SOW UItenhage 651 - Exterior painting and repairs- make ready. V2_SM.pdf
PDF 340 KB Posted
- Solicitation number
- PR16401406
- Issued by
-
Department of State US Embassy Pretoria
About this file
This is a Statement of Work (SOW) for maintenance and repair services at the U.S. Embassy Pretoria, specifically for exterior painting and repairs at a residential property (Uitenhage 651) to prepare it for occupancy. The project requires general exterior painting with one coat on all previously painted surfaces, minor maintenance repairs, removal of bird nests, and installation of a steel door on a municipal box. Work scope includes eight primary tasks: painting exterior eaves/boarding/ceilings, surface-mounted equipment and pipes, concrete surfaces, steelwork (window frames, gates, rails, pool fence), all exterior building surfaces, miscellaneous maintenance (roof inspections and aluminum drying line installation), property-specific items, and final finishing with touch-ups and paint removal from fixtures and windows.
Proposals must include itemized cost breakdowns separating labor and materials by task category, a detailed project timeline, confirmation of completion within two weeks maximum (combined interior and exterior work), company profile with evidence of similar projects, and a comprehensive safety plan. Specific paint products are mandated, including Bergmaster Craftsman Nukote White Acrylic, Dulux Weatherguard Ultrasmooth, and Dulux High Gloss Enamel in black or white. The contractor bears responsibility for all materials, equipment, insurance, permits, and site cleanup, with a 12-month workmanship guarantee required on all surfaces and repairs. All contractor personnel must complete security vetting before site access, and a mandatory pre-construction safety meeting is required. The Point of Contact is Etienne Smit, Project Manager/COR. No response deadline, award date, pricing terms, or federal set-asides are specified in this SOW.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation provision and clauses.docx | DOCX document | |
| SOW UItenhage 651 - Interior painting and repairs- make ready. V2_SM.pdf |
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR SIGNATURE___________________________________________________________
US Embassy Statement of Work – GOP Residential, Preparing residence for Occupation.
Exterior painting and repairs.
Uitenhage 651
P a g e 1 | 7
Embassy of the United States of America
Pretoria, South Africa.
STATEMENT of WORK
Maintenance and repair.
Project: Exterior painting and repairs.
Exterior painting and repairs.
Uitenhage 651
P a g e 2 | 7
Project title: Uitenhage 651 - Exterior painting and repairs.
1. GENERAL
1.1 Scope of Work The Contractor shall furnish all professional services, labor, materials, equipment, required insurance, permits, and any other items, accessories, and services needed to complete the maintenance work specified here. The Contractor shall perform all work in accordance with this Statement of Work, available information, and local regulations.
1.2 Project Description The U.S. Embassy Pretoria requires general exterior painting and minor maintenance repairs to prepare the residence for occupation. The residence is generally in good condition. The scope covers:
• Preparing, repairing and repainting all previously painted exterior surfaces (one coat)
• General maintenance, repairs and upkeep of all buildings on the property
• Removing bird nests and installing a steel door on the municipal box
1.3 Proposal Requirements Proposals shall include:
• A detailed response to every task in Section 6: Project Requirements
• An itemized cost breakdown separating labor and materials for each task category
• A project timeline and work plan showing the time needed to perform the services
• Confirmation that the interior and exterior work can be completed within the combined project duration
• A detailed lump sum fee for the services
• A company profile (if new to U.S. Government projects), with evidence of similar completed projects
• A safety plan (required before work starts)
1.4 Site Access and Security Requirements All Contractor personnel must complete security vetting before accessing the site.
Vetting requires:
• Submitting copies of identification documents to the P.O.C.
• P.O.C. submission to the security office for temporary clearance approval
• Access clearances valid only for the dates and times coordinated with the P.O.C.
• Recording all service dates on access control sheets
• Presenting original identification documents (not certified copies) at each site visit for verification
2. DEFINITIONS
• Owner: The U.S. Embassy Pretoria
• P.O.C. (Point of Contact): The designated Project Manager and Contracting Officer's Representative, Etienne Smit
• COR: Contracting Officer's Representative
• Contractor: The awarded vendor
3. SITE FAMILIARIZATION
The Embassy will conduct a site visit. The Contractor shall show thorough familiarity with the nature of the work, site conditions, and all factors that may affect the project. The Contractor shall notify the P.O.C. in writing of any additional information it needs.
4. SUGGESTED MODIFICATIONS
The Contractor may propose changes to the scope of work that would improve project outcomes. The Owner will review all suggestions for acceptance.
Exterior painting and repairs.
