PNA_South Cobb Drive_City of Smyrna.pdf
PDF 361 KB Posted
- Solicitation number
- PE-63353-NONST-2027-000000047
- Issued by
- Cobb County, Georgia
About this file
This is a Public Notice Advertisement from the City of Smyrna, Georgia, soliciting a Design-Build contractor to provide design, preconstruction, and construction services for State Route 280 (South Cobb Drive) Improvements Project (P.I. Number: 0018265). The project encompasses corridor improvements along South Cobb Drive from Concord Road to Windy Hill Road, including a 12-foot shared-use path on both sides of the roadway, local access lanes in each direction, two through lanes in each direction, raised landscaped buffers, a raised median, curb and gutter, roadway lighting, storm drainage enhancements including two culvert improvements, installation of one new traffic signal, reconstruction of six existing traffic signals, driveway modifications, and realignment of Plaza Drive. The solicitation follows a two-phase selection process using the Georgia Department of Transportation Design-Build methodology. The tentative schedule includes an Industry Forum on November 27, 2027, at 8:00 a.m. (virtual, pre-recorded presentation); Request for Qualifications issuance on March 5, 2027; Statement of Qualifications deadline on April 2, 2027, at 5:00 p.m.; notice to finalists on April 16, 2027, at 11:00 a.m.; Request for Proposals issuance on April 30, 2027, at 10:00 a.m.; proposal receipt on May 28, 2027; bid opening on May 31, 2027, at 9:00 a.m.; and city letting on June 14, 2027. The selection of the apparent successful proposer will be based on the highest overall score among proposers meeting RFQ/P requirements.
The Design-Builder must be prequalified by Georgia DOT in Urban Roadway Design (Area Class 3.02) or Complex Urban Roadway Design (Area Class 3.03) for the land design consultant role. Additionally, team members must maintain Georgia DOT prequalification in multiple area classes including NEPA Documentation, traffic projections and operations, landscape architecture, utility coordination, hydraulic and hydrological studies, land surveying, utility engineering, soil surveys, hazardous waste assessment, construction engineering, and erosion and sedimentation control. Key team leaders required include a DB Project Manager, Preconstruction Project Manager, Construction Project Manager, and Utility Liaison. The following firms are identified as conflicted and ineligible: Croy Engineering, LLC; Greg Malcom & Associates, Inc.; Geo-Hydro Engineering, Inc.; Lumenor Consulting Group, Inc.; Marr Traffic, Inc.; and New South Associates, Inc. All communication regarding this solicitation will be conducted through the Georgia Procurement Registry and BidNet Direct. No pricing information, set-asides, or funding sources are specified in this public notice advertisement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NTC_South Cobb Drive_City of Smyrna.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Posted: November 13, 2026
City of Smyrna, Georgia
Public Notice Advertisement
PNA-006-11132026DB
To Provide
Design-Build Services for SR 280 (South Cobb Drive) Improvements Project
P.I. Number: 0018265 City of Smyrna, GA
City of Smyrna, Georgia City Hall
2800 King Street, Smyrna, Georgia 30080
Page 2 of 4 PNA-006-11132026DB
Public Notice Advertisement Design Build Services
The City of Smyrna, Georgia hereby posts the following Public Notice Advertisement (“PNA”) for considered services. The City of Smyrna intends to solicit responses from interested firms to provide services as Design-Builder (DB) for the State Route 280 (South Cobb Drive) Improvements Project in Smyrna, Georgia.
Please review Section 3 (Tentative Schedule of Events) below to obtain solicitation information.
THIS IS A PUBLIC NOTICE ADVERTISEMENT ONLY. No document submittals are expected or required in response to this PNA.
This project will follow the Georgia Department of Transportation (Georgia DOT) Design Build process.
Information regarding Georgia DOT’s Design-Build process can be reviewed at the following website:
https://www.dot.ga.gov/PartnerSmart/DesignManuals/DesignBuild/001-GDOT_Design-Build_Manual.pdf
Method of Communication
All general communication of relevant information regarding this PNA and any subsequent solicitation will be made via the Georgia Procurement Registry (“GPR”) at https://ssl.doas.state.ga.us/gpr/ and Smyrna Purchasing Division at https://www.bidnetdirect.com/georgia/cityofsmyrna through the advertisement of the RFQ/P. All proposers that respond to a City of Smyrna-issued solicitation are responsible for checking the GPR on a regular basis for updates, clarifications, and announcements.
SECTION 1 – GENERAL PROJECT INFORMATION AND SCOPE
The City of Smyrna is seeking to contract with a Design-Build Contractor to provide design, preconstruction and construction services that are necessary for the corridor improvements to State Route 280 (South Cobb Drive) along its existing alignment from Concord Road to Windy Hill Road in Smyrna, Georgia (“Project”).
Proposed improvements include a 12-foot shared-use path on both sides of the roadway, a local access lane in each direction, two through lanes in each direction, raised landscaped buffers separating the through lanes from the local access lanes, and a raised median separating opposing traffic movements. Additional improvements include curb and gutter, roadway lighting along the shared-use paths and local access lanes, storm drainage enhancements including two culvert improvements, installation of one new traffic signal, reconstruction of six existing traffic signals, driveway modifications, and the realignment of Plaza Drive.
