plasma Exposure Experiment (MPEX) at Oak Ridge National Laboratory (ORNL). The Target Service Shield is a water-cooled barrier component designed to protect Target Exchange Chart components during plasma exposure testing in the MPEX device, which is a superconducting magnet, steady-state fusion research apparatus. The scope includes fabrication per drawing MPEX-04-DES-05-A550 REVERSE TARGET SHIELD FULL ASSY, with ORNL providing one Company Furnished Equipment (CFE) component: the TARGET SHIELD EX-BONDED SHORT, COOLING CHANNEL (MPEX-04-DES-05-A562).
The work is organized into five primary tasks: (1) development of a quality plan and project schedule; (2) design review and performance specifications assessment; (3) manufacturing design review with fabrication plan documentation; (4) fabrication with recurring monthly status meetings; and (5) factory acceptance testing and delivery to ORNL's Oak Ridge, Tennessee facility under Delivered at Place (DAP) terms. The supplier must maintain an ISO 9001-certified or NQA-1 2008/2009a-compliant Quality Assurance Program and comply with the MPEX Vacuum Handbook and MPEX Quality Assurance Plan. Key requirements include electropolishing of stainless-steel vacuum components per ASTM B912, vacuum and hydrostatic leak testing, coordinate measuring machine (CMM) inspection after machining, welder and inspector qualifications, and comprehensive documentation including material certifications, weld inspections, dimensional reports, and magnetic permeability verification. The supplier must participate in bi-weekly status meetings, submit monthly reports by the third calendar day, and report any cost overruns immediately to the Technical Project Officer and Procurement Officer.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MPEX-04-SOW-604-R0
Statement of Work for a Target Service Shield for the
MATERIAL PLASMA EXPOSURE EXPERIMENT
(MPEX)
Prepared by
OAK RIDGE NATIONAL LABORATORY
Oak Ridge, TN 37831-6283 Managed by
UT-BATTELLE, LLC
For the
US DEPARTMENT OF ENERGY
under contract DE-AC05-00OR22725
This report was prepared as an account of work sponsored by an agency of the United States government. Neither the United States government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States government or any agency thereof.
MPEX-04-SOW-604-R0 Page 2 of 15
Material Plasma Exposure Experiment Oak Ridge National Laboratory
Statement of Work for a Target Service Shield for the
Material Plasma Exposure Experiment Project
MPEX-04-SOW-604
Reviewers:
Laura Parmley, TPO Date
Misty Magill, Procurement Officer Date
Milena Keys, Quality Assurance Representative Date
Aftab Hussain, MPEX Lead Engineer Date
Doug Curry, MPEX Operations Lead
Approver:
Adam Aaron, CAM Vacuum Systems, TPO Date
Distribution:
Phil Ferguson, MPEX Project Director Robyn Rose, MPEX Project Manager wc1 Comment on Text TPO updated to Matt Dessel. Original TPO signature staying on the document despite change.
