PN 0070_2267 Addendum 1.pdf

PDF 41 KB Posted

Attached to
PN0070-2267 Fulford Ctr HVAC Replacement
Solicitation number
PE-57200-RFQ-2024-000000004
Issued by
Douglas County, Georgia

About this file

This document is an addendum to the Fulford Center HVAC Replacement project at East Georgia State College. The addendum provides updates to the project specifications, including requirements to provide float switches in the auxiliary drain pan, replace duct insulation in the mechanical room, protect refrigerant lines with metal shields, and replace supply and return air sensors as part of the HVAC unit replacement. The addendum also confirms that pressed connection fittings for refrigerant piping are allowed, and provides updates to the electrical requirements.

The overall project seeks proposals from qualified contractors to provide a new air handler and condensing unit to replace aging equipment and improve air quality through the addition of bi-polar ionization and better filtration. The work is being procured by the Board of Regents of the University System of Georgia on behalf of East Georgia State College, and covers facilities located in Emanuel County, Georgia.

View the file

Other files

File Type Posted
Bid Tabulation Sheet (Fulford Center HVAC Rep.xlsx XLSX spreadsheet
EGSC Fulford HVAC Drawings _ Final.pdf PDF
EGSC Fulford HVAC Specs _ Final.pdf PDF
Bid Tabulation Sheet (Modernization Academic .xlsx XLSX spreadsheet
NOIA 0070 2267_0001.pdf PDF
Pre Bid Sign In Sheet PN 0070_2267.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

E:\E GA College Fulford Center HVAC -23088.00\Admin\Addendum\Addendum 1.docx

Chatham Engineering Company, LLC

109 Park of Commerce Drive, Suite 6 • Savannah, GA 31405-1396

T 912•238•2400 f 912•238•2412

East Georgia State College

0070-2267 Fulford Center HVAC Replacement

ADDENDUM 1

1. On sheet M1.1, Note 8 add to the note that the contractor shall provide 4 float switches in the auxiliary drain pan. One in each corner.

2. On sheet M1.1, add new note D6. Remove all duct insulation in mechanical room and replace with new.

3. On sheet M1.1, Note 6 add to the note for the refrigerant lines exposed in the Storage room shall be protected with a metal shield.

4. On sheet M1.1, add new note 11. Siemens controls to replace supply air and return air sensors in the system as part of the unit replacement.

5. Question was asked if pressed connection fittings for refrigerant piping would be allowed.

They are allowed as long as the installation follows the instructions from the manufacturer and passes a leak test.

6. On sheet M1.1, Note E3 remove reference to extend 2” C w/ 3 No. 2/0,1 No. 6(G) and change to reuse existing 3 No. 3/0,1 No. 6(G).