Plung Pool Repairs Salt Creek NE Drawings.pdf
PDF 26 MB Posted
- Attached to
- Plunge Pool Repairs at Salt Creek, NE
- Solicitation number
- W9128F20B0020
About this file
This federal contract opportunity solicitation seeks bids for repairs to plunge pools and outlet channels damaged in the 2019 flood event along Salt Creek in Nebraska. The scope of work involves grading and reshaping sloughed banks, placing riprap and bedding material around plunge pool perimeters, removing accumulated sediment and debris, seeding disturbed areas, and drawing down reservoir levels prior to construction to ensure adequate downstream channel capacity. A site visit is scheduled for August 27, 2020 at 10:00am local time. The construction duration is 180 calendar days with an estimated budget between $1,000,000 to $5,000,000. All solicitation documents will be posted to beta.sam.gov. The issuing agency is the Department of the Army Corps of Engineers Omaha District. The solicitation number is W9128F20B0020 and bids are due in response to an opportunity posted for plunge pool repairs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Abstract Plunge Pool Repair Salt Creek NE 20B0020.pdf | ||
| Am0002.pdf | ||
| Am0002_SC24_G-008.pdf | ||
| Am0001.pdf | ||
| Plunge Pool Repairs Salt Creek NE Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CULLIN.ROSS.J.13666021
2020.08.10 13:27:55 -05'00'
MELLIGER.JOSHUA.
JAMES.1385431216
Digitally signed by
MELLIGER.JOSHUA.JAMES.138
5431216 Date: 2020.08.10 09:26:26 -05'00'
TAYLOR.RICHAR
D.J.1220810204
Digitally signed by
TAYLOR.RICHARD.J.1220810204
Date: 2020.08.10 14:36:19 -05'00'
BARRY.A
NDREW.L
.1252332
Digitally signed by
BARRY.ANDRE
W.L.1252332479 Date: 2020.08.06 09:28:52 -05'00'
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
G
2 3 4 5 6 7 8 9 10
NUMBER
IDENTIFICATION
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
P B
F
IL
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
%PRODUCTION DATA 4%%PRODUCTION DATA 3%%PRODUCTION DATA 2%
%PRODUCTION DATA 1%
GI002
IN
D
E X
M - 2 0 1
INDEX LEGEND:
GENERAL
INDEX
CIVIL
S C
G I0
.d g n
SHEET SEQUENCE NUMBER
w/ Level 2 Designator
DISCIPLINE DESIGNATOR
2. DISCIPLINE DESIGNATORS:1. SHEET IDENTIFICATION NUMBERS:
R
T
E
M
D
P
F
Q
I
A
S
L
C
B
V
H
G
RESOURCE
TELECOMMUNICATIONS
ELECTRICAL
MECHANICAL
PROCESS
PLUMBING
FIRE PROTECTION
EQUIPMENT
INTERIORS
ARCHITECTURAL
STRUCTURAL
LANDSCAPE
CIVIL
GEOTECHNICAL
SURVEY / MAPPING
HAZARDOUS MATERIALS
GENERAL
Designator)
RELEASE 3.0 for Level 2
(see A/E/C CADD STANDARD
SHEET TYPE DESIGNATOR
3. SHEET TYPE DESIGNATORS:
FOR INFORMATION ONLY
3D REPRESENTATIONS
USER DEFINED
USER DEFINED
SCHEDULES & DIAGRAMS
DETAILS
LARGE-SCALE VIEWS
SECTIONS
ELEVATIONS
PLANS
GENERAL
F
TYPICAL RIPRAP CROSS SECTION AND ELEVATION - SITE 13 - TWIN LAKES DAMC-206SC24_C-206.DGN
TYPICAL RIPRAP CROSS SECTION AND ELEVATION - SITE 12 - CONESTOGA DAMC-205SC24_C-205.DGN
TYPICAL RIPRAP CROSS SECTION AND ELEVATION - SITE 10 - YANKEE HILL DAMC-204SC24_C-204.DGN
TYPICAL RIPRAP CROSS SECTION AND ELEVATION - SITE 9 - STAGECOACH DAMC-203SC24_C-203.DGN
TYPICAL RIPRAP CROSS SECTION AND ELEVATION - SITE 8 - WAGON TRAIN DAMC-202SC24_C-202.DGN
TYPICAL RIPRAP CROSS SECTION AND ELEVATION - SITE 4 - BLUESTEM DAMC-201SC24_C-201.DGN
FINAL GRADING PLAN - SITE 13 - TWIN LAKES DAMC-106SC24_C-106.DGN
FINAL GRADING PLAN - SITE 12 - CONESTOGA DAMC-105SC24_C-105.DGN
FINAL GRADING PLAN - SITE 10 - YANKEE HILL DAMC-104SC24_C-104.DGN
FINAL GRADING PLAN - SITE 9 - STAGECOACH DAMC-103SC24_C-103.DGN
FINAL GRADING PLAN - SITE 8 - WAGON TRAIN DAMC-102SC24_C-102.DGN
FINAL GRADING PLAN - SITE 4 - BLUESTEM DAMC-101SC24_C-101.DGN
EXISTING CONDITIONS - SITE 13 - TWIN LAKES DAMV-106SC24_V-106.DGN
EXISTING CONDITIONS - SITE 12 - CONESTOGA DAMV-105SC24_V-105.DGN
EXISTING CONDITIONS - SITE 10 - YANKEE HILL DAMV-104SC24_V-104.DGN
EXISTING CONDITIONS - SITE 9 - STAGECOACH DAMV-103SC24_V-103.DGN
EXISTING CONDITIONS - SITE 8 - WAGON TRAIN DAMV-102SC24_V-102.DGN
EXISTING CONDITIONS - SITE 4 - BLUESTEM DAMV-101SC24_V-101.DGN
GENERAL NOTES AND CONSTRUCTION NOTESGR001SC24_GR001.DGN
GENERAL PLAN AND SURVEY CONTROL DATA - SITE 13 - TWIN LAKES DAMG-013SC24_G-013.DGN
GENERAL PLAN AND SURVEY CONTROL DATA - SITE 12 - CONESTOGA DAMG-012SC24_G-012.DGN
GENERAL PLAN AND SURVEY CONTROL DATA - SITE 10 - YANKEE HILL DAMG-011SC24_G-011.DGN
GENERAL PLAN AND SURVEY CONTROL DATA - SITE 9 - STAGECOACH DAMG-010SC24_G-010.DGN
GENERAL PLAN AND SURVEY CONTROL DATA - SITE 8 - WAGON TRAIN DAMG-009SC24_G-009.DGN
GENERAL PLAN AND SURVEY CONTROL DATA - SITE 4 - BLUESTEM DAMG-008SC24_G-008.DGN
VICINITY MAP - SITE 13 - TWIN LAKES DAMG-007SC24_G-007.DGN
VICINITY MAP - SITE 12 - CONESTOGA DAMG-006SC24_G-006.DGN
VICINITY MAP - SITE 10 - YANKEE HILL DAMG-005SC24_G-005.DGN
VICINITY MAP - SITE 9 - STAGECOACH DAMG-004SC24_G-004.DGN
VICINITY MAP - SITE 8 - WAGON TRAIN DAMG-003SC24_G-003.DGN
VICINITY MAP - SITE 4 - BLUESTEM DAMG-002SC24_G-002.DGN
PROJECT LOCATIONS AND AERIAL VIEWSG-001SC24_G-001.DGN
INDEXGI002SC24_GI002.DGN
COVER SHEETGI001SC24_GI001.DGN
DESCRIPTIONSHEET NUMBERDESIGN FILE
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
PROJECT LOCATION MAP
C
G -0
.d g n
BLUESTEM DAM
AERIAL VIEW OF SITE 04
WAGON TRAIN DAM
AERIAL VIEW OF SITE 08
STAGECOACH DAM
AERIAL VIEW OF SITE 09
CONESTOGA DAM
AERIAL VIEW OF SITE 12
TWIN LAKES DAM
AERIAL VIEW OF SITE 13
YANKEE HILL DAM
AERIAL VIEW OF SITE 10
SITE 13
LOCATION
PROJECT
SITE 12
LOCATION
PROJECT
SITE 10
LOCATION
PROJECT
SITE 04
LOCATION
PROJECT
SITE 09
LOCATION
PROJECT
SITE 08
LOCATION
PROJECT
(NOT TO SCALE) G-001
P R
O J E
C T L
O C
A T
IO
N S A
N D A
E R
IA
L V
IE
W
N
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-002
V
IC
IN
IT
Y M
A P
SCALE: 1" = 2000'
0 2000'2000'1000'
N
VICINITY MAP - SITE 04
S
IT
E
B
L U
E S
T E
M D
A M
SITE 04
LOCATION
PROJECT
S C
G -0
.d g n
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-003
IC
IN
IT
Y M
A P
SCALE: 1" = 2000'
0 2000'2000'1000'
N
VICINITY MAP - SITE 08
SITE 08
LOCATION
PROJECT
S
IT
E
W
A G
O N T
R A
IN
D
A M
S C
G -0
.d
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-004
IC
IN
IT
Y M
A P
SCALE: 1" = 2000'
0 2000'2000'1000'
N
VICINITY MAP - SITE 09
SITE 09
LOCATION
PROJECT
S
IT
E
S
T A
G E
C O
A C
H D
A M
S C
G -0
.d
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-005
IC
IN
IT
Y M
A P
SCALE: 1" = 2000'
0 2000'2000'1000'
N
VICINITY MAP - SITE 10
SITE 10
LOCATION
PROJECT
S
IT
E
Y
A N
K E
E H
IL
L D
A M
S C
G -0
.d
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-006
IC
IN
IT
Y M
A P
SCALE: 1" = 2000'
0 2000'2000'1000'
N
VICINITY MAP - SITE 12
SITE 12
LOCATION
PROJECT
S
IT
E
C
O N
E S
T O
G A D
A M
S C
G -0
.d
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-007
IC
IN
IT
Y M
A P
SCALE: 1" = 2000'
0 2000'2000'1000'
N
VICINITY MAP - SITE 13
SITE 13
LOCATION
PROJECT
S
IT
E
T
W
IN
L
A K
E S D
A M
S C
G -0
.d
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-008
E
N E
R A
L P
L A
N A
N D S
U R
V E
Y C
O N
T R
O L D
A T
A
SCALE: 1" = 300'
0 300'300' 150'
GENERAL PLAN & SURVEY CONTROL DATA - SITE 04
EASTING (FT)NORTHING (FT)AREA
CREST ROAD
EMBANKMENT
PT-1A
BOUNDARY
USACE PROPERTY
INTAKE STRUCTURE
OUTLET WORKS
STAGING AREA B
CONTRACTOR
WORKS CONDUIT
CL OUTLET
SHEET GR001
SEE NOTE 8 ON
HAUL ROUTE
STAGING AREA A
CONTRACTOR
CONSTRUCTION AREA
GENERAL
SEE NOTE 4 ON SHEET GR001
DAM SAFETY INSTRUMENTATION
CONTRACTOR SHALL PROTECT ALL
V-SALT-4
PT-2A
S
IT
E E
N T
R A
N C
E
W SPRAGUE ROAD
S W
N
D S
T R
E E
T
SHEET GR001
SEE NOTE 8 ON
BORROW AREA A
SHEET GR001
SEE NOTE 8 ON
BORROW AREA B
EMBANKMENT
BLUESTEM DAM
BLUESTEM LAKE
THE TABLE BELOW.