MPEX-04-SOW-604-R0 Page 3 of 15
Statement of Work for a Target Service Shield for the
Material Plasma Exposure Experiment Project
MPEX-04-SOW-604
Revision History
Revision Date DESCRIPTION OF CHANGE
REVISION TYPE
Major Minor
0 7/2026 Initial Issue ☒ ☐
MPEX-04-SOW-604-R0 Page 4 of 15
CONTENTS
ACRONYMS
1 INTRODUCTION
2 SCOPE
3 APPLICABLE DOCUMENTS
4 PERFORMANCE REQUIREMENTS
4.1 TASK 1: QUALITY PLAN AND PROJECT SCHEDULE
4.2 TASK 2: DESIGN REVIEW AND PERFORMANCE SPECIFICATIONS
4.3 TASK 3: MANUFACTURING DESIGN REVIEW
4.4 TASK 4: TARGET SERVICE SHIELD FABRICATION
4.4.1 Company Furnished Equipment (CFE)
4.5 TASK 5: DELIVER TARGET SERVICE SHIELD
5 PROJECT MANAGEMENT
5.1 LANGUAGE
5.2 COMMUNICATIONS PROTOCOL
5.3 REPORTING .............................................................. ERROR! BOOKMARK NOT DEFINED.
5.4 KICKOFF MEETING
5.5 SCHEDULE AND MILESTONES
5.6 VARIANCE REPORTING
5.7 PERIODIC COMMUNICATIONS
5.7.1 Monthly Reports
6 QUALITY ASSURANCE
6.1 QUALITY PROGRAM
6.2 ACCESS FOR SOURCE SURVEILLANCE INSPECTION
6.3 SUPPLIER REQUESTED DEVIATIONS
6.4 MEASUREMENT AND TEST EQUIPMENT
6.5 MEASURING AND TEST MILESTONES
wc1 Cross-Out wc1 Inserted Text
4.5 Task 5: Factory Acceptance Testing
4.6 Task 5: Deliver Target Service Shield
MPEX-04-SOW-604-R0 Page 5 of 15
7 TRANSPORTATION
8 VACUUM INTEGRITY
9 DELIVERABLES
10 REFERENCES
MPEX-04-SOW-604-R0 Page 6 of 15
ACRONYMS
MPEX Material Plasma Exposure Experiment
TPO Technical Project Officer
ISO International Organization for Standardization
NIST National Institute of Standards and Technology
NQA ASME Nuclear Quality Assurance
QAP Quality Assurance Program
SOW Statement of Work
STEP Standard for the Exchange of Product Data
PMI Plasma Material Interaction
COTS Commercial Off The Shelf
DAP Delivered At Place
FAT Factory Acceptance Test
POC Point of Contact
PO Procurement Officer
ORNL Oak Ridge National Laboratory
CMM Coordinate Measuring Machine
VCR Swagelok VCR® Metal Gasket Face Seal Fitting
TEC Target Exchange Cart or Target Exchange Chamber
S/CI Suspect/Counterfeit Item
CFE Company Furnished Equipment
MPEX-04-SOW-604-R0 Page 7 of 15
1 INTRODUCTION
The Material Plasma Exposure eXperiment (MPEX), a superconducting magnet, steady-state device, is being constructed at Oak Ridge National Laboratory (ORNL), herein referred to as “the Company”, to address the harsh conditions inside a fusion reactor. This device, as designed, will have the unique feature conducting accelerated lifetime tests of plasma-facing components, including those that have experienced neutron damage.
The primary role of the Target Service Shield is to provide a water-cooled barrier to protect the Target Exchange Chart (TEC) components that support the target during plasma exposure in the MPEX device.
2 SCOPE
This Statement of Work (SOW) applies to the fabrication, assembly, testing, inspection, packaging, and delivery of QTY (1) of a Target Service Shield as defined in MPEX-04-DES-05-
A550 REVERSE TARGET SHIELD FULL ASSY [1]
Table 1 Target Service Shield Definition
Item Order Qty Drawing / Description
REVERSE TARGET SHIELD FULL ASSY 1 MPEX-04-DES-05-A550
The following components are being provided by the company in fulfillment of this fabrication:
Table 2 Target Service Shield Company Furnished Equipment
Item Order Qty Drawing / Description
TARGET SHIELD EX-BONDED SHORT,
COOLING CHANNEL
1 MPEX-04-DES-05-A562
3 APPLICABLE DOCUMENTS
The documents in Table 3 apply to this procurement.