Uitenhage 651
P a g e 3 | 7
5. PROPOSAL SUBMISSION REQUIREMENTS
5.1 Critical Notice The Contractor must verify all measurements before submitting a quotation. The Owner will not approve cost adjustments due to measurement errors.
5.2 Pricing Requirements
CONTRACTOR/COMPANY: ________________________________________
TASK CATEGORY COST – LABOR
(R)
COST – MATERIAL
(R)
1. Exterior Eaves/Boarding/Ceilings (1 coat)
2. Surface Mounted Equipment (1 coat)
3. Concrete (1 coat)
4. Steelwork (1 coat)
5. Exterior, All Buildings (1 coat)
6. Maintenance and Miscellaneous
7. Property-Specific Items (Bird Nest Removal, Municipal Box Steel
Door)
8. Final Finishing
SUBTOTAL
VAT (if applicable)
TOTAL AMOUNT QUOTED
Contractor Concerns and Notes:
Exterior painting and repairs.
Uitenhage 651
P a g e 4 | 7
6. PROJECT REQUIREMENTS
General Requirement – Preparation and Neatening
• Before painting starts, the Contractor shall neaten all areas: repair, patch, fill and make good all damage. The Owner will not accept paint applied over unrepaired defects.
TASK 1: Painting – Exterior Eaves/Boarding/Ceilings (1 Coat)
6.1.1 Surface Preparation
• Remove all poorly adhering paint
• Brush down and wash off friable deposits, dust and surface contamination
• Brush down areas of mold and fungus growth, then treat them with Excelsior MouldGo and leave it to react for at least
24 hours
• Wash off with clean water, then apply a second coat of Excelsior MouldGo
• Sand down all nail heads to remove surface rust, and wipe clean
6.1.2 Priming
• Prime all nail heads with one coat of Duram NS4 Metal Primer (White)
• Prime all bare areas with Dulux Rock Grip Plaster Primer (5148264)
6.1.3 Finish Coating
• Apply one coat of Bergmaster Craftsman Nukote White Acrylic
TASK 2: Painting – Surface Mounted Equipment, Pipes, Trunking (1 Coat)
6.2.1 Scope
• All exposed copper pipes, conduit, PVC pipes and PVC trunking
• All surface-mounted equipment
6.2.2 Surface Preparation
• Scrape down and sand to remove all loose and flaking paint
• Wash down the entire surface to remove dust and surface contamination
6.2.3 Finish Coating
• Apply one coat of Dulux Weatherguard Ultrasmooth
TASK 3: Painting – Concrete (Steps/Gulleys/Surrounds/Windowsills) (1 Coat)
6.3.1 Scope
• All concrete steps, cement gulleys, drain surrounds and windowsills
6.3.2 Surface Preparation
• Scrape and sand down to remove all loose cement and dirt
• Scour with a steel bristle brush and water
• Allow 24 hours to dry before painting
6.3.3 Finish Coating
• Apply one coat of Dulux Weatherguard Ultrasmooth, color to match the gutters
TASK 4: Painting – Steelwork (1 Coat)
6.4.1 Scope
• All window frames, including window frame putty repairs
• All exterior steelwork: gates, rails, balustrades, pool fence, vehicle gate, intercom, etc.
• Pool fence: Replace the post caps on all main posts with flat caps
6.4.2 Surface Preparation
• Scrape down and sand to remove all poorly adhering paint, then wipe clean
• Chip away all rust scale and sand down to a rust-free surface (as far as practically possible)
• Apply Duram NS1 Rust Buster to all rust-affected surfaces. Let the chemical reaction finish before washing down with clean water, then allow to dry.
Exterior painting and repairs.
Uitenhage 651
P a g e 5 | 7
6.4.3 Priming and Undercoating
• Prime all bare metal areas with Duram NS4 Metal Primer (White)
• Apply Dulux Trade Universal Undercoat to the primed areas; allow to dry, sand lightly and wipe clean
6.4.4 Finish Coating
• Apply one coat of Dulux High Gloss Enamel (Black/White), to match the existing color
TASK 5: Painting – Exterior, All Buildings (1 Coat)
6.5.1 Scope
• All previously painted exterior surfaces, including all walls, pots and windowsills
6.5.2 Surface Preparation
• Complete all necessary repairs and preparation before painting, to deliver a neat and professional finished product
• Wash all surfaces thoroughly with sugar soap
6.5.3 Paint Specifications
• Apply one coat
• Exterior colors: Karoo Land and Cattlewood Canyon
TASK 6: Maintenance – Miscellaneous
• Inspect all roofs for leaks and integrity. Report findings to the P.O.C., then repair minor leaks as required.