(NAVD88). THEY ARE BASED ON CONTROL POINT PT-1A. VERTICAL AND HORIZONTAL CONTROL DATA ARE SHOWN IN
ELEVATIONS ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN VERTICAL DATUM OF 1988
STATE PLANE COORDINATE SYSTEM FOR NEBRASKA (2600). THEY ARE BASED ON CONTROL POINT PT-1A.
COORDINATES ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN DATUM OF 1983 (NAD 83)
HORIZONTAL AND VERTICAL CONTROL POINTS (PT-1A, PT-2A AND V-SALT-4) ARE SHOWN IN THE GENERAL PLAN. GRID
1. PROJECT ELEVATIONS:
GENERAL NOTES:
2532326.95308063.27
2532336.07307895.52
2532610.67307910.45
2532601.55308078.20BORROW AREA B
2532835.41306783.30
2533034.96306679.34
2533081.16306768.02
2532881.62306871.99BORROW AREA A
2532109.77307121.54
2532206.34307236.56
2532118.45307279.96
2532032.73307125.88STAGING AREA B
2531677.50306472.18
2531643.70306501.69
2531556.64306375.05
2531601.83306334.45STAGING AREA A
2531491.73306296.91
2531587.12306224.65
2531640.59306289.43
2531551.57306369.40GENERAL CONSTRUCTION AREA
1334.9942529222.966306216.727V-SALT-4
1" IRON ROD IN CASING1338.6942532113.761307341.453PT-2A
1" IRON ROD IN CASING1340.0122530182.268304979.420PT-1A
DESCRIPTIONELEVATION (FT)EASTING (FT)NORTHING (FT)NAME
NAVD88
5. AREAS SHOWN BELOW MAY BE SLIGHTLY ADJUSTED AS NEEDED WITH APPROVAL OF THE COR.
4. YELLOW LINE REPRESENTS APPROXIMATE USACE PROPERTY BOUNDARY.
3. ACQUIRE ALL REQUIRED LOCAL, STATE, AND FEDERAL PERMITS FOR HAUL OR MATERIAL DELIVERY.
2. CHECK ALL BRIDGE DESIGN LOAD RATINGS ALONG ACCESS ROUTE TO JOB SITE AND DO NOT OVERLOAD BRIDGES.
S C
G -0
.d g n
S
IT
E
B
L U
E S
T E
M L
A K
E D
A M
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-009
E
N E
R A
L P
L A
N A
N D S
U R
V E
Y C
O N
T R
O L D
A
SITE ENTRANCE
GENERAL PLAN & SURVEY CONTROL DATA - SITE 08
EASTING (FT)NORTHING (FT)AREA
CREST ROAD
EMBANKMENT
PT-2A
BOUNDARY
USACE PROPERTY
INTAKE STRUCTURE
OUTLET WORKS
STAGING AREA B
CONTRACTOR
WORKS CONDUIT
CL OUTLET
WAGON TRAIN LAKE
SHEET GR001
SEE NOTE 8 ON
HAUL ROUTE
STAGING AREA A
CONTRACTOR
THE TABLE BELOW.
(NAVD88). THEY ARE BASED ON CONTROL POINT PT-2A. VERTICAL AND HORIZONTAL CONTROL DATA ARE SHOWN IN
ELEVATIONS ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN VERTICAL DATUM OF 1988
STATE PLANE COORDINATE SYSTEM FOR NEBRASKA (2600). THEY ARE BASED ON CONTROL POINT PT-2A.
COORDINATES ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN DATUM OF 1983 (NAD 83)
HORIZONTAL AND VERTICAL CONTROL POINTS (PT-1A AND PT-2A) ARE SHOWN IN THE GENERAL PLAN. GRID
1. PROJECT ELEVATIONS:
GENERAL NOTES:
S
IT
E
W
A G
O N T
R A
IN
L
A K
E D
A M
STATE HWY 55AWAGON TRAIN ROAD
EMBANKMENT
WAGON TRAIN DAM
S th S
T R
E E
TS
th S
T R
E E
T
PT-1A
AREA
MARSHY
WET
SHEET GR001
SEE NOTE 8 ON
BORROW AREA
CONSTRUCTION AREA
GENERAL
SEE NOTE 4 ON SHEET GR001
DAM SAFETY INSTRUMENTATION
CONTRACTOR SHALL PROTECT ALL
2588728.03305126.82
2588758.21305078.72
2588779.78305024.99
2588782.21304963.46
2588855.54304941.71
2588892.07305001.26
2588978.19305013.47
2589020.85305052.13
2589009.18305123.85
2588992.42305190.10
2588863.32305192.04
2588765.18305170.55WET MARSHY AREA
2586605.27305739.30
2586615.47305519.54
2586915.15305533.46
2586904.94305753.22BORROW AREA
2589361.73305168.02
2589080.15305135.21
2589085.38305002.95
2589278.50305010.59STAGING AREA B
2588086.14305195.05
2588086.02305100.72
2588169.78305100.61
2588269.56305151.33
2588269.62305194.81STAGING AREA A
2587941.20305095.18
2588081.06305101.32
2588074.48305251.18
2587934.62305245.04GENERAL CONSTRUCTION AREA
5. AREAS SHOWN BELOW MAY BE SLIGHTLY ADJUSTED AS NEEDED WITH APPROVAL OF THE COR.
4. YELLOW LINE REPRESENTS APPROXIMATE USACE PROPERTY BOUNDARY.
3. ACQUIRE ALL REQUIRED LOCAL, STATE, AND FEDERAL PERMITS FOR HAUL OR MATERIAL DELIVERY.
2. CHECK ALL BRIDGE DESIGN LOAD RATINGS ALONG ACCESS ROUTE TO JOB SITE AND DO NOT OVERLOAD BRIDGES.
1" IRON ROD IN CASING1317.7432589949.360305320.413PT-2A
1" IRON ROD IN CASING1315.6722586861.606305504.382PT-1A
DESCRIPTIONELEVATION (FT)EASTING (FT)NORTHING (FT)NAME
NAVD88
S C
G -0
.d g
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-010
E
N E
R A
L P
L A
N A
N D S
U R
V E
Y C
O N
T R
O L D
A
GENERAL PLAN & SURVEY CONTROL DATA - SITE 09
EASTING (FT)NORTHING (FT)AREA
CREST ROAD
EMBANKMENT
PT-2A
PT-1A
BOUNDARY
USACE PROPERTY
INTAKE STRUCTURE
OUTLET WORKS
STAGING AREA B
CONTRACTOR
WORKS CONDUIT
CL OUTLET
AREA
CONSTRUCTION
GENERAL
STAGECOACH LAKE
SHEET GR001
SEE NOTE 8 ON
HAUL ROUTE
STAGING AREA A
CONTRACTOR
THE TABLE BELOW.