Table 3. Appliable Documents for the Target Service Shield
Document MPEX-00-ENG-002 MPEX Vacuum Handbook [5]
MPEX-12-PLAN-001 Quality Assurance Plan for the MATERIAL PLASMA EXPOSURE
EXPERIMENT [6]
MPEX-04-SOW-604-R0 Page 8 of 15
4 PERFORMANCE REQUIREMENTS
4.1 TASK 1: QUALITY PLAN AND PROJECT SCHEDULE
The Seller shall prepare a quality plan and a project schedule for the fabrication, assembly, testing, inspection, packaging, and delivery of the Target Service Shield. The quality plan shall address how the Seller's Quality Program will be applied to the work in this SOW, and identify procedures and other documentation for all special processes, measurements, etc. The quality plan shall also identify the planned work to be outsourced, list the planned or expected subcontractors and Sellers, and address how the quality requirements of this SOW will be flowed down to these subcontractors and Sellers.
The project schedule shall contain sufficient detail so that ORNL may track procurement, fabrication, assembly, testing and shipping activities. The Seller shall propose milestones for tracking progress and payments including at a minimum those listed in Section 5.4.
For this task, the Seller shall provide ORNL with:
• Quality plan
• Project Schedule
• Factory Acceptance Test Plan
4.2 TASK 2: DESIGN REVIEW AND PERFORMANCE SPECIFICATIONS
The Seller shall review the MPEX drawings identified by the drawing package provided to the Seller in Table 1 and the guidelines and requirements outlined in MPEX-00-ENG-002 Vacuum Handbook (ORNL, 2021). The Seller can propose deviations or changes to these specifications.
ORNL will review these change requests.
Proprietary Seller fabrication processes that are different than drawing specifications or requirements of MPEX-00-ENG-002 Vacuum Handbook (ORNL, 2021) shall be identified and reviewed with ORNL. The seller is responsible for documenting any deviation from the MPEX Target Service Shield drawings.
Any deviation request shall be submitted by the Seller and approved by ORNL for all process or specification deviations then must be maintained under revision control after ORNL approval. The seller shall provide ORNL with all released documents.
4.3 TASK 3: MANUFACTURING DESIGN REVIEW
With the completion of Task 2, and with authorization from ORNL, the Seller shall prepare a fabrication plan for the Target Service Shield to demonstrate how the design specifications given in the Engineering Drawing Package (ORNL, 2023)[8] and MPEX-00-ENG-002 Vacuum Handbook (ORNL, 2021) will be satisfied. The Seller shall prepare a report and participate in a
MPEX-04-SOW-604-R0 Page 9 of 15 fabrication review. The Fabrication review will be held by videoconferencing or at the Seller's site based on agreement between the Seller and ORNL. The Seller shall prepare written meeting minutes and submit them to ORNL for review within 3 working days after the meeting.
Completion of the Fabrication review and closure of all action items shall constitute a project milestone.
The Fabrication Review and Report shall include:
• Component fabrication plan, including all purchased and outsourced components
• Review of materials and processes to be used for Target Service Shield fabrication
• A project plan summary of how compliance with all MPEX requirements and specifications will be achieved.
4.4 TASK 4: TARGET SERVICE SHIELD FABRICATION
After completion of Task 3 and with approval of the TPO, the Supplier shall provide an updated manufacturing schedule and commence construction. The Supplier and TPO shall establish a recurring fabrication update meeting not to exceed 1 month between meetings. The Supplier shall prepare a current manufacturing status report and identify any fabrication issues or logistics that will affect the agreed upon delivery date. The TPO will review the manufacturing status and identify action items for the the Supplier, TPO, or POC as applicable. Action item status shall be reviewed at each fabrication status meeting. Fabrication status meetings shall be held by videoconference or at the Supplier's site based on agreement between the POC and TPO. The Supplier shall prepare written meeting minutes and submit them to the TPO for review within 3 working days after each meeting. Meeting minutes may be used to supplement the monthly reporting requirements of 5.7
At a minimum, the meeting minutes shall include:
• Project schedule update o Component fabrication status o Assembly and Weldment fabrication status o Delivery status
• Quality Assurance status update o Quality Control Inspection reports o Non-conformance reports
• Status of action items
• Report any variances or deviations from the agreed upon specifications
• Summary of main discussion topics
• Summary of decisions and agreements between the Supplier, POC, and TPO
MPEX-04-SOW-604-R0 Page 10 of 15
Company Furnished Equipment (CFE)
The Supplier shall:
• Inspect the Target Service Shield assembly MPEX-04-DES-05-A562 TARGET SHIELD EX-BONDED SHORT, COOLING CHANNEL[9] upon receipt and document incoming receipt inspection for quantity, identification, visible damage, and condition and shall maintain custody control and protection of such material while it is in the Seller’s possession. Seller shall provide receipt inspection documentation to ORNL and notify the TPO of any shipping damage or discrepancies.
