Plans - NP COLO 1C14 1D48 1E15.pdf
PDF 15 MB Posted
- Attached to
- Colonial National Historical Park Federal contract opportunity
- Solicitation number
- 693C73-24-B-000009
About this file
This document is a solicitation for the rehabilitation of seven bridges within the Colonial National Historical Park in James City County, Virginia. The project consists of repairing concrete, cleaning and resealing joints, cleaning and painting structural steel, cleaning and sealing concrete decks, repairing timber decks, and other miscellaneous work. The project is estimated to cost between $2,000,000 and $5,000,000 and will be split into multiple work schedules/contract options. The solicitation is set aside for certified Small Business Concerns only. Bid documents will be available on or about May 1, 2024, and bids are due by a date and location specified in the solicitation. Interested vendors must register in the System for Award Management (SAM) database prior to submitting a bid. The solicitation is issued by the Department of Transportation Federal Highway Administration.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Results of Bid Opening - Project VA NP COLO 1C15 1D48 1E15.pdf | ||
| IFB Solicitation - VA NP COLO 1C14 1D48 1E15.pdf | ||
| Bridge Inspection Report 4290-023P.pdf | ||
| Categorical Exclusion Form (NEPA).pdf | ||
| Bridge Inspection Report 4290-031P.pdf | ||
| ADV_Bidders Qualifications Form.doc | DOC document | |
| Bridge Inspection Report 4290-025P.pdf | ||
| Bridge Inspection Report 4290-024P.pdf | ||
| Bridge Inspection Report 4290-028P.pdf | ||
| FP14_Eng.pdf | ||
| Bridge Inspection Report 4290-026P.pdf | ||
| Bridge Inspection Report 4290-029P.pdf | ||
| VETS-4212 Form.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Title Sheet
Symbols And Abbreviations
Location Map
Tabulation of Quantities
Erosion And Sediment Control Narrative
DESCRIPTION
INDEX TO SHEETS
PLANS FOR PROPOSED
PLANS PREPARED BY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
ASHBURN, VIRGINIA
ADT (2022)
ADT (2042)
DHV
%Truck
D
V (MPH)
50/50
2%
25-50
SPECIFICATIONS:
DESIGN DESIGNATION:
e(max) 8%
C/A None
JAMES CITY COUNTY, VIRGINIA
4290-028P, 4290-029P, AND 4290-031P)
(STRUCTURE NO. 4290-023P, 4290-024P, 4290-025P, 4290-026P,
REHABILITATION OF SEVEN BRIDGES
Administration
Federal Highway
U.S. Department of Transportation
SHEET
NO
A01
A02-A03
A04
C01-C03
M01-M02
U.S. DEPARTMENT OF THE INTERIOR
NATIONAL PARK SERVICE
COLONIAL NATIONAL HISTORICAL PARK
1C14, 1D48, 1E15
PROJECT VA NP COLO
and Bridges on Federal Highway Projects", FP-14.
"Standard Specifications for Construction of Roads
FEBRUARY 2024
Project Manager
D. WESTON
Lead Designer
J. JOHNSON
Highway Design Manager
K. KHAN
DESCRIPTION OF PROJECT
IMPROVEMENT:
PROJECT LENGTH: 0.47 Miles
BRIDGE:
timber decks, and other miscellaneous work.
paint structural steel, clean and seal concrete decks, repair
Repair concrete spalls, clean and reseal joints, clean and
LANE MILES:
ROAD: WIDTH SURFACE BASEROAD: WIDTH
24' to 38'
SURFACE BASE
Concrete and asphalt
Exposed Aggregate
Base
AggregateColonial Parkway
N
0 4040
SCALE IN MILES
Richmond
Arlington
Charlottesville
Front
Royal
KEY MAP
STATE OF VIRGINIA
To Richmond
Williamsburg
Pa rkwa y
Colonial
C o lo n ia l
Yorktown
To Newport News and Norfolk
Cheatham Annex
To Wash. D.C.