(NAVD88). THEY ARE BASED ON CONTROL POINT PT-1A. VERTICAL AND HORIZONTAL CONTROL DATA ARE SHOWN IN
ELEVATIONS ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN VERTICAL DATUM OF 1988
STATE PLANE COORDINATE SYSTEM FOR NEBRASKA (2600). THEY ARE BASED ON CONTROL POINT PT-1A.
COORDINATES ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN DATUM OF 1983 (NAD 83)
HORIZONTAL AND VERTICAL CONTROL POINTS (PT-1A AND PT-2A) ARE SHOWN IN THE GENERAL PLAN. GRID
1. PROJECT ELEVATIONS:
GENERAL NOTES:
PANAMA ROAD
EMBANKMENT
STAGECOACH DAM
S th S
T R
E E
T
SEE NOTE 4 ON SHEET GR001
DAM SAFETY INSTRUMENTATION
CONTRACTOR SHALL PROTECT ALL
5. AREAS SHOWN BELOW MAY BE SLIGHTLY ADJUSTED AS NEEDED WITH APPROVAL OF THE COR.
4. YELLOW LINE REPRESENTS APPROXIMATE USACE PROPERTY BOUNDARY.
3. ACQUIRE ALL REQUIRED LOCAL, STATE, AND FEDERAL PERMITS FOR HAUL OR MATERIAL DELIVERY.
2. CHECK ALL BRIDGE DESIGN LOAD RATINGS ALONG ACCESS ROUTE TO JOB SITE AND DO NOT OVERLOAD BRIDGES.
1" IRON ROD IN CASING1301.6162573402.558300135.434PT-2A
1" IRON ROD IN CASING1297.5612574665.174298024.837PT-1A
DESCRIPTIONELEVATION (FT)EASTING (FT)NORTHING (FT)NAME
NAVD88
S C
G -0
.d g n
2574557.25296753.04
2574559.22296949.06
2574419.55296918.26
2574420.34296782.26BORROW AREA
2574385.19297287.57
2574402.90297362.05
2574402.37297476.11
2574294.04297489.65
2574324.25297311.01
2574341.44297277.67
2574364.87297253.19STAGING AREA B
2574055.37299429.11
2574099.37299486.37
2574085.19299573.97
2574002.72299716.89
2573913.87299670.72STAGING AREA A
2573865.25299670.91
2573993.03299737.29
2573940.64299843.03
2573845.65299842.71
2573797.71299784.32GENERAL CONSTRUCTION AREA
SHEET GR001
SEE NOTE 8 ON
BORROW AREA
S
IT
E
S
T A
G E
C O
A C
H L
A K
E D
A
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-011
E
N E
R A
L P
L A
N A
N D S
U R
V E
Y C
O N
T R
O L D
A
SCALE: 1" = 200'
0 200'200' 100'
GENERAL PLAN & SURVEY CONTROL DATA - SITE 10
IT
E
Y
A N
K E
E H
IL
L D
A M
EASTING (FT)NORTHING (FT)AREA
CREST ROAD
EMBANKMENT
PT-2A
BOUNDARY
USACE PROPERTY
INTAKE STRUCTURE
OUTLET WORKS
WORKS CONDUIT
CL OUTLET
AREA
CONSTRUCTION
GENERAL S
W
T
H S
T R
E E
T
EMBANKMENT
YANKEE HILL DAM
YANKEE HILL LAKE
THE TABLE BELOW.
(NAVD88). THEY ARE BASED ON CONTROL POINT PT-1B. VERTICAL AND HORIZONTAL CONTROL DATA ARE SHOWN IN
ELEVATIONS ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN VERTICAL DATUM OF 1988
STATE PLANE COORDINATE SYSTEM FOR NEBRASKA (2600). THEY ARE BASED ON CONTROL POINT PT-1B.
COORDINATES ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN DATUM OF 1983 (NAD 83)
HORIZONTAL AND VERTICAL CONTROL POINTS (PT-2A AND PT-1B) ARE SHOWN IN THE GENERAL PLAN. GRID
1. PROJECT ELEVATIONS:
GENERAL NOTES:
2532707.53342955.79
2532837.38342961.99
2532833.57343041.89
2532703.72343035.70BORROW AREA B
2532961.15342263.07
2532870.20342348.82
2532805.03342279.69
2532895.98342193.95BORROW AREA A
2532600.21342621.20
2532536.99342685.26
2532467.24342616.42
2532530.46342552.36STAGING AREA B
2532380.14342951.78
2532351.54342993.88
2532305.11342985.43
2532274.63342964.73
2532313.97342906.83STAGING AREA A
2532305.14342985.40
2532351.54342993.88
2532418.04343054.53
2532337.17343143.19
2532270.68343082.54
2532257.97343037.12GENERAL CONSTRUCTION AREA
1" IRON ROD IN CASING1278.7242532562.292342447.650PT-1B
1" IRON ROD IN CASING1277.0812530259.985344941.403PT-2A
DESCRIPTIONELEVATION (FT)EASTING (FT)NORTHING (FT)NAME
NAVD88
5. AREAS SHOWN BELOW MAY BE SLIGHTLY ADJUSTED AS NEEDED WITH APPROVAL OF THE COR.
4. YELLOW LINE REPRESENTS APPROXIMATE USACE PROPERTY BOUNDARY.
3. ACQUIRE ALL REQUIRED LOCAL, STATE, AND FEDERAL PERMITS FOR HAUL OR MATERIAL DELIVERY.
2. CHECK ALL BRIDGE DESIGN LOAD RATINGS ALONG ACCESS ROUTE TO JOB SITE AND DO NOT OVERLOAD BRIDGES.
S
IT
E E
N T
R A
N C
E
PT-1B
SHEET GR001
SEE NOTE 8 ON
HAUL ROUTE
STAGING AREA A
CONTRACTOR
STAGING AREA B
CONTRACTOR
SHEET GR001
SEE NOTE 8 ON
BORROW AREA A
SHEET GR001
SEE NOTE 4 ON
INSTRUMENTATION
DAM SAFETY
PROTECT ALL
CONTRACTOR SHALL
SHEET GR001
SEE NOTE 8 ON
BORROW AREA B
DO NOT USE)
(DISTURBED -
PT-1A
S C
G -0
.d g
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-012
E
N E
R A
L P
L A
N A
N D S
U R
V E
Y C
O N
T R
O L D
A
0 300'300' 100'
GENERAL PLAN & SURVEY CONTROL DATA - SITE 12
EASTING (FT)NORTHING (FT)AREACREST ROAD
EMBANKMENT
BOUNDARY
USACE PROPERTY
INTAKE STRUCTURE
OUTLET WORKS STAGING AREA B
CONTRACTOR
WORKS CONDUIT
CL OUTLET
SEE NOTE 8 ON SHEET GR001
HAUL ROUTE
AREA
CONSTRUCTION
GENERAL
AREA A
STAGING
CONTRACTOR
S
IT
E
C
O N
E S
T O
G A D
A M
S W
T
H S
T R
E E
T U
S H
W Y
A
W PIONEERS BLVD
W PIONEERS BLVD
SITE ENTRANCE
CONESTOGA LAKE
PT-2B
SEE NOTE 8 ON SHEET GR001
BORROW AREA
EMBANKMENT
CONESTOGA DAM
THE TABLE BELOW.
(NAVD88). THEY ARE BASED ON CONTROL POINT PT-2B. VERTICAL AND HORIZONTAL CONTROL DATA ARE SHOWN IN
ELEVATIONS ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN VERTICAL DATUM OF 1988
STATE PLANE COORDINATE SYSTEM FOR NEBRASKA (2600). THEY ARE BASED ON CONTROL POINT PT-2B.
COORDINATES ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN DATUM OF 1983 (NAD 83)
HORIZONTAL AND VERTICAL CONTROL POINTS (PT-1A AND PT-2B) ARE SHOWN IN THE GENERAL PLAN. GRID
1. PROJECT ELEVATIONS:
GENERAL NOTES:
2512936.08353714.71
2513147.52353581.32
2513211.55353682.81
2513000.11353816.20BORROW AREA
2514169.17355300.55
2514174.16355408.44
2514024.32355415.37
2514019.33355307.49STAGING AREA B
2513924.30357251.38
2514129.29357253.08
2513922.22357501.37STAGING AREA A
2513879.09355034.89
2514093.80355023.73
2514105.74355253.42
2513891.03355264.58GENERAL CONSTRUCTION AREA
SEE NOTE 4 ON SHEET GR001
DAM SAFETY INSTRUMENTATION
CONTRACTOR SHALL PROTECT ALL
5. AREAS SHOWN BELOW MAY BE SLIGHTLY ADJUSTED AS NEEDED WITH APPROVAL OF THE COR.
4. YELLOW LINE REPRESENTS APPROXIMATE USACE PROPERTY BOUNDARY.
3. ACQUIRE ALL REQUIRED LOCAL, STATE, AND FEDERAL PERMITS FOR HAUL OR MATERIAL DELIVERY.
2. CHECK ALL BRIDGE DESIGN LOAD RATINGS ALONG ACCESS ROUTE TO JOB SITE AND DO NOT OVERLOAD BRIDGES.
BRASS-CAP
1" IRON ROD IN CASING1264.9362513877.833357766.926PT-2B
USACE BRASS CAP IN CONCRETE1263.1142513718.617354506.293BRASS-CAP
DESCRIPTIONELEVATION (FT)EASTING (FT)NORTHING (FT)NAME
NAVD88
S C
G -0
.d g n
SEE NOTE 4 ON SHEET GR001
DAM SAFETY INSTRUMENTATION
CONTRACTOR SHALL PROTECT ALL
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
G-013
E
N E
R A
L P
L A
N A
N D S
U R
V E
Y C
O N
T R
O L D
A
0 300'300' 100'
GENERAL PLAN & SURVEY CONTROL DATA - SITE 13
S
IT
E
T
W
IN
L
A K
E S D
A M
EASTING (FT)NORTHING (FT)AREA
TWIN LAKES
CREST ROAD
EMBANKMENT
PT-3A
PT-2A PT-4A
BOUNDARY
USACE PROPERTY
INTAKE STRUCTURE
OUTLET WORKS
STAGING AREA B
CONTRACTOR
WORKS CONDUIT
CL OUTLETSEE NOTE 8 ON SHEET GR001
BORROW AREA B
SEE NOTE 8 ON SHEET GR001
BORROW AREA A
HOLDREDGE ROAD
SEE NOTE 8 ON SHEET GR001
HAUL ROUTE
AREA
CONSTRUCTION
GENERAL
AREA A
STAGING
CONTRACTOR
THE TABLE BELOW.