• Protect and maintain the furnished assembly while in its possession.
• Incorporate the furnished assembly into the completed Target Service Shield in accordance with the approved engineering drawings.
• Return the completed Target Service Shield assembly including this part to ORNL in accordance with the packaging and delivery requirements of this Statement of Work.
4.5 TASK 5: FACTORY ACCEPTANCE TESTING
Upon successful completion of Task 4 and with authorization of the TPO, the Supplier shall perform factory acceptance testing, generate quality plan compliance documentation.
4.6 TASK 5: DELIVER TARGET SERVICE SHIELD
Deliver the Target Service Shield in accordance with approved design from Task 3 meeting the specifications in [1] and [5] and according to an approved shipping plan. The Supplier shall provide support either remotely or at the Company's site for the site acceptance testing. Final acceptance of the Target Service Shield will occur upon successful completion of the site acceptance tests at the Company's facility.
5 PROJECT MANAGEMENT
5.1 LANGUAGE
All communications and documentation shall be in English.
5.2 COMMUNICATIONS PROTOCOL
The Supplier shall designate an official single POC to interface with the Company’s TPO. Only the Company’s Procurement Officer (PO) can authorize changes to the price or work scope. SOW or Technical Specification updates will only be issued to the Supplier by the Company's PO.
Problems encountered or anticipated shall be communicated as soon as practical.
MPEX-04-SOW-604-R0 Page 11 of 15
5.3 KICKOFF MEETING
The kickoff meeting will be scheduled at a mutually agreeable time as soon as practical after award of the subcontract. The Supplier is responsible for recording meeting minutes and submitting them to the TPO within 3 working days after the meeting.
The primary purpose for the kickoff meeting is to confirm that the project participants understand the terms and conditions of the subcontract, SOW, specifications, and work activities.
The following topics will be discussed:
1. Flow down of requirements, including flow down to outsourced suppliers.
2. Work activities, schedules, and deliverables
3. Expectations for satisfying quality standards and documentation
The Supplier shall be prepared to review Tasks 1 and 2 during the kickoff meeting.
5.4 SCHEDULE AND MILESTONES
At a minimum, the schedule shall include the following activities or milestones:
• Kickoff meeting
• Manufacturing Design Review
• Resolution of issues or concerns and approval for construction
• Materials ordered or fabrication commenced
• Factory Acceptance Tests
• Preparation for shipment
• Complete assembly at customer site
• Customer site final acceptance tests
• Complete final documentation
5.5 VARIANCE REPORTING
The Supplier shall notify the TPO and the PO immediately in writing when it is determined the actual cost may exceed the Agreement price. In no case shall the Supplier continue work without authorized funding if it is determined that actual cost may exceed the Agreement price.
5.6 PERIODIC COMMUNICATIONS
The Supplier shall participate in a bi-weekly (every other week) meeting to be held with the Company’s TPO to discuss any technical issues and schedule, personnel, and any other items pertinent to the work activities. The bi-weekly phone conference will serve as a mechanism to get early visibility of potential problems and issues arising during the performance of this subcontract.
The Supplier shall prepare written meeting minutes and submit these to the TPO within 3 working days after the meeting.
