Plant City RC Lighting Scope of Work.pdf

PDF 175 KB Posted

Attached to
217047 Plant City Lighting Upgrade
Solicitation number
ITB-06932
Issued by
Hillsborough County, Eastpoint CDP, Florida

About this file

This document is a Scope of Work for the Plant City Exterior Lighting Upgrade project, which is a state and local contract opportunity in Florida. The project involves the removal of existing wall packs and pole-mounted lighting fixtures and poles, and the installation of new LED wall packs, tenon-mount luminaires, steel light poles, and concrete pole bases at the Main Armory Building, Public Parking Area, and Motor Pool locations. The project must meet Florida Building Code, State Fire Marshall, local Authorities Having Jurisdiction, and Area Water Management requirements, and the contractor is responsible for obtaining all necessary permits and fees. The project number is 12217047, and the location is 4004 Airport Rd., Plant City, FL 33563.

The document provides detailed specifications for the new equipment, including luminaire and pole models, and outlines the electrical work required, including the use of existing wiring and connections where possible, as well as the installation of new underground electrical feeders and conduit. The contractor is responsible for the environmentally appropriate disposal of any waste associated with the project and must have a current State of Florida Contractor's License. The project is being withdrawn and will be re-advertised sometime between the end of January and the end of February 2024, as indicated in the related State and Local Contract Opportunity document.

View the file

Other files

File Type Posted
Demo Plan.pdf PDF
Invitation to Bid (ITB).pdf PDF
Addendum #1.pdf PDF
Part 1-Cover-Supplemental Conditions.pdf PDF
Fixture Specifications.pdf PDF
Photometric Plan.pdf PDF
Light Pole Specifications.pdf PDF
Original Site Electrical As-Built.pdf PDF
Pole Mount Fixture Orientation Detail.pdf PDF
Addendum to General Terms & Conditions.pdf PDF
Part 2-General Terms and Conditions.pdf PDF
Plant City Lighting Plan.pdf PDF
Pole Base Specifications.pdf PDF
Proposal & SubList.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NUMBER: 12217047

PROJECT NAME & LOCATION: Plant City Exterior Lighting Upgrade – 4004 Airport Rd., Plant City, FL 33563

Exhibit 1

Project must meet Florida Building Code, State Fire Marshall, local Authorities Having Jurisdiction and Area Water Management requirements, and any other permits and fees required by other county, local or state authorities.

Regulatory permitting to include the preparation, submittal, payment and review coordination of the Water Management District, Environmental Resource Permit (including permit fees), Florida Department of Environmental Protection (FDEP) Notice of Intent (including filing fees), City and/or County Review Permit Fee, and any other permits and fees required by other county, local or state authorities.

Detailed Scope of Work:

1. Removal of existing equipment

1.1. Main Armory Building

1.1.1. Contractor will remove Qty 15 Wall Packs

1.2. Public Parking Area (POV)

1.2.1. Contractor will remove Qty.1 Pole mount Luminaire and concrete pole (Demo Plan ID- Z)

1.3. Motor Pool (MOV)

1.3.1. Contractor will remove Qty. 2 Pole mount Luminaires and concrete poles (Demo Plan ID - Z)

1.3.2. Contractor will remove Qty. 1 Pole mount Luminaire and steel pole (Demo Plan ID - P)

1.3.3. Contractor will remove luminaires (2) from pole. Pole to remain. (Demo Plan ID Z1)

2. Installation of new equipment

2.1. Main Armory Building – Furnish and install:

2.1.1. Qty - 16 LED Wall Packs (Specifications - Exhibit 6)

2.2. Public Parking Area (POV) – Furnish and install:

2.2.1. Qty 2 – Tenon mount luminaire (Specifications – Exhibit 6)

2.2.2. Qty 2 – 25’ tapered round steel light pole (Specifications – Exhibit 7)

2.2.3. Qty 2 – Pre-Cast round rusticated concrete pole base (Specifications – Exhibit 8)

2.3. Motor Pool (MOV) – Furnish and install:

2.3.1. Qty 5 – Tenon mount luminaire (Specifications – Exhibit 6)

2.3.2. Qty 5 – 25’ tapered round steel light pole (Specifications – Exhibit 7)

2.3.3. Qty 5 – Pre-Cast round rusticated concrete pole base (Specifications – Exhibit 8)

2.4. Manufacturer/Model Designation

2.4.1. All luminaires listed in this section (Exhibit 1) are Basis of Design

2.4.1.1. See Luminaire Specifications and performance requirements (Specifications – Exhibit 6)

3. Lighting Controls

3.1 Photocell

3.1.1. Furnish and install (Qty 7) pole mounted photocell on each light pole

3.1.1.1. Manufacturer – WattsStopper - EM-24A2 or equal

3.1.1.2. Photocells to be mounted 10’ AFF.

3.1.2. There are no additional new lighting controls in this specification.

This space intentionally left blank

PROJECT NUMBER: 12217047

Exhibit 1 – Cont’d.

4. Electrical Connections

4.1 Existing AsBuilt plans indicate 277VAC

4.1.1. It is the responsibility of the contractor to confirm the voltage on site, and to confirm and/or revise the voltage code in the basis of design manufacturer’s model designation listed in Luminaire Specifications (Pages 3, 4, and 5)

4.2 Contractor will utilize all existing wiring and connections where available.

4.3 Contractor will inspect all existing wiring and connections related to this scope of work and repair and/or upgrade to meet current NEC requirements where applicable.

4.4 Contractor will furnish and install new underground electrical feeders and conduit to added/relocated light poles and luminaires

4.4.1. Conduit

4.4.1.1. Sch 40 1 ¼” dia

4.4.2. Wire

4.4.2.1. 2 #10 THHN/THWN & #10 THHN/THWN Gnd

5. Environmental

5.1. The contractor is responsible for environmentally appropriate disposal of any and all waste associated with the removal of existing lighting fixtures and installation of new fixtures.

6. General

6.1. Contractor must have a current State of Florida Contractors License (General and/or Electrical)

6.2. All work performed must be performed in accordance with current NEC Guidelines and local building codes.

6.3. Contractor is responsible for securing any necessary permits.

6.4. Contractor will leave job site free of debris, tools, and/or equipment at the end of each work day.

6.5. Any storage of contractor’s tools and/or equipment on site, during this project, must be approved, in advance, by the POC on site.

6.6. Contractor will clean job site upon completion of work.

6.7. Contractor is responsible for environmentally appropriate disposal, off site, of any project related materials/equipment.

6.8. Contractor will perform start-up per manufacturer’s recommendations and check system for proper operation

End of Section