P k w y
N
0.92 Miles
SCALE IN MILES
0 1 2
PROJECT VA NP COLO 1C14, 1D48, 1E15
PROJECT VA NP COLO 1C14, 1D48, 1E15
10' to 25' Asphalt
Base
AggregateJamestown Loop
Colonial Parkway
N01 Traffic Control Narrative
Traffic Control PlanN02
Standards And DetailsS01-S06
Bridge Design PlanR01-R46
C04-C05
Structure Name Structure No. PMIS Number Last Date of
Inspection
Schedule
B01 Typical Section
B, C
B, C
B, C
<26
100/0
<1%
8%
None
<220
<327
Jamestown Loop
M03 Erosion And Sediment Control Plan
Know what'sbelow.
before you dig.Call
R
811 or 800-552-7001 Virginia 811 va811.com/dig with care
6/12/2023
6/12/2023
6/12/2023
6/14/2023
6/13/2023
6/15/2023
6/14/2023
JAMES RIVER
Jamestown
Y O
R K R
IV
E R
INTERSTATE
INTERSTATE
:2
P
M
F e b r u a r y
U
S
S u r2 D fh fl fi le s e rv e .f lh d .f h w a .d o t.
g o v \d a ta
\P R
O J E
C T
S \c o lo
\1 c d e \H
W Y
D
E S
\C A
D D
\A -N
P C
O L
O
C D
E tt l.
d g n
PROJECT
NUMBER
SHEET
VA NP COLO 1C14, 1D48, 1E15 A01
NPS Drwg No. 333/180254NPS PMIS NO. 222594, 222622, 222643, 222642
NPS PMIS No. 222636, 222632, 323954, 0.00EL.
BH TP
sidewalk symmetrical solid white point of spiral to tangent spiral structural stiffener stringer standard station point of spiral to tangent stopping sight distance point of spiral to spiral (no curve) point of spiral to reverse spiral square yard square foot spacing, spaces or spaced shoulder section point of spiral to curve seasonal average daily traffic south
S/W sym.
SW or SDW
STS
struc.
stiff.
stgr.
std.
Sta.
ST
SSD
SS
SRS
sqyd sqft spa.
shldr.
sec.
SC
SADT
S typ.
Ts
TS
traf.
thd.
TBM
T.
T typical tangent distance (spiraled curve) point of tangent to spiral traffic thread temporary bench mark township tangent distance
VPI
vph var.
V vertical point of intersection vehicles per hour varies design speed
W west mon.
min.
max.
MP
MOD
ML
monument minimum maximum mile post modification main line
No.
NMSA
NC
N number nominal maximum size aggregate normal crown north
OG
OD
o. to o.
ohwm
o. c.
original ground outside diameter out to out ordinary high water mark on center pvmt.
PT
PST
PSC
PS
prop.
POT
POS
POE
POC
POB
pl.
PI
PGL
PCS
PCC
PC
pavement point of tangent point of spiral to tangent point of spiral to curve point of tangent to spiral proposed point on tangent point on spiral point of ending point on curve point of beginning plate point of intersection profile grade line point of curve to spiral point of compound curve point of curve rte.
rt. or RT reqd.
reinf.
RECP
rdwy.
R/W
R.
R route right required reinforcement rolled erosion control product roadway right-of-way range radius sidewalk symmetrical solid white point of spiral to tangent spiral structural stiffener stringer standard station point of spiral to tangent stopping sight distance point of spiral to spiral (no curve) point of spiral to reverse spiral square yard square foot spacing, spaces or spaced shoulder section point of spiral to curve seasonal average daily traffic south
S/W sym.
SW or SDW
STS
struc.
stiff.
stgr.
std.
Sta.
ST
SSD
SS
SRS
sqyd sqft spa.
shldr.
sec.
SC
SADT
S
1 6
1 6
SEC.
SEC.
E
N 0
00000
JH
RBAR
NO. DATE BY REVISIONS
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION COLONIAL NATIONAL HISTORICAL PARK
HW
hex.
hdwl.
inv.
ID
jt.
high water hexagon headwall invert inside diameter joint ftg.
flg.
fin.
footing flange finish θs Ø ∆c
DY or DTY DW or DTW
DSY
drwg(s).
dist.
diaph.
diag.
dia.
DHV
D ctrs.
CS
cont.
constr. jt.
conn.
conc.
col.
CMP
CL
cc or c. to c.
BW
brg.
br.
BP
BM
bldg.
BL
BK
Asph
ASC
appr.
AMD
AH
Agg
ADT
ACP
abut.
spiral central angle diameter curve central angle total central angle dotted yellow dotted white double solid yellow drawing(s) distance diaphragm diagonal diameter design hourly volume diameter centers curve to spiral continuous construction joint connection concrete column corrugated metal pipe centerline center to center broken white bearing bridge balance point bench mark building baseline back asphalt aggregate surface course approach amendment ahead aggregate average daily traffic asphalt concrete pavement abutment expansion joint excavation existing edge of water equivalent single axle load edge of road equation edge of travel way edge of shoulder edge of pavement embankment elevation electric superelevation rate east exp. jt.
exc.
ex. or exist.