MPEX-04-SOW-604-R0 Page 12 of 15
5.7 MONTHLY REPORTS
Monthly reports shall be submitted by the third calendar day of each month or on the Supplier’s usual reporting schedule as mutually agreed between the TPO and the Supplier’s designated POC.
Monthly report data shall include actual schedule progress, milestones reached, corrective actions needed, display of the present critical path for the Supplier’s work, and a brief narrative describing the status of work, significant accomplishments, actual and potential problems and risk mitigations or corrective actions.
6 QUALITY ASSURANCE
6.1 QUALITY PROGRAM
The Supplier shall have an established and effectively implemented Quality Assurance Program (QAP) that, at a minimum, is ISO 9001 certified, but preferably compliant with NQA-1 2008/2009a or equivalent. The Supplier shall be able to demonstrate that it can fulfill the quality assurance requirements in this Statement of Work.
At a minimum, the prospective supplier shall have an established, documented, and effectively implemented quality assurance program describing controls for: work processes (controlled by instructions/procedures), personnel training and qualification, document and records control, design, procurement, inspection, and testing; including the use of measuring and test equipment when used, corrective action, and assessments (audits).
The Seller’s QAP will be evaluated to determine the degree of effective implementation of the quality program. Deficiencies, if any, identified during the evaluation shall be addressed and corrected to the satisfaction of ORNL. The QAP shall be approved prior to procurement of items.
All suppliers/sub-suppliers, subcontractors, and fabricators (as applicable) shall have a Quality Assurance Program that meets or exceeds the requirements described above.
All work at Supplier’s facility shall comply with the accepted industrial standards and codes and Quality Assurance Plan for the MPEX-12-Plan-001 MATERIAL PLASMA EXPOSURE
EXPERIMENT [6].
When a nonconformance is identified, the Supplier shall document and report the condition to the Company in a Non-Conformance Report (via email, copy of internal NCR Form, Or Supplier’s NCR form partially completed) to the TPO, with a copy to the Procurement Officer (PO) and MPEX Quality Representative (QR), as soon as reasonably possible.
Items that do not conform to specified requirements shall be controlled to prevent inadvertent installation or use. The Non-Conformance Report should contain or refer to all relevant material available to enable an informed decision on the definite course of action to be taken. At a minimum, this report shall describe the issue, provide details on how it could or could not affect the performance, safety, reliability, operability, traceability, interchangeability, or regulatory requirements, and provide disposition of the issue as applicable.
MPEX-04-SOW-604-R0 Page 13 of 15
The Company TPO will review and discuss the Non-Conformance Report with the Supplier and based on the review, either return the Non-Conformance to the Seller POC with approval to provide any additional details, action items, proposed dispositions, and justifications with resolution for the Supplier to implement prior to resuming work.
The Supplier’s QAP shall include a S/CI Program that is compliant with DOE O 414.1D, Quality Assurance ( https://www.directives.doe.gov/ ), or an approved equivalent.
6.2 ACCESS FOR SOURCE SURVEILLANCE INSPECTION
As part of the Company’s quality assurance program, the Company reserves the right to perform source surveillance/inspection activities at the Supplier’s facility or any sub-tier Supplier facility that the Company determines necessary to ensure that quality requirements are met.
The Company reserves the right to schedule all critical operations (to be determined by the Company) for the convenience to supervise and witness these operations.
6.3 SUPPLIER REQUESTED DEVIATIONS
The Supplier shall propose any deviations to the specifications, drawings, or other technical requirements and obtain the Company’s approval prior to invoking the deviation. Any Deviation Requests arising from the fabrication phase shall adhere to the Supplier's Quality Program procedure and must be approved by the Technical Project Officer (TPO).
6.4 MEASUREMENT AND TEST EQUIPMENT
Tools, gages, instruments, and other measuring and test equipment used for activities affecting quality shall be controlled, calibrated at specified periods, adjusted, and maintained to required accuracy limits. Records shall be provided to ORNL prior to onset of activities.