(NAVD88). THEY ARE BASED ON CONTROL POINT PT-3A. VERTICAL AND HORIZONTAL CONTROL DATA ARE SHOWN IN
ELEVATIONS ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN VERTICAL DATUM OF 1988
STATE PLANE COORDINATE SYSTEM FOR NEBRASKA (2600). THEY ARE BASED ON CONTROL POINT PT-3A.
COORDINATES ARE REFLECTED IN US SURVEY FEET AND REFER TO THE NORTH AMERICAN DATUM OF 1983 (NAD 83)
HORIZONTAL AND VERTICAL CONTROL POINTS (PT-2A, PT-3A, AND PT-4A) ARE SHOWN IN THE GENERAL PLAN. GRID
1. PROJECT ELEVATIONS:
GENERAL NOTES:
EMBANKMENT
TWIN LAKES DAM
2483224.44376246.88
2483320.32376296.58
2483266.94376399.57
2483171.05376349.86BORROW AREA B
2484037.93375386.25
2484192.24375428.54
2484154.99375526.65
2484019.96375489.65BORROW AREA A
2485650.72375970.06
2485651.09376010.96
2485664.52376057.74
2485655.81376073.47
2485559.76376028.95
2485593.67375980.30STAGING AREA B
2485998.00376293.76
2485867.07376173.17
2485905.00376131.98
2486035.94376252.56STAGING AREA A
2485651.09376010.96
2485650.72375970.06
2485681.29375924.85
2485729.89375914.32
2485747.54375869.99
2485724.51375813.53
2485648.90375727.60
2485687.00375699.12
2485722.21375735.35
2485827.67375864.98
2485828.32375966.12
2485827.25376019.06
2485789.09376085.59
2485731.48376093.17
2485664.52376057.74GENERAL CONSTRUCTION AREA
SEE NOTE 4 ON SHEET GR001
DAM SAFETY INSTRUMENTATION
CONTRACTOR SHALL PROTECT ALL
5. AREAS SHOWN BELOW MAY BE SLIGHTLY ADJUSTED AS NEEDED WITH APPROVAL OF THE COR.
4. YELLOW LINE REPRESENTS APPROXIMATE USACE PROPERTY BOUNDARY.
3. ACQUIRE ALL REQUIRED LOCAL, STATE, AND FEDERAL PERMITS FOR HAUL OR MATERIAL DELIVERY.
2. CHECK ALL BRIDGE DESIGN LOAD RATINGS ALONG ACCESS ROUTE TO JOB SITE AND DO NOT OVERLOAD BRIDGES.
1" IRON ROD IN CASING1370.5612486169.233376489.006PT-4A
1" IRON ROD IN CASING1370.1322484084.892375522.991PT-3A
1" IRON ROD IN CASING1372.2292482932.279376362.374PT-2A
DESCRIPTIONELEVATION (FT)EASTING (FT)NORTHING (FT)NAME
NAVD88
S C
G -0
.d g n
INTERSTATE
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
GR001
E
N E
R A
L N
O T
E S A
N D C
O N
S T
R U
C T
IO
N N
O T
E S
S C
G R
.d
REPAIRED AT THE CONTRACTOR'S EXPENSE.
EQUIPMENT REACTIONS. SPECIAL PROVISIONS MUST BE APPROVED BY THE COR PRIOR TO USE. ANY DAMAGE TO THE CONDUIT MUST BE
OPERATE OVER THE CONDUIT UNLESS A MINIMUM COVER OF 4 FEET IS PROVIDED OR SPECIAL PROVISIONS ARE MADE TO DISPERSE THE
C3. SUPPORT ANY UNSUPPORTED OUTLET WORKS CONDUIT LENGTHS GREATER THAN 4 FEET DURING EXCAVATION. EQUIPMENT MUST NOT
00 EARTHWORK.
C2. COMPLETE THE WORK AT SITE 8 IN TWO CONSTRUCTION STAGES AS DESCRIBED IN PARAGRAPH 3.1 IN SPECIFICATION SECTION 31 00
APPROVED BY THE COR AND ACCORDING TO THE SPECIFICATIONS.
C1. EXCAVATED TOPSOIL AND FOUNDATION MATERIAL MUST BE SELECTIVELY STOCKPILED AND REUSED AS APPLICABLE FILL MATERIALS AS
CONSTRUCTION NOTES:
COMPLETION OF THE PROJECT.
ACCORDANCE WITH LOCAL REGULATIONS. REMOVE ALL MATERIAL AND EQUIPMENT NOT SPECIFIED AS REMAINING ON THE PROPERTY AT
20. KEEP THE JOB SITE CLEAN AND HAZARD-FREE. REMOVE ALL EXCAVATED MATERIAL, DEBRIS, AND RUBBISH FROM THE JOB SITE IN
DRAWING SIZE IS FURNISHED OR PLOTTED AND NOTIFY SUB-CONTRACTORS REGARDING THE ABOVE INFORMATION.
19. ALL SCALES SHOWN ON THE DRAWINGS ARE BASED ON A STANDARD DRAWING SIZE OF 22" X 34". ADJUST THE SCALES IF ANY OTHER
MODIFICATION TO THE DESIGN.
PART OF THE WORK. IMMEDIATELY NOTIFY THE COR OF ANY SUBSURFACE OR OTHER SITE CONDITIONS ENCOUNTERED THAT WOULD REQUIRE
18. MODIFICATIONS MAY BE REQUIRED TO SUIT JOB SITE DIMENSIONS OR CONDITIONS, AND SUCH MODIFICATIONS MUST BE INCLUDED AS
17. ASTM SPECIFICATIONS NOTED ON THE CONSTRUCTION DOCUMENTS WILL BE OF THE LATEST REVISION.
THE INDICATED STAGING AND CONSTRUCTION AREAS IS NOT PERMITTED, UNLESS NOTED OTHERWISE OR APPROVED BY THE COR.
16. THE EXTENTS OF ALL SITE WORK MUST BE AS INDICATED IN THE CONSTRUCTION DOCUMENTS. EXCAVATION OR DISTURBANCE BEYOND
FIRM NAME, ADDRESS, TELEPHONE, FAX, POINT OF CONTACT, AND RESPONSIBILITIES RELATED TO THE PROJECT.
15. PROVIDE USACE WITH A LIST OF ALL SUBCONTRACTORS WHO WILL BE PERFORMING WORK ON THE PROJECT. THE LIST MUST INCLUDE
AND PROCEDURES AND FOR COORDINATING ALL PORTIONS OF THE WORK UNDER THIS CONTRACT.
14. SUPERVISE AND DIRECT THE WORK, AND BE SOLELY RESPONSIBLE FOR ALL CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES
GENERAL NOTES: (CONTINUED)
WORKING HOURS.
INCLUDING SAFETY OF ALL PERSONS AND PROPERTY. THIS REQUIREMENT MUST APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL
13. ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION OF THIS PROJECT
BY THE CONTRACT DOCUMENTS.
12. RECEIVE, IN WRITING, AUTHORIZATION TO PROCEED BEFORE STARTING WORK ON ANY ITEM NOT CLEARLY DEFINED OR IDENTIFIED
11. BRING ANY DISCREPANCIES TO THE ATTENTION OF THE COR PRIOR TO PROCEEDING WITH THE WORK.
TO PROCEEDING WITH CONSTRUCTION.
AND DIMENSIONS SHOWN IN CONTRACT DOCUMENTS. CONFIRM THAT THE WORK MAY BE ACCOMPLISHED AS SHOWN ON THE DRAWINGS PRIOR
10. VISIT THE JOB SITES PRIOR TO PROCEEDING WITH CONSTRUCTION AND BE RESPONSIBLE FOR FAMILIARITY WITH FIELD CONDITIONS
DOCUMENTS.
9. FURNISH ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY TO COMPLETE ALL WORK AS INDICATED IN THE CONSTRUCTION
EARTHWORK.