EW
ESAL
ER
EQ or eq.
EOT
EOS
EOP
emb.
elev.
elec.
e E
LW
lt. or LT Ls
LPSM
long.
LOD
lat.
lam.
L low water left length of spiral lump sum longitudinal Limits of Disturbance latitude lamination length of curve gnd or grnd galv.
GAB
ga.
HW
hex.
hdwl.
ground galvanized graded aggregate base gage (gauge) high water hexagon headwall
National Boundary
State Boundary
County Boundary
City Boundary
Township or Range Line
Section Line
Section Corner (Found, Projected)
Section Line4
Section Corner (Found, Projected)4
Section Line16
Section Corner (Found, Projected)16
Property Line w/Found Property Corner
Parcel Number
National Park Boundary
National Forest Boundary
National Wildlife Refuge Boundary
BLM Lands Boundary
Indian Reservation Boundary
Existing Roadway (Road, Paved, Gravel)
Railroad
Trail
Intermittent Drainage or Small Creek
Large Creek or River
Lake, Pond or Reservoir
Spring or Seep
Treeline; Individual Trees
Material Source; Bore Hole; Test Pit
Spot Elevation; Coordinate Grid Tick
Control Point (Terrestrial and GPS); Jump Hub
Sheet 1 of 2
:4
A e c e m b e r
S
H E
E T
C
H
W Y
D
E S
\V A
N P
C O
L O
C
D
E
\1
P S
E
\C A
D D
\A
-A
N
P C
O L
O
C
D
E s y m
.d g n
SYMBOLS AND ABBREVIATIONS
PROJECT
NUMBER
SHEET
A02
NPS Drwg No. 333/180254 NPS PMIS No. 222594, 222622, 222643, 222642
VA NP COLO 1C14, 1D48, 1E15
N
AREA PATTERN
PROJECT SPECIFIC SYMBOLS AND ABBREVIATIONS:
U.S. DEPARTMENT OF TRANSPORTATION
Type 3 barricade
COLONIAL NATIONAL HISTORICAL PARK
Fiber Roll or Wattle
North Arrow
Fence
Gate with Fence
Cattleguard
Guardrail
Retaining Wall
Concrete Barrier
Slope Stake Limits
Delineators
Signs (single, double post; portable)
Transition
Toe of Fill
Top of Cut
Pipe Culvert (arrow shows flow)
Pipe Culvert with End Section
Pipe Culvert with Headwall
Underdrain
Pipe Culvert with Drop Inlet
Box Culvert
Underground Utilities
Overhead/Above Ground Utilities
STEAM = steam, T = telephone, TV = CATV, W = water
P = power, SA = sanitary sewer, SD = storm drain, SS = storm sewer, FM = force main, FO = fiber optic, G = gas, IRR = irrigation, O = oil, Light, Support w/Anchor)
Poles (Power, Telephone, Joint Use, Miscellaneous Utility Features
UP = transformer or junction box, WF = water fountain
EM = electric meter, T = telephone pedestal, TV = CATV pedestal, Building
Right-of-Way Line with Monument
Permanent Easement
Construction Easement
Riprap
EXISTING PROPOSED
DI
Pavement Removal / Roadway Obliteration
Full Depth Pavement
Sidewalk Asphalt/Concrete
Mill and Overlay
Overlay
Silt Fence
Diversion Berm
Drainage Divide
Check Dam
Limits of Disturbance
Sheet 2 of 2
SYMBOLS AND ABBREVIATIONS
:4 e c e m b e r
S
H E
E
H W
Y
D E
S \V
A N
P C
O L
O
C
D
E
\1
P
S
E \C
A D
D \A
-A
N P
C O
L O
C
D
E s y m .d g n
PROJECT
A03
VA NP COLO 1C14, 1D48, 1E15
SCALE IN FEET
0 2000 4000
(Structure No. 4290-024P)
Mill Creek Bridge
(Structure No. 4290-025P)
Powhatan Creek Bridge
(Structure No.4290-029P)
Blacks Point Bridge
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
LOCATION MAP
COLONIAL NATIONAL HISTORICAL PARK
1 See Details E635-15
NOTE:
:4
D e c e m b e r
D e f a u lt
P R
O J E
C T
S \c o lo
\1 c d e \H
W Y
D
E S
\C A
D D
\A N
P C
O L
O
C D
E
L o c .d g n
PROJECT
A04
NPS Drwg No. 333/180254NPS PMIS No. 222594, 222622, 222643, 222642
NPS PMIS No. 222636, 222632, 323954, NP COLO 1C14, 1D48, 1E15VA
(Structure No.4290-031P)
Long Bridge
T r e a s u r e I s la n d R d
Wessex Hundred
Jockey's Neck Trail
Robert Fenton Rd
S ir T h o m a s W a y
(Structure No. 4290-026P)
Isthmus Bridge
(Structure No.4290-028P)
Pitch and Tar Bridge
(Structure No. 4290-023P)
College Creek Bridge
Island Drive East Loop
Island Drive W est Loop
Island Drive
Colonial Pkwy
Sm ith Rd
Captain John pavement asphalt
Existing course base
Existing
Tack coat (Typ.)
ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2
Varies (See Note)
Pay limits or subgrade.
pavement to expose subbase
Saw cut and remove existing
/2" NMSA, <0.3 Million ESAL.1 Type 2, Place Asphalt concrete pavement, conditions encountered at time of construction.
The CO will determine the patching limits based on
Note:
NO SCALE
U.S. DEPARTMENT OF TRANSPORTATION COLONIAL NATIONAL HISTORICAL PARK
:5
J a n u a r y
U
S S u r_ ft
P R
O J E
C T
S \c o lo
\1 c d e
\H
W Y
D
E S
\C A
D D
\B
-N
P C
O L
O
C
D
E
.d g n
TYPICAL SECTION
PROJECT
B01
NP COLO 1C14, 1D48, 1E15VA
U.S. DEPARTMENT OF TRANSPORTATION
SCHEDULE A
:4
D e c e m b e r
C
S
H E
E
P R
O J E
C T
S \c o lo
\1 c d e
\H
W Y
D
E S
\C A
D D
\C
-C
N
P C
O L
O
C
D
E q ty
.d g n
TABULATION OF QUANTITIES
PROJECT
C01
NPS PMIS No. 222636, 222632, 323954, FEDERAL HIGHWAY ADMINISTRATION
SCHEDULE B
:4
D e c e m b e r
C
P R
O J E
C T
S \c o lo
\1 c d e
\H
W Y
D
E S
\C A
D D
\C
-C
N
P C
O L
O
C
D
E q ty
.d g n
TABULATION OF QUANTITIES
PROJECT
C02
NPS PMIS No. 222636, 222632, 323954, FEDERAL HIGHWAY ADMINISTRATION
SCHEDULE C
:3
F e b r u a r y
C
H W
Y D
E S
\V A
N P
C O
L O
C
D
E
\1
P S
E
\C A
D D
\C -C
N
P C
O L
O
C D
E q ty
.d g n
TABULATION OF QUANTITIES
PROJECT
C03
NPS PMIS No. 222636, 222632, 323954, FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
:5
J a n u a r y
C
P R
O J E
C T
S \c o lo
\1 c d e \H
W Y
D
E S
\C A
D D
\C -C
N
P C
O L
O
C D
E q ty
.d g n
PERMANENT SIGN SUMMARY
PROJECT
C04
NPS Drwg No. 333/180254NPS PMIS No. 222594, 222622, 222643, 222642
NPS PMIS No. 222636, 222632, 323954, FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
:5
J a n u a r y
C
P R
O J E
C T
S \c o lo
\1 c d e \H
W Y
D
E S
\C A
D D
\C -C
N
P C
O L
O
C D
E q ty
.d g n
CONSTRUCTION SIGN SUMMARY
PROJECT
C05
NPS PMIS No. 222636, 222632, 323954, In general, preserve existing vegetation, trees, and shrubs when possible, and where specifically directed by the CO.
Do not allow any construction equipment to operate or access on the downslope side of perimeter control measures.
Do not allow construction vehicles to track sediment off-site of the project limits.
Do not drive construction equipment in or across flowing waterways.
Control only sediment-laden runoff generated by the project site.
permanently ceased.
disturbed areas as soon as is practical, but no more than 14 days after construction activity has temporarily or
Preventing initial soil erosion is much more effective than trying to control eroded sediment. Therefore, stabilize all
Do not modify the type, size, or location of any control or practice without approval from the CO.
Install all erosion and sediment control measures as shown in the Plans or as directed by the Contracting Officer (CO).
practices in incremental stages as construction proceeds.
activities to ensure economical, effective, and continuous erosion and sediment control. Employ temporary stabilization
Coordinate the installation, use, and removal of erosion and sediment control measures with roadway construction
Special Contract Requirements.
in the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14 and the pollution prevention controls. Soil erosion controland turf establishment measures are also defined and outlined waters. The measures consist of stabilization and structural practices, stormwater controls, and other miscellaneous minimize the sedimentation of rivers, streams, and impoundments such as lakes, reservoirs, bays, and coastal sediment. The work consists of applying measures throughout the life of the project to control erosion and to
The Erosion and Sediment Control Plan/Location (ESCP) is a guideline for preventing erosion and controlling
1. GENERAL GUIDELINES
EROSION AND SEDIMENT CONTROL NARRATIVE
and ditches according to Sections 624 and 625.