The Project’s scope will be in accordance with requirements set forth in the DB Request for Qualifications/Proposals
(“RFQ/P”).
To review the project synopsis and other available information about the Project, please go to the following website: https://www.smyrnaga.gov/departments/administration/city-administrator/city-projects/south-cpbb-drove-project
The Project information is located in the following folder: 0018265 – SR 280 at Concord Rd to Windy Hill.
The following firms are known to be conflicted on the Project and may not participate:
Croy Engineering, LLC Greg Malcom & Associates, Inc.
Geo-Hydro Engineering, Inc.
Lumenor Consulting Group, Inc.
Marr Traffic, Inc.
New South Associates, Inc.
Page 3 of 4 PNA-006-11132026DB
SECTION 2 – SELECTION PROCESS
A two-phase, low bid selection process will be used to award the Project to the apparent successful proposer.
The selection of the apparent successful proposer will be based on the highest overall score among the proposers who presented proposals meeting the requirements described in the RFQ/P.
Selection of Design-Builder
SECTION 3 – TENTATIVE SCHEDULE OF EVENTS
The following Tentative Schedule of Events represents The City of Smyrna’s best estimate of the procurement schedule. All times indicated are prevailing times in Smyrna, Georgia. The City of Smyrna reserves the right to adjust the schedule as it deems necessary.
TENTATIVE SCHEDULE OF EVENTS
a. City of Smyrna issues Public Notice Advertisement 11/13/2026 ----------
b. Industry Forum – Virtual (pre-recorded presentation) 11/27/2027 8:00 am
c. City of Smyrna issues RFQ 3/5/2027 -----------
d. Deadline for submission of SOQ 4/2/2027 5:00 pm
e. City issues the notice to finalists 4/16/2027 11:00 am
f. City issues RFP to finalists 4/30/2027 10:00 am
g. Receipt of Proposals from Finalists 5/28/2027 -----------
h. Bid Opening 5/31/2027 9:00 am
i. Smyrna letting 6/14/2027 -----------
A virtual industry forum will be conducted for the Project on the dates noted above. During the industry forum presentation, the City of Smyrna will provide information regarding the Project’s delivery goals, anticipated scope, anticipated procurement process, and potential risks. There is no limitation on the number of participants. This is a pre-recorded presentation, and participants will not be provided with the opportunity to ask questions. Any information provided by the City of Smyrna shall be considered as informational only and is subject to change. For additional information regarding the virtual industry forum, visit the website, https://www.bidnetdirect.com/georgia/cityofsmyrna and select project folder: 0018265 – SR 280 (South Cobb Drive) Improvements Project. Interested parties can preregister at https://docs.google.com/forms/d/e/1FAIpQLSeHPOLphntosR94khELtn5ZTo_CPArX215IweLhjKNRF- FhDg/viewform for access to the pre-recorded presentation on the date noted above, 24-hours prior to its posting on the City of Smyrna Innovative Projects website at:
https://www.bidnetdirect.com/georgia/cityofsmyrna
Page 4 of 4 PNA-006-11132026DB
SECTION 4 – ANTICIPATED KEY TEAM LEADER REQUIREMENTS
As part of the qualifications package, the proposing respondent will be required to submit resumes for each of the key team leaders identified below. The City of Smyrna reserves the right to modify key team leaders, as well as other schedule procurement information detailed in this PNA, at any time in its sole discretion.
Anticipated Key Team Leaders for DB:
DB Project Manager Preconstruction Project Manager Construction Project Manager Utility Liaison
SECTION 5 – SELECTION CRITERIA
As part of the qualifications package, the proposing Design-Builder and/or their subconsultant team member must be prequalified in the Area Class(es) identified below for the work they perform on the project.
The Land Design Consultant for the Design-Builder MUST be prequalified by Georgia DOT in the Area Class(es) Below.
Number Area Class
3.02 Urban Roadway Design
3.03 Complex Urban Roadway Design
The team members (the Lead Contractor, the lead design Consultant, and/or one more of the subconsultants team members or any subcontractor) MUST be prequalified by Georgia DOT in each of the Area Classes listed below:
Number Area Class 1.06(a) NEPA Documentation 1.06(b) History 1.06(c) Air Studies 1.06(d) Noise Studies 1.06(e) Ecology 1.06(f) Archaeology 1.06(g) Freshwater Aquatic Surveys 1.06(h) Bat Surveys
1.07 Attitude, Opinion and Community Value Studies
1.10 Traffic Projections
3.06 Traffic Operations Studies
3.07 Traffic Operations Design
3.08 Landscape Architecture
3.09 Traffic Control Systems Analysis, Design and Implementation
3.10 Utility Coordination
3.12 Hydraulic and Hydrological Studies (Roadway)
5.01 Land Surveying
5.02 Engineering Surveying
5.08 Overhead/Subsurface Utility Engineering (SUE)
6.01(a) Soil Survey Studies
6.05 Hazardous Waste Site Assessment Studies
8.01 Construction Engineering
9.01 Erosion, Sedimentation and Pollution Control Plan (ESPCP) Preparation
9.02 Rainfall and Runoff Reporting
9.03 Field Inspections for Compliance of Erosion and Sedimentation Control Device
Installations
File details come from the government source that posted it. Updated .