BORROW AREAS MUST MEET THE REQUIREMENT OF COHESIVE MATERIALS AS SPECIFIED IN PARAGRAPH 1.2.3 IN SPECIFICATION 31 00 00
GRADING, SEED AND MULCH THE BORROW AREAS WITH SEED MIX "B" AND MULCH AS INDICATED IN SPECIFICATION 32 92 19 SEEDING.
AWAY FROM PERTINENT STRUCTURES AS INDICATED IN PARAGRAPH 3.7 IN SPECIFICATION 31 00 00. UPON COR APPROVAL OF THE
11 00 CLEARING AND GRUBBING. UPON COMPLETION OF CONSTRUCTION, BORROW AREAS MUST BE GRADED TO PROVIDE PROPER DRAINAGE
PROPERTY. AREAS USED TO OBTAIN BORROW MATERIAL MUST BE CLEARED AND GRUBBED IN ACCORDANCE WITH SPECIFICATION SECTION 31
SITE 8, 1294.6 SITE 9, 1271.7 SITE 10, 1260.9 SITE 12, AND 1364.2 SITE 13. ALL BORROW AREAS ARE LOCATED ON GOVERNMENT
MUST NOT OCCUR FOR THESE LOCATIONS BELOW THE FOLLOWING NAVD88 U.S. SURVEY FEET ELEVATIONS: 1334.2 AT SITE 4, 1312.9
RESERVOIR RIM" WITHIN BORROW AREAS LOCATED ADJACENT TO WHERE THE EMBANKMENT TIES INTO HIGH GROUND, BORROW EXCAVATION
COORDINATE ACCESS TO AND THE USE OF ALL BORROW AREAS. TO ELIMINATE POTENTIAL DETRIMENTAL EFFECTS FROM "LOWERING THE
:BORROW AREAS AND HAUL ROUTES8.
FOR GROUND SURFACE AND PIPE INVERT. PROVIDE THE AS-BUILT SURVEY DATA IN NAVD 88, U.S. SURVEY FEET UNITS.
SURVEY FEET UNITS. THE VERTICAL LOCATION OF ALL FEATURES COMPLETED AS PART OF THIS CONTRACT MUST INCLUDE ELEVATIONS
COORDINATES UTILIZING THE NORTH AMERICAN DATUM OF 1983 (NAD83) STATE PLANE COORDINATE SYSTEM FOR NEBRASKA (2600), U.S.
OF THIS CONTRACT INCLUDING BUT NOT LIMITED TO THE CONDUIT, FILTER, MANHOLES, AND PIEZOMETERS. PROVIDE SURVEY IN
AS INDICATED IN SPECIFICATION SECTION 01 78 39.00 24. SURVEY THE HORIZONTAL LOCATION OF ALL FEATURES COMPLETED AS PART
SUBMIT AS-BUILT DRAWINGS AND ASSOCIATED CADD FILES DEPICTING ACTUAL AS-BUILT CONDITIONS OF THE COMPLETED CONSTRUCTION
:AS- BUILT DRAWINGS AND SPECIFICATIONS7.
BY THE COR.
STOCKPILE CONSTRUCTION MATERIALS ONLY IN THE WORK AREAS, STOCKPILE AREAS, STAGING AREAS, OR IN OTHER AREAS DESIGNATED
:STOCKPILES6.
TO BEGINNING WORK.
PROTECT FROM DAMAGE ALL UTILITIES WITHIN AND IN THE VICINITY OF THE WORK AREAS. LOCATE AND VERIFY ALL UTILITIES PRIOR
:UTILITIES5.
ANY DAMAGE OR LOSS OF THESE FEATURES MUST BE REPAIRED OR REPLACED AT THE CONTRACTOR'S EXPENSE.
INSTRUMENTATION AND PROJECT FEATURES WITHIN AND IN THE VICINITY OF THE CONTRACT WORK AREAS PRIOR TO BEGINNING WORK.
WORK. THE LOCATION OF THESE FEATURES ARE SHOWN ON THE DRAWINGS OR WILL BE IDENTIFIED BY THE COR. MARK ALL
INSTRUMENTATION, OTHER DAM SAFETY INSTRUMENTATION, OUTLET WORKS CONDUITS, DRAIN PIPES, AND ROADWAYS IN THE AREAS OF
EXCEPT AS INDICATED IN THE CONSTRUCTION DRAWINGS, PROTECT FROM DAMAGE ALL PIEZOMETER PIPES, MOVEMENT MARKERS, SEISMIC
:INSTRUMENTATION AND EXISTING PROJECT FEATURES4.
SET FENCES BACK A MINIMUM OF 12 FEET FROM EXCAVATIONS. INSTALLATION OF TEMPORARY FENCE MUST BE APPROVED BY THE COR.
WITH ORANGE PLASTIC CONSTRUCTION FENCING AND SIGNAGE AS DESCRIBED IN THE SPECIFICATIONS AND AS DIRECTED BY THE COR.
FENCE OFF ALL WORK AREAS TO PREVENT ACCESS BY THE GENERAL PUBLIC. SECURE THE PERIMETER OF EACH INDIVIDUAL WORK AREA
:FENCING3.
MUST BE APPROVED BY THE COR PRIOR TO USE.
UTILIZE ONLY THE STAGING AREAS SHOWN ON SHEETS G-008 THROUGH G-013. ANY ADDITIONAL AREAS UTILIZED BY THE CONTRACTOR
:CONTRACTOR STAGING AREAS2.
ROUTE PHOTOGRAPHS MUST BE TAKEN FOR EACH BORROW AREA USED.
PRIOR TO BEGINNING WORK. PRE-CONSTRUCTION AND POST-CONSTRUCTION HAUL ROUTE CENTERLINE PROFILE GROUND SURVEYS AND HAUL
REQUIRED BY THE COR. HAUL ROAD LOCATIONS TO AND FROM BORROW LOCATIONS AND/OR STOCKPILES MUST BE APPROVED BY THE COR
THE DAMS AS MUCH AS PRACTICABLE FOR HAUL ROUTES. SPECIFIC APPROVAL TO USE THE CREST OF THE DAM AS A HAUL ROUTE IS
WORK AS INDICATED IN PARAGRAPH 1.6.2 IN SPECIFICATION SECTION 31 00 00. UTILIZE THE DAM GROINS AND DOWNSTREAM TOE OF
THE PROPERTY ARE NOT REQUIRED. RE-ESTABLISH TEMPORARY HAUL ROADS TO PRECONSTRUCTION CONDITIONS UPON COMPLETION OF THE
ENTERING OR LEAVING THE WORK AREAS. ALL WORK AREAS ARE ON GOVERNMENT PROPERTY. ACQUISITION OF RIGHTS-OF-ENTRY TO ENTER
CONTRACTING OFFICER'S REPRESENTATIVE (COR). SECURE ALL ACCESS POINTS EACH TIME THEY ARE USED FOR VEHICLES/EQUIPMENT
ACCESS THE CONTRACT WORK AREAS AS INDICATED ON SHEETS G-008 THROUGH G-013, UNLESS OTHERWISE APPROVED BY THE
:ACCESS ROUTE AND HAUL ROADS1.
GENERAL NOTES:
M
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
V-101
E X
IS
T
IN
G C
O N
D
IT
IO
SURVEY NOTES
IT
E
B
L U
E S
T E
M D
A M
PILE BENTS
SCALE: 1" = 10'
0 10'10' 5'
S C
V -1
.d g
ACCESS MANHOLE
LEGEND
MAJOR CONTOUR
MINOR CONTOUR
PILING
BOTTOM OF DITCH
EXISTING RIPRAP
SIGNPOST
TOP OF SCARP
TOP OF SCARP
OUTLET WORKS CONDUIT
CONDUIT CENTERLINE
SURFACE IS UNKNOWN, FIELD VERIFY.
6. EDGE OF EXISTING RIPRAP BENEATH WATER
5. COMBINED SCALE FACTOR 0.999713801.
4. CONTOUR INTERVAL IS 1 US SURVEY FOOT.
METHODS. FIELD SURVEY DATE: NOVEMBER 2019.
3. TOPOGRAPHY IS DERIVED FROM GPS/RTK SURVEY
G-008.
BASED ON CONTROL POINT PT-1A. SEE SHEET
VERTICAL DATUM 1988 (NAVD 88). THEY ARE
FEET AND REFER TO THE NORTH AMERICAN
2. ELEVATIONS ARE REFLECTED IN US SURVEY
SHEET G-008.
THEY ARE BASED ON CONTROL POINT PT-1A. SEE
SYSTEM FOR: NEBRASKA STATE PLANE (2600).
DATUM OF 1983 (NAD83) STATE PLANE COORDINATE
SURVEY FEET AND REFER TO THE NORTH AMERICAN
1. GRID COORDINATES ARE REFLECTED IN US
EXISTING CONDITIONS - SITE 04
LEFT (NORTHEAST) SLOPE
SITE 04 PLUNGE POOL
SITE 04 PLUNGE POOL
SLOUGH AREA
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
M
V-102
X
IS
T
IN
G C
O N
D
IT
IO
E
W
A G
O N T
R A
IN
D
A M
SCALE: 1" = 15'
0 15'15' 10'
MAJOR CONTOUR
MINOR CONTOUR
PILING
BOTTOM OF DITCH
EXISTING RIPRAP
CONDUIT CENTERLINE
ACCESS MANHOLE
PILE BENTS
OUTLET WORKS CONDUIT
TOP OF SCARP
S C
V -1
.d g n
SITE 08 PLUNGE POOL
EXISTING CONDITIONS - SITE 08
SURFACE IS UNKNOWN, FIELD VERIFY.