As soon as practical, but not to exceed 14 calendar days, apply permanent turf establishment to the finished slopes more than 14 calendar days or as directed by the CO.
Apply temporary turf establishment and 2-inch topsoil on uncompleted disturbed areas that will remain exposed for
* PHASE II (INTERMEDIATE CONTROLS/STABILIZATION):
not leave the project site. Perimeter controls include silt fence.
Prior to bridge repair and improvements, construct perimeter controls to ensure that any disturbed sediment does
* PHASE I (ESTABLISH PERIMETER CONTROLS):
Unless otherwise noted, sequence of construction phasing applies to all areas of work.
B. SEQUENCE OF CONSTRUCTION
concrete decks, repairing timber decks, and other miscellaneous work.
repairing concrete spalls, cleaning and resealing joints, cleaning and painting structural steel, cleaning and sealing
This project consists of the rehabilitation of several bridges and ramps along the Colonial Parkway. Work includes
A. PROJECT DESCRIPTION
2. SITE DESCRIPTION
of inspection and repairs. Provide the CO with copies every month and the entire record at the completion of the project.
operations. If visible sedimentation is found off-site, take immediate measures to clean up the site. Maintain written records
Replace erosion and sediment control measures that cannot be maintained and those that are damaged by construction during wet weather. Clean erosion and sediment control measures when half full of sediment. Repair measures as necessary.
erosion and sediment control measures at least weekly, but also within 24 hours after a rain at 0.5 inches or more, and daily
Inspect, maintain, and clean all erosion and sediment control measures according to Section 157. Check, clean, and repair
5. INSPECTION AND MAINTENANCE PROCEDURES FOR CONTROLS
measures.
Structural practices used on this project include silt fence, culvert inlet/outlet protection measures, and other approved
4. LIST OF STRUCTURAL PRACTICES
vegetation, and other approved measures.
Temporary stabilization practices used on this project include temporary seeding with mulching, preservation of existing
A. TEMPORARY
3. LIST OF STABILIZATION PRACTICES
Stabilize all areas which are disturbed due to the removal of sediment control devices.
Remove all perimeter controls, silt fence, and other erosion and sediment control measures when directed by the CO.
Remove all perimeter silt fence only after turf is well established.
Remove silt fence and inlet protection only after all upslope areas are stabilized and vegetation is well established.
Inspect, clean, and repair all culvert outlet protection, riprap basins, and stabilized channels.
has not established.
Where necessary, replace eroded topsoil and reapply permanent turf establishment to disturbed areas where vegetation
After completion of construction, perform the following as directed by the CO:
* PHASE III (FINAL CONTROLS/STABILIZATION):
remaining in place longer than 14 days or when directed by the CO.
Provide silt fence around all stockpiled roadway material. Apply temporary mulch or temporary turf establishment to stockpiles
Do not allow ponded water to encroach into travel lanes.
traffic.
In order to prevent traffic hazards caused by ponded water on the roadway, do not install inlet protection at inlets adjacent to
Install temporary inlet protection to any inlet, susceptible to receiving sediment laden water.
When directed by the CO, apply temporary mulch to all disturbed slopes at the end of each day's operations.
temporary turf establishment.
To control erosion during the time periods between seeding seasons shown in Section 625, apply temporary mulch in lieu of
U.S. DEPARTMENT OF TRANSPORTATION COLONIAL NATIONAL HISTORICAL PARK
Sheet 1 of 2
:3
J a n u a r y
D e f a
P R
O J E
C T
S \c o lo
\1 c d e \H
W Y
D
E S
\C A
D D
\M -M
-e d it s -N
P C
O L
O
C D
E
E
S C
N a rr a ti v e .d g n
CONTROL NARRATIVE
EROSION AND SEDIMENT
PROJECT
M01 must be addressed.
standards (from the Virginia Erosion & Sediment Control Regulations, MS-1MS-19 of the Virginia Erosion & Sediment Control Handbook. All applicable minimum
This section presents the guidelines & requirements identified in Chapter 6
VESCH Minimum Standards (MS-19) dormant for more than one year.
stabilization shall be applied to areas to be left dormant for longer than