PPQ Replace 15K Feeder Line.pdf
PDF 143 KB Posted
- Solicitation number
- 36C25621R0124
About this file
This document contains a past performance questionnaire and federal contract opportunity notice for replacement of an electrical feeder line at a Department of Veterans Affairs medical center. The past performance questionnaire seeks input on a contractor's performance on previous, similar projects and includes 19 questions rated on a scale from Outstanding to Unacceptable, along with yes/no questions regarding cure notices, proactive behavior, cost savings suggestions, and recommendation of the contractor. The related federal contract opportunity is to replace a 15kV electrical feeder line at the Eugene Towbin Veterans Hospital in North Little Rock, Arkansas, with a cost estimate between $500,000 and $1,000,000. The replacement work requires removing an overhead transmission line and installing an underground concrete-encased duct bank. The project is designated as 100% set aside for Service-Disabled Veteran Owned Small Businesses under NAICS code 236220 with a small business size standard of $39.5 million.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AUG 2021.07.30_598-19-120_Construction Documents Addendum #1_Drawings.pdf | ||
| 36C25621R0124 0003.docx | DOCX document | |
| AUG Replacement of 15kV Electrical Feeder RFIs.docx | DOCX document | |
| Replacement of 15kV Electrical Feeder RFIs-PARTIAL ANSWERS.docx | DOCX document | |
| 36C25621R0124 0002.docx | DOCX document | |
| 36C25621R0124 0001.docx | DOCX document | |
| Division Cost Page (002).docx | DOCX document | |
| WAGE DETERMINATIO1 - Copy.docx | DOCX document | |
| Combine Drawings-598-19-120 Replace High Voltage Feed NLR - Copy.pdf | ||
| S02. SOL 36C25621R0124_1.pdf | ||
| 598-19-120_Construction Documents Submission_Spec Manual - Copy.pdf | ||
| SOW 598-19-120 REPLACE HIGH VOLTAGE FEED NLR - Copy.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAST PERFORMANCE QUESTIONAIRE
Replacement of 15K Feeder Line
To: ____________________ (Point of Contact)** ____________________ (Company)** ____________________ (Phone) ____________________ (Fax) ____________________ (E-Mail)** _____________________ (Name of Company requesting survey)**
The company from which you received this survey is competing for award of a contract with the Department of Veterans Affairs, Little Rock, AR. As part of the process for screening potential Offerors, this company is soliciting your input and assessment of its past performance for one or more projects they performed for your firm. Please respond to each of the questions below and forward the completed survey directly to the CAVHS Contract Specialist.
To consider your responses, the Contract Officer must receive your responses, either by fax or e-mail.
If you have any questions or comments, feel free to contact me. Thank you in advance for your assistance.
Brad Martin Contracting Officer Email: Bradley.Martin@va.gov
Please identify the project(s) that this company has performed for your organization, description, city, state, and award amount and final dollar value at completion of contract:
mailto:Bradley.Martin@va.gov
PAST PERFORMANCE SURVEY
Respond to the question using the following scale: O- Outstanding, A- Acceptable, S- Satisfactory, M- Marginal, U-Unacceptable.
1. Did the contractor commit adequate resources in timely fashion to the contract to meet the requirements and to successfully solve problems? O A S M U
2. To what extent did the contractor respond positively and promptly to technical direction, contract change orders, etc.?
O A S M U
3. How reliably did the contractor follow through on commitments?
O A S M U
4. To what extent did the contractor’s management system provide visibility into problems and risks?
O A S M U
5. How responsive do you think the contractor was to information requests, issues, or problems during the course of the contract? O A S M U
6. How effective has the contractor been in identifying requirements?
O A S M U
7. To what extent did the contractor have the ability to administer and manage the contract?
O A S M U
8. To what extent did the contractor issue professional correspondence?
O A S M U
9. How well did the contractor adhere to the Statement of Work? O A S M U
10. What was your level of satisfaction with the contractor’s management and support staff?
O A S M U
11. What was your level of satisfaction with the contractor’s Supervisor(s)?
O A S M U
12. To what extent did the contractor submit required reports and documentation in a timely manner? O A S M U
13. To what extent were the contractor’s reports and documentation accurate and complete?
O A S M U
14. To what extent was the contractor’s maintenance and problem tracking/reporting documentation timely, accurate and of appropriate content?
O A S M U
15. To what extent did the contractor comply with safety requirements?
O A S M U
16. What was your level of satisfaction with the contractor’s overall quality of service?
O A S M U
17. To what extent was the contractor effective in interfacing with the Government staff?
O A S M U
18. What was your level of overall customer satisfaction? O A S M U
19. To what extent were the contractor’s employees experienced and qualified?
O A S M U Respond: Yes or No.
20. Were there any cure notices issued? Yes: ____ No: ____
21. Was contractor pro-active? Yes: ____ No: ____
22. Did contractor suggest cost-saving changes? Yes: ____ No: ____
23. Would you recommend this contractor? Yes: ____ No: ____
For Federal contracts:
24. Were there any Labor Department Investigations? Yes: ____ No: ____
24a. If yes, please describe reason and final outcome.
25. Were there any safety investigations? Yes: ____ No: ____
25a. If yes, please describe reason and final outcome.
26. Were there any security investigations? Yes: ____ No: ____
26a. If yes, please describe reason and final outcome.
27. Was there a partial or complete termination for default or convenience?
Yes: ____ No: ____
27a. If yes, please describe reason and final outcome.
28. Are there any pending terminations? Yes: ____ No: ____
29. What is/was the duration of the contract? _____________________
30. Were there any performance issues regarding the contractor’s work? If yes, please describe
(use a separate sheet of paper if necessary).
Please provide other comments (Use a separate sheet of paper if necessary):
Signature: ____________________________
Date: ____________________________
**Required
File details come from the government source that posted it. Updated .