6. EDGE OF EXISTING RIPRAP BENEATH WATER
5. COMBINED SCALE FACTOR 0.999716813.
4. CONTOUR INTERVAL IS 1 US SURVEY FOOT.
METHODS. FIELD SURVEY DATE: NOVEMBER 2019.
3. TOPOGRAPHY IS DERIVED FROM GPS/RTK SURVEY
G-009.
BASED ON CONTROL POINT PT-2A. SEE SHEET
VERTICAL DATUM 1988 (NAVD 88). THEY ARE
FEET AND REFER TO THE NORTH AMERICAN
2. ELEVATIONS ARE REFLECTED IN US SURVEY
SHEET G-009.
THEY ARE BASED ON CONTROL POINT PT-2A. SEE
SYSTEM FOR: NEBRASKA STATE PLANE (2600).
DATUM OF 1983 (NAD83) STATE PLANE COORDINATE
SURVEY FEET AND REFER TO THE NORTH AMERICAN
1. GRID COORDINATES ARE REFLECTED IN US
RIGHT (WEST) SLOPE
SITE 08 PLUNGE POOL
DISPERSED RIPRAP
EXISTING
DISPERSED RIPRAP
FENCE
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
50 1250
12551255
T
M
V-103
X
IS
T
IN
G C
O N
D
IT
IO
E
S
T A
G E
C O
A C
H D
A M
SCALE: 1" = 15'
0 15'15' 7.5'
PILE BENTS
S C
V -1
.d
1320 MAJOR CONTOUR
MINOR CONTOUR
PILING
EXISTING RIPRAP
CONDUIT CENTERLINE
TOP OF SCARP
PZ 4-12
PIEZOMETER
ACCESS MANHOLE
TOP OF SCARP
OUTLET WORKS CONDUIT
EXISTING CONDITIONS - SITE 09
SURFACE IS UNKNOWN, FIELD VERIFY.
6. EDGE OF EXISTING RIPRAP BENEATH WATER
5. COMBINED SCALE FACTOR 0.999725427.
4. CONTOUR INTERVAL IS 1 US SURVEY FOOT.
METHODS. FIELD SURVEY DATE: NOVEMBER 2019.
3. TOPOGRAPHY IS DERIVED FROM GPS/RTK SURVEY
G-010.
BASED ON CONTROL POINT PT-1A. SEE SHEET
VERTICAL DATUM 1988 (NAVD 88). THEY ARE
FEET AND REFER TO THE NORTH AMERICAN
2. ELEVATIONS ARE REFLECTED IN US SURVEY
SHEET G-010.
THEY ARE BASED ON CONTROL POINT PT-1A. SEE
SYSTEM FOR: NEBRASKA STATE PLANE (2600).
DATUM OF 1983 (NAD83) STATE PLANE COORDINATE
SURVEY FEET AND REFER TO THE NORTH AMERICAN
1. GRID COORDINATES ARE REFLECTED IN US
LEFT (NORTH) SLOPE
SITE 09 PLUNGE POOL
SITE 9 PLUNGE POOL
M
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
V-104
X
IS
T
IN
G C
O N
D
IT
IO
E
Y
A N
K E
E H
IL
L D
A M
SCALE: 1" = 15'
0 15'15' 7.5'
S C
V -1
.d
PILING
EXISTING RIPRAP
SIGNPOST
CONDUIT CENTERLINE
TOP OF SCARP
TOP OF SCARP
PILE BENTS
ACCESS MANHOLE
OUTLET WORKS CONDUIT
EXISTING CONDITIONS - SITE 10
SURFACE IS UNKNOWN, FIELD VERIFY.
6. EDGE OF EXISTING RIPRAP BENEATH WATER
5. COMBINED SCALE FACTOR 0.999695391.
4. CONTOUR INTERVAL IS 1 US SURVEY FOOT.
METHODS. FIELD SURVEY DATE: NOVEMBER 2019.
3. TOPOGRAPHY IS DERIVED FROM GPS/RTK SURVEY
G-011.
BASED ON CONTROL POINT PT-1B. SEE SHEET
VERTICAL DATUM 1988 (NAVD 88). THEY ARE
FEET AND REFER TO THE NORTH AMERICAN
2. ELEVATIONS ARE REFLECTED IN US SURVEY
SHEET G-011.
THEY ARE BASED ON CONTROL POINT PT-1B. SEE
SYSTEM FOR: NEBRASKA STATE PLANE (2600).
DATUM OF 1983 (NAD83) STATE PLANE COORDINATE
SURVEY FEET AND REFER TO THE NORTH AMERICAN
1. GRID COORDINATES ARE REFLECTED IN US
LEGEND
SITE 10 CONDUIT OUTLET
SITE 10 PLUNGE POOL
12051205
1205 1205
0 12
M
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
V-105
X
IS
T
IN
G C
O N
D
IT
IO
SCALE: 1" = 20'
0 20'20' 10'
S
IT
E
C
O N
E S
T O
G A D
A M
S C
V -1
.d
PILING
EXISTING RIPRAP
CONDUIT CENTERLINE
TOP OF SCARP
PILE BENTS
TOP OF SCARP
ACCESS MANHOLE
OUTLET WORKS CONDUIT
SITE 12 PLUNGE POOL
EXISTING CONDITIONS - SITE 12
LEFT (NORTH) SLOPE
SITE 12 PLUNGE POOL
SURFACE IS UNKNOWN, FIELD VERIFY.
6. EDGE OF EXISTING RIPRAP BENEATH WATER
5. COMBINED SCALE FACTOR 0.999685498.
4. CONTOUR INTERVAL IS 1 US SURVEY FOOT.
METHODS. FIELD SURVEY DATE: NOVEMBER 2019.
3. TOPOGRAPHY IS DERIVED FROM GPS/RTK SURVEY
G-012.
BASED ON CONTROL POINT PT-2B. SEE SHEET
VERTICAL DATUM 1988 (NAVD 88). THEY ARE
FEET AND REFER TO THE NORTH AMERICAN
2. ELEVATIONS ARE REFLECTED IN US SURVEY
SHEET G-012.
THEY ARE BASED ON CONTROL POINT PT-2B. SEE
SYSTEM FOR: NEBRASKA STATE PLANE (2600).
DATUM OF 1983 (NAD83) STATE PLANE COORDINATE
SURVEY FEET AND REFER TO THE NORTH AMERICAN
1. GRID COORDINATES ARE REFLECTED IN US
M
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
V-106
X
IS
T
IN
G C
O N
D
IT
IO
SCALE: 1" = 20'
0 20'20' 10'
S
IT
E
T
W
IN
L
A K
E S D
A M
S C
V -1
.d
TOP OF SCARP
TOP OF SCARP
ACCESS MANHOLE
PILE BENTS
PILING
BOTTOM OF DITCH
CONDUIT CENTERLINE
CONDUIT
OUTLET WORKS
GROUTED RIPRAP
LEGEND
EXISTING CONDITIONS - SITE 13
SITE 13 PLUNGE POOL
SURFACE IS UNKNOWN, FIELD VERIFY.
6. EDGE OF EXISTING RIPRAP BENEATH WATER
5. COMBINED SCALE FACTOR 0.999670546.
4. CONTOUR INTERVAL IS 1 US SURVEY FOOT.
METHODS. FIELD SURVEY DATE: NOVEMBER 2019.
3. TOPOGRAPHY IS DERIVED FROM GPS/RTK SURVEY
G-013.
BASED ON CONTROL POINT PT-3A. SEE SHEET
VERTICAL DATUM 1988 (NAVD 88). THEY ARE
FEET AND REFER TO THE NORTH AMERICAN
2. ELEVATIONS ARE REFLECTED IN US SURVEY
SHEET G-013.
THEY ARE BASED ON CONTROL POINT PT-3A. SEE
SYSTEM FOR: NEBRASKA STATE PLANE (2600).
DATUM OF 1983 (NAD83) STATE PLANE COORDINATE
SURVEY FEET AND REFER TO THE NORTH AMERICAN
1. GRID COORDINATES ARE REFLECTED IN US
LEFT (EAST) SLOPE
SITE 13 PLUNGE POOL
SITE 13 CONDUIT OUTLET
EXISTING RIPRAP
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
128012
85 1285
M
SCALE: 1" = 10'
0 10'10' 5'
FINAL GRADING PLAN - SITE 04
A
C -2
C -1
EXISTING RIPRAP
REMOVE AND REPLACE
RIPRAP CROSS-SECTION, SEE SHEET C-201.
FOR PLUNGE POOL SLOPE ELEVATION AND1.
