This document outlines a post-award schedule for a project-specific advertisement (PSA) attachment to a lease of office space within Region 3. The schedule provides timeframes for key activities following a lease award, including design kick-off meetings, submissions of design intent drawings and construction documents, pricing for tenant improvements and building security access controls, construction kick-off meetings, and government acceptance. Major milestones include the lessor providing initial design intent drawings within 60 days, 100% construction documents within 15 days, tenant improvement and security pricing within 30 days, construction completion within 270 days, and government acceptance within 10 days of substantial completion. The schedule is intended to replace the attachment referenced in the request for lease proposals and inform timelines in the lease agreement.

View the file

Other files

File Type Posted
NewDA.pdf PDF
Delineated Area.pdf PDF
Architect Scope of Work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 and 4.06 of the Lease (L100).

The below post-award schedule commences within 10 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Design Kick-Off Meeting with Lessor, GSA, & Agency 10 days after lease award

Lessor Provides Initial Design Intent Drawings (DIDs) 60 days

Lessor Provides 100% DIDs 15 days

Lessor Provides Initial CDs 60 days

Lessor Provides 100% CDs 15 days

Lessor Provides TI and BSAC Pricing 30 days

TI/BSAC Bid Negotiations complete 60 days

Construction Kick Off Meeting 15 days

Lessor Completes Required Construction Work 270 days

Government Acceptance/Substantial Completion 10 days

Punch List Completed 10 days