• Supply and install aluminum foldable clothing drying lines, black powder-coated, 2.5m x 6 lines. The Contractor shall confirm the quantity with the P.O.C. on site.
TASK 7: Property-Specific Exterior Items
6.7.1 Bird Nest Removal
• Remove all bird nests from the exterior of the property, including the eaves, roof void access points and any other affected areas. The P.O.C. will confirm locations at the site visit.
• Inspect for any damage or blockages caused by the nesting, for example in gutters or vents. Report findings to the
P.O.C. before carrying out any repairs.
6.7.2 Municipal Box Steel Door
• Supply and install a steel door on the exterior municipal box
• Size the door to fit the existing opening. It shall be hinged, lockable and weather resistant.
• Prime the door, then paint one coat to match the surrounding exterior finish, or as the P.O.C. directs
TASK 8: Final Finishing
6.8.1 Touch-Up and Snag Correction
• The Contractor shall return for touch-up painting or minor snag work needed after the residence is furnished and during the final occupancy phases
6.8.2 Paint Removal and Cleaning
• Remove all paint marks (new or old) from windows, floors, fixtures, fittings, doors, furniture, appliances and worktops
• Do not use abrasive or harmful materials or chemicals; use scraper blades where appropriate
• Make sure no fittings or fixtures are damaged or scratched during cleaning
6.8.3 Detail Work
• Attention to detail is essential. The Contractor shall complete small detail and miscellaneous finishing work that may not have been seen during the site meeting.
Exterior painting and repairs.
Uitenhage 651
P a g e 6 | 7
7. GENERAL REQUIREMENTS
7.1 Site Management
• Remove all redundant and unused equipment, nails, hooks, wiring, antennas, dishes and mounting fixtures (confirm with the P.O.C. before removal)
• Keep the site clean and organized at all times; clean up daily
• Remove and dispose of all removed and scrap material off site (confirm with the P.O.C. before removal)
7.2 Quality Standards
• Neaten and finish all affected and surrounding damaged areas, top to bottom
• Pay meticulous attention to detail in every phase
• The Contractor is liable for repairing or replacing any fixtures and fittings it damages
7.3 Warranty
• 12-month workmanship guarantee on all surfaces and repairs
• The warranty covers defects in materials and workmanship
8. POINTS OF CONTACT
Project Manager / COR / P.O.C.: Etienne Smit U.S. Embassy Pretoria
Procurement: Until the Purchase Order is issued, route all communication through the Pretoria Procurement agent assigned to the project.
9. PROJECT LOCATION
Uitenhage 651, Pretoria
10. PROJECT DURATION
• Duration: TWO weeks maximum for the combined interior and exterior project
11. SAFETY REQUIREMENTS
11.1 Applicable Safety Standards The Contractor shall comply with all U.S. and local government safety regulations, including:
• U.S. Army Corps of Engineers EM 385-1-1 Safety and Health Requirements Manual, available at:
http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx
• United States Occupational Safety and Health Administration (OSHA) requirements
11.2 Safety Plan and Implementation The Contractor shall:
1. Develop and submit: a project-specific safety plan; hazard control methods appropriate to the work in accordance with
EM 385-1-1; emergency response procedures
2. Provide PPE: safety gloves, safety footwear, eye protection, hearing protection, and fall protection equipment (where applicable)
3. Implement safety measures:
o Appropriate barricades and warning signage o Fall protection systems for elevated work, including roof inspections, eaves and bird nest removal o Ladder safety protocols for working at heights o Proper inspection and maintenance of all equipment and tools, including GFCI protection for electrical appliances such as pressure washers o Proper use of PPE, and proper material handling and storage
4. Maintain compliance: conduct daily safety briefings; perform regular safety inspections; document safety activities;
correct unsafe conditions immediately; report all incidents to the P.O.C.
http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx
Exterior painting and repairs.
Uitenhage 651
P a g e 7 | 7
11.3 Pre-Construction Safety Meeting The Contractor shall attend a mandatory safety meeting before work starts. The meeting will review project-specific hazards, safety plan implementation, emergency procedures, site-specific requirements and communication protocols.
11.4 EM 385-1-1 Compliance Guide For successful compliance with EM 385-1-1, Contractors should focus on:
• The Introductory Letter (overview and intent)
• Section 1 (general requirements and submission procedures)
• Appendix A (required documentation and forms)
These sections detail what you need to know and submit to begin work. Additional technical sections apply only to specific hazards relevant to your project scope.
12. PICTURE INDICATIONS
Partial indications only; these do not replace the full SOW.
End of SOW