NOTES:
S C
C -1
.d g n
RIPRAP
EXISTING
RIPRAP
CONTRACT
SEPARATE
1V ON 2.5H
1V ON 2.5H
IDOT CLASS C
RIPRAP
DESIGN
E = 2531571.82 N = 306250.05
E = 2531589.82 N = 306242.58
TOP OF SCARP
E = 2531591.57 N = 306273.60
ELEV = 1273'
IDOT CLASS C
PLUNGE POOL
AT BOTTOM OF
TOP OF RIPRAP
E = 2531594.37
N = 306276.95 CHANNEL ENTRANCE
PILED RIPRAP AT
REMOVE EXISTING
(FIELD VERIFY)
E = 2531549.44 N = 306270.63
ELEV = 1285'
IDOT CLASS C
ALONG TOP EDGE
TOP OF RIPRAP
ELEVATION MAY VARY
(PLACED IN A SEPARATE CONTRACT)
TOP OF CONDUIT RIPRAP
BLEND DESIGN RIPRAP TO MEET
IN A SEPARATE CONTRACT
THIS RIPRAP TO BE PLACED
TOP OF SCARP
E = 2531627.97 N = 306285.25
E = 2531614.37 N = 306300.79
(FIELD VERIFY)
E = 2531589.51 N = 306321.36
E = 2531566.91 N = 306344.54
CONDUIT
OUTLET WORKS
E = 2531523.40 N = 306308.26
F
IN
A L G
R A
D
IN
G P
L A
N
S
IT
E
B
L U
E S
T E
M L
A K
E D
A M
E = 2531635.24 N = 306297.40
E = 2531606.44 N = 306277.75
E = 2531599.37 N = 306282.90
E = 2531586.64 N = 306267.72
E = 2531596.21 N = 306258.90
E = 2531575.10 N = 306237.16
E = 2531529.15 N = 306308.67
E = 2531565.06 N = 306339.42
C-101
1V ON 2.5H
1V ON 2.5H
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
127512751275
M
A L G
R A
D
IN
G P
L A
N
S
IT
E
W
A G
O N T
R A
IN
L
A K
E D
A M
FINAL GRADING PLAN - SITE 08
SCALE: 1" = 10'
0 10'10' 5'
A
C -2
C -1
RIPRAP CROSS-SECTION, SEE SHEET C-202.
FOR PLUNGE POOL SLOPE ELEVATION AND1.
NOTES:
E = 2588051.75
N = 305147.63
E = 2588040.89
N = 305242.09
CONDUIT
OUTLET WORKS
TOP OF SCARP
TOP OF SCARP
B
C-202C-102
1V O
N 2.5
H
1V
ON 2
.5H
E = 2588025.54
N = 305149.26
E = 2588008.42
N = 305150.32
E = 2587981.98
N = 305151.97
ELEV = 1268.5'
IDOT CLASS C
ALONG TOP EDGE
TOP OF RIPRAP
ELEV = 1258'
IDOT CLASS C
PLUNGE POOL
AT BOTTOM OF
TOP OF RIPRAP
BACKFILL (SEE NOTE 4)
INSTALL SAND DRAIN AND
WEST SLOPE (SEE NOTE 4)
ACTIVE SEEPAGE FROM
SURROUNDING SLOPE
AREA AND BLEND TO
FILL AND GRADE SLOUGH
RIPRAP
EXISTING
IDOT CLASS C
RIPRAP
DESIGN
SECTION 31 00 00 PARAGRAPH 3.2.
STAGES DESRIBED IN EARTHWORK
COMPLETE CONTRUCTION ACCORDING TO2.
NECESSARY AT BOTTOM OF PLUNGE POOL.
BELOW THE WATER SURFACE. FIELD FIT WILL BE
AND EXTENT OF EXISTING RIPRAP IS APPROXIMATE
EXISTING RIPRAP NEAR THE CONDUIT. DEPTH
EXISTING RIPRAP TO MATCH THICKNESS OF
FULLY EXPOSE EXISTING RIP RAP AND TAPER3.
SLOPE NEAR ELEVATION 1269 FEET.
ACTIVE SEEPAGE ON WEST PLUNGE POOL5.
EARTHWORK SECTION 31 00 00 PARAGRAPH 3.17.
DISPOSE OF SLOUGHED MATERIAL ACCORDING TO6.
D
C-202C-102
E = 2588069.76
N = 305125.75
E = 2588017.60
N = 305112.89
E = 2587966.12
N = 305136.94
E = 2587957.99
N = 305208.92
(SEE NOTE 3)
AT ELEV 1268.5
EXISTING RIPRAP
BLEND TO
E = 2587990.38
N = 305243.42
E = 2588036.42
N = 305125.02
TO REMAIN IN PLACE
ADJACENT TO CONDUIT
EXISTING RIPRAP
AND EARTHWORK SECTION 31 00 00 PARAGRAPH 3.2.
INSTALL SAND DRAIN. SEE DETAILS ON SHEET C-2024.
S C
C -1
.d g n
E = 2587966.06
N = 305207.34
(REMOVE)
RIPRAP
DISBURSED
EXISTING
(SEE PHOTO P-102.1)
ON LEFT (EAST) SLOPE
EXISTING RIPRAP
REMOVE AND REPLACE
LEFT (EAST) SLOPE
PHOTO P-102.1 SITE 8 PLUNGE POOL
RIPRAP (REMOVE)
EXISTING DISBURSED
E = 2588033.03
N = 305148.81
E = 2587998.35
N = 305150.95
E = 2587958.32
N = 305150.11
E = 2588044.14
N = 305245.16
E = 2588063.46
N = 305146.90
C-102
1V ON 2.5H
1V O N 2.5
H
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
0 1245
T
M
A L G
R A
D
IN
G P
L A
N
PZ 4-12
PIEZOMETER
E = 2573922.49
N = 299731.08
E = 2573920.31
N = 299794.91
E = 2573840.83
N = 299769.86
E = 2573866.85
N = 299724.15
CHANNEL ENTRANCE
RIPRAP FROM OUTLET
REMOVE EXISTING
RIPRAP CROSS-SECTION, SEE SHEET C-203.
FOR PLUNGE POOL SLOPE ELEVATION AND1.
NOTES:
CONDUIT
OUTLET WORKS
FINAL GRADING PLAN - SITE 09
SCALE: 1" = 10'
0 10'10' 5'
BENEATH WATER UNKNOWN
EXTENTS OF EXISTING RIPRAP
BLEND TO EXISTING RIPRAP-
CHANNEL ENTRANCE
WITH RIPRAP FROM OUTLET
FILL BOTTOM OF SLOUGH
TOP OF SCARP
TOP OF SCARP
RIPRAP
EXISTING
E = 2573912.08
N = 299760.55
A
C -2
C -1
E = 2573912.33
N = 299764.70
E = 2573942.28
N = 299736.91
E = 2573951.63
N = 299802.10
E = 2573860.85
N = 299796.40
1V ON 2.5H
1V O
N 2.
5H
(SEE NOTE 2)
AT ELEV 1249.5'
EXISTING RIPRAP
BLEND TO
TO REMAIN IN PLACE
ADJACENT TO CONDUIT
EXISTING RIPRAP
EXISTING RIPRAP NEAR THE CONDUIT.
EXISTING RIPRAP TO MATCH THICKNESS OF
FULLY EXPOSE EXISTING RIP RAP AND TAPER2.
OF PLUNGE POOL.
FIELD FIT WILL BE NECESSARY AT BOTTOM
APPROXIMATE BELOW THE WATER SURFACE.
DEPTH AND EXTENT OF EXISTING RIPRAP IS3.
IDOT CLASS A
RIPRAP
DESIGN
ELEV = 1249.5'
IDOT CLASS A
ALONG TOP EDGE
TOP OF RIPRAP
ELEV = 1237'
IDOT CLASS A
PLUNGE POOL
AT BOTTOM OF
TOP OF RIPRAP
S C
C -1
.d g n
S
IT
E
S
T A
G E
C O
A C
H L
A K
E D
A M
C-103
E = 2573935.75
N = 299755.87
E = 2573952.34
N = 299738.50
E = 2573960.97
N = 299757.41
E = 2573961.91
N = 299748.86
E = 2573896.72
N = 299817.42
E = 2573911.22
N = 299815.67
E = 2573954.74
N = 299780.11
E = 2573863.11
N = 299720.73
E = 2573894.98
N = 299715.69
E = 2573929.11
N = 299721.98
1V ON 2.5H
M
S O
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
A L G
R A
D
IN
G P
L A
N
S
IT
E
Y
A N
K E
E H
IL
L D
A M
EXISTING RIPRAP
REMOVE AND REPLACE
A
C -2
C -1
B
C-204C-104
E = 2532283.84
N = 343032.98
E = 2532348.23
N = 343034.71
E = 2532307.43
N = 343077.78
FINAL GRADING PLAN - SITE 10
SCALE: 1" = 10'
0 10'10' 5'
RIPRAP CROSS-SECTION, SEE SHEET C-204.
FOR PLUNGE POOL SLOPE ELEVATION AND1.
