PR14917290 - PROJECT MILESTONE - BSB - GSO MP-PREVENTIVE CORRECTIVE MAINT FOR EMB VHCLs.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
BPA SETUP FOR PREVENT & CORRECT. MAINT. FOR EMB VHCLs
Solicitation number
19BR2525Q0002
Issued by

About this file

This is a project milestone tracking spreadsheet for a Blanket Purchase Agreement (BPA) setup for vehicle preventive and corrective maintenance services at the U.S. Embassy in Brasilia, Brazil. The project spans from October 17, 2023 to May 16, 2025, with an overall duration of 370 days and is currently 82% complete.

The milestone schedule shows key procurement phases including SOW development (completed), RFQ preparation and solicitation (completed), market research and advertisement (completed), and BPA setup activities. Several upcoming tasks remain including a new RFQ submission scheduled for January 28, 2025, re-advertisement on the Embassy website and SAM.gov, BPA approval and issuance to vendors, and caller training planned for May 16, 2025. The project is being managed by Leovegildo Mata for the Department of State U.S. Embassy Brasilia, with the solicitation number 19BR2525Q0002.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project tasks

Project nameBPA SETUP FOR GSO MPOOL|PREVENTIVE & CORRECTIVE MAINT FOR EMB VHCLs
Project managerLeovegildo Mata
Project start date10/17/2023
Project finish date5/16/2025
Duration370 days
% complete82%
Exported on12/13/2024
Task numberTask DescriptionAssigned toDurationStartFinish% complete
1Scope of Work (SOW)Leovegildo Mata65 days10/23/20231/19/2024100%
2Receive a PRLeovegildo Mata1 day1/19/20241/19/2024100%
3RFQ - Prepare Solicitation PackageLeovegildo Mata113 days1/19/20246/25/2024100%
4Advertisement/Market Research & RFQ e-mailsLeovegildo Mata15 days6/26/20247/16/2024100%
5Receive the RFQ signed by the vendorsLeovegildo Mata18 days7/8/20247/31/2024100%
6Prepare BPA Setups and Send for Final ApprovalLeovegildo Mata2 days7/17/20247/18/2024100%
7Prepare BPA Setups and Send for Final ApprovalLeovegildo Mata45 days7/19/20249/19/2024100%
8CO Notification to submit a RFQ and start a new processLeovegildo Mata1 day10/8/202410/8/2024100%
9New RFQ will be submitted for CO approvalLeovegildo Mata1 days1/28/20251/28/20250%
10Re-advertisement on the Embassy Official Website and SAM.GOVLeovegildo Mata15 days1/28/20252/11/20250%
12Approve the BPAs-SetupLeovegildo Mata1 day2/12/20252/13/20250%
13Issue out the BPA Setup to the vendorsLeovegildo Mata1 day2/14/20252/17/20250%
14Receive the BPA Setup SignedLeovegildo Mata3 days2/18/20252/21/20250%
15Create a BPA Log and sent instruction to the callersLeovegildo Mata1 day2/21/20252/21/20250%
16Training presentation for the callers about BPALeovegildo Mata1 day5/16/20255/16/20250%