Measuring and test equipment used by the Supplier to perform work under this Statement of Work shall be calibrated and traceable to NIST standards. Calibrations shall be current. Calibration records shall be provided to the Company.
6.5 MEASURING AND TEST MILESTONES
• CMM inspection required after completion of machining of Target Service Shield
• Vacuum and hydrostatic leak testing required for welds of complete assembly after completion of final welding of full assembly of Target Service Shield
7 TRANSPORTATION
ORNL will ship the Company Furnished Target Service Shield assembly to the Supplier following subcontract award.
MPEX-04-SOW-604-R0 Page 14 of 15
The completed Target Service Shield shall be packaged in a manner that protects the equipment from damage, indicates exposure to shock during handling, and facilitates movement, loading, and unloading by fork truck or crane. Delivered at Place (DAP) (ORNL Facility – Oak Ridge TN).
8 VACUUM INTEGRITY
• All stainless-steel vacuum components exposed to vacuum shall be electropolished per
ASTM B912, passivation of stainless steels using electropolishing.
o Passivate MPEX-04-DES-05-A549. [6] o Do NOT passivate MPEX-04-DES-05-A548 [6]or MPEX-04-DES-05-A550. [6]
• VCR fittings shall incorporate appropriate VCR caps.
9 DELIVERABLES
The Supplier shall deliver:
• Target Service Shield meeting the requirements of the referenced documents.
• Calibration records for measurement and test equipment
• Welder qualification documents
• Inspector qualification documents
• Test and Inspection results
• Material Mill Test Report
• Cleaning Certification
• Certificates of Compliance for all purchased components and materials
• Final report documenting any non-conformances
• Shipping plan compliant with MPEX Vacuum Handbook [6]
• Any documentation otherwise identified above but not part of this list.
Completed factory acceptance test report shall include as a minimum:
• Vacuum Leak Checking Report (Water passages must be vacuum tight since assembly operates in vacuum chamber.)
• Hydrostatic Testing Report
• Magnetic Permeability Verification Report
• Material Certifications
• Weld Certifications and Weld Inspections
• Dimensional Inspection Report wc1 Cross-Out Reference [4] wc1 Cross-Out wc1 Inserted Text Reference [3] wc1 Cross-Out wc1 Inserted Text References [1] and [2] wc1 Cross-Out wc1 Inserted Text Reference [5]
MPEX-04-SOW-604-R0 Page 15 of 15
10 REFERENCES
[1] MPEX-04-DES-05-A550 REVERSE TARGET SHIELD FULL ASSY
[2] MPEX-04-DES-05-A550 REVERSE TARGET SHIELD FULL ASSY.STEP
[3] MPEX-04-DES-05-A548 TARGET SERVICE SHIELD SHORT, WELDMENT
[4] MPEX-04-DES-05-A549 TARGET SHIELD SUPPORT REVERSE ASSY
[5] MPEX-00-ENG-002 Vacuum Handbook [6] MPEX-12-PLAN-001 Quality Assurance Plan for the MATERIAL PLASMA EXPOSURE
EXPERIMENT
[7] ASME Boiler and Pressure Vessel Code (BPVC) [8] Engineering Drawing Package (ORNL, 2023)
[9] MPEX04-DES-05-A562 TARGET SHIELD EX-BONDED SHORT, COOLING CHANNEL
| 2026-08-20T07:38:07-0400 | |
| Laura Parmley |
| 2026-08-24T08:00:35-0400 | |
| Misty Magill |
| 2026-08-24T10:12:54-0400 | |
| Milena Keys |
| 2026-08-24T11:41:48-0400 | |
| Muhammad Aftab Hussain |
| 2026-08-25T02:39:10-0400 | |
| Not applicable for this document |
| 2026-08-25T09:03:32-0400 | |
| Aaron, Adam |
File details come from the government source that posted it. Updated .