NOTES:
CONDUIT
OUTLET WORKS
E = 2532302.24
N = 343013.60
ON SHEET C-204
SEE CROSS-SECTION B
FOR LIMITS OF BEDDING,
TOP OF SCARP
TOP OF SCARP
RIPRAP
EXISTING
IDOT CLASS C
RIPRAP
DESIGN
ELEV = 1221'
IDOT CLASS C
ALONG TOP EDGE
TOP OF RIPRAP
ELEV = 1210'
IDOT CLASS C
PLUNGE POOL
AT BOTTOM OF
TOP OF RIPRAP
E = 2532310.61
N = 343100.35
E = 2532379.37
N = 343033.17
1V O N 2.5
H
1V O
N 2.5
H
E = 2532339.34
N = 342992.29
E = 2532266.05
N = 343047.68
E = 2532326.35
N = 343057.81
E = 2532329.32
N = 343054.68
E = 2532352.98
N = 343067.06
E = 2532337.20
N = 343081.35
BOTTOM OF PLUNGE POOL.
SURFACE. FIELD FIT WILL BE NECESSARY AT
CONDUIT IS APPROXIMATE BELOW THE WATER
DEPTH AND EXTENT OF EXISTING RIPRAP NEAR2.
S C
C -1
.d g n
E = 2532313.43
N = 343050.48
E = 2532321.30
N = 343042.17
C-104
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
12051205
1205 1205
0 12
M
A L G
R A
D
IN
G P
L A
N
S
IT
E
C
O N
E S
T O
G A D
A M
RIPRAP CROSS-SECTION, SEE SHEET C-205.
FOR PLUNGE POOL SLOPE ELEVATION AND1.
NOTES:
SCALE: 1" = 10'
0 10'10' 5'
FINAL GRADING PLAN - SITE 12
AC
-2
C -1
E = 2513963.24
N = 355096.24
E = 2513959.50
N = 355186.30
CONDUIT
OUTLET WORKS
E = 2514034.23
N = 355186.97
TOP OF SCARP
TOP OF SCARP
RIPRAP
EXISTING
B
C-205C-105
(SEE NOTE 2)
AT ELEV 1208.5
EXISTING RIPRAP
BLEND TO
(SEE NOTE 2)
AT ELEV 1208.5
EXISTING RIPRAP
BLEND TO
E = 2514064.98
N = 355151.84
ELEV = 1208.5'
ALONG TOP EDGE
TOP OF RIPRAP
E = 2514032.97
N = 355097.74
E = 2514051.59
N = 355132.73
ELEV = 1197'
IDOT CLASS C
PLUNGE POOL
AT BOTTOM OF
TOP OF RIPRAP
ELEV = 1208.5'
IDOT CLASS C
ALONG TOP EDGE
TOP OF RIPRAP
E = 2514028.96
N = 355158.71
E = 2514027.89
N = 355126.03
E = 2514065.53
N = 355187.11
1V ON 2.5H
1V O N 2.
5H
EXISTING RIPRAP NEAR THE CONDUIT.
EXISTING RIPRAP TO MATCH THICKNESS OF
FULLY EXPOSE EXISTING RIP RAP AND TAPER2.
OF PLUNGE POOL.
FIELD FIT WILL BE NECESSARY AT BOTTOM
APPROXIMATE BELOW THE WATER SURFACE.
DEPTH AND EXTENT OF EXISTING RIPRAP IS3.
BENEATH WATER UNKNOWN
EXTENTS OF EXISTING RIPRAP
BLEND TO EXISTING RIPRAP-
TO REMAIN IN PLACE
ADJACENT TO CONDUIT
EXISTING RIPRAP
IDOT CLASS C
RIPRAP
DESIGN
S C
C -1
.d g n
E = 2514058.60
N = 355102.08
E = 2513947.91
N = 355192.54
C-105
1V ON 2.5H
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
M
A L G
R A
D
IN
G P
L A
N
S
IT
E
T
W
IN
L
A K
E S D
A M
AC
-2
C -1
6B
C-206C-106
FINAL GRADING PLAN - SITE 13
SCALE: 1" = 10'
0 10'10' 5'
RIPRAP CROSS-SECTION, SEE SHEET C-206.
FOR PLUNGE POOL SLOPE ELEVATION AND1.
NOTES:
(DEPTH UNKNOWN)
GROUTED RIPRAP
REMOVE EXISTING
E = 2485715.80
N = 375968.34
CONDUIT
OUTLET WORKS
ON SHEET C-206
SEE CROSS-SECTION B
FOR LIMITS OF BEDDING,
TOP OF SCARP
TOP OF SCARP
RIPRAP
EXISTING
E = 2485713.34
N = 375938.80
E = 2485734.03
N = 375943.42
E = 2485761.14
N = 376064.14
E = 2485731.16
N = 376034.18
E = 2485679.52
N = 376029.01
E = 2485799.70
N = 375983.38
E = 2485780.91
N = 375959.23
E = 2485736.84
N = 375978.48
E = 2485744.94
N = 375982.40
E = 2485766.69
N = 375992.93
ELEV = 1308'
IDOT CLASS C
ALONG TOP EDGE
TOP OF RIPRAP
ELEV = 1298'
IDOT CLASS C
PLUNGE POOL
AT BOTTOM OF
TOP OF RIPRAP
1V O N 2.5
H
1V ON 2.5H
GROUTED RIPRAP EXTENTS ARE APPROXIMATE.2.
IDOT CLASS C
RIPRAP
DESIGN
AT CHANNEL ENTRANCE
REMOVE EXISTING RIPRAP
DEMOLITION OF GROUTED RIP RAP
PROTECT EXISTING DRAIN DURING
S C
C -1
.d g n
EL 1308.0
TOP OF RIPRAP
E = 2485705.07
N = 376021.88
E = 2485728.63
N = 375992.77
E = 2485738.78
N = 375997.63
E = 2485742.52
N = 376069.46
C-106
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
13001300
13001300
0+00 0+10 0+20 0+30 0+40 0+50 0+60
E L E
V A
T
IO
N F
E E
T
STATION (FEET)
2.5H
1V
EL 1285.0
SURFACE
EXISTING
GRADE
FINAL
THICKNESS
3.75' RIPRAP LAYER
THICKNESS
9" SPALLS LAYER 3.75'
VARIES
EL
6" TOPSOIL
6" FOR REUSE AS TOPSOIL
EXCAVATE - STRIP TOP
EL 1273.0
LENGTH VARIES
C-201
SCALE: 1" = 5'
0 5'5' 2.5'
A
C-201C-101
ELEVATION - PLUNGE POOL SLOPE - SITE 04 - BLUESTEM DAM
TYPICAL RIPRAP SECTION
NORTH AMERICAN VERTICAL DATUM OF 1988 (NAVD 88).
ELEVATIONS ARE SHOWN IN US SURVEY FEET3.
FOR SITE 04 GENERAL PLAN, SEE SHEET G-008.2.
FOR SITE 04 GRADING PLAN, SEE SHEET C-101.1.
NOTES:
S C
C -2
.d g n
S
IT
E
B
L U
E S
T E
M D
A M
T Y
P
IC
A L R
IP
R A
P C
R O
S S S
E C
T
IO
N A
N D E
L E
V A
T
IO
L
IC
IT
A T
IO
N N
O
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
A
M A
R K
S
IZ
E
D A
T E
C H
E C
K E
D B
Y
D R
A W
N B
Y
B
C
D
E
F
SHEET
®of Engineers
US Army Corps
O M
A H
A
N E
B R
A S
K A
C O
R P
S O
F E
N G
IN
E E
R S
U .S
A R
M Y E
N G
IN
E E
R D
IS
T R
IC
T
D E
S
IG
N F
IL
E x i n
J L
W
D A
T E
C O
N T
R A
C T N
O
B C
A
S U
B M
IT
T E
D B
Y
A L
W /K
E N
U M
B E
R
W F -2
-B -0
A U
G U
S T
S A
L T C
R E
E K D
A M S
IT
E S
P L
U N
G E P
O O
L R
E P
A
IR
S
THICKNESS
12" SPALLS LAYER
SURFACE
EXISTING
THICKNESS
9" SPALLS LAYER
THICKNESS
9" SPALLS LAYER
BEDDING
12" FINE AGGREGATE
0+00 0+10 0+20 0+30 0+40 0+50 0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30 1+40
STATION (FEET)
2.5H
1VVARIES
EL
RIPRAP
3.75 FT THICK
EL 1258.0
WIDTH VARIES
EL 1273.0'
EL 1268.5EL 1268.5
E L E
V A
T
IO
N F E E
L E
V A
T
IO
N F E E
COMPACTED COHESIVE FILL
REPLACE WITH
SLOUGH AREA
THIS SHEET)
(SEE DETAIL C
1V:2.5H SLOPE
2' THICK WITH
SAND DRAIN
OF EXISTING RIPRAP
ESTIMATED BOTTOM
0+00 0+10 0+20 0+30 0+40 0+50
STATION (FEET)
EL 1271.45
EL 1258.0
EXISTING SURFACE
EXISTING OUTLET WORKS CONDUIT (TO BE PROTECTED)
VARIES
EL
E L E
V A
T
IO
N F E E
L E
V A
T
IO
N F E E
SPALLS
9" THICK
RIPRAP (VERIFY)
2.5 FT THICK
EXISTING
SPALLS
9" THICK
EXISTING
BEDDING
9" THICK
EXISTING
RIPRAP
3.75 FT THICK
60'
(FIELD VERIFY)
This is the start of the file's text. The full file is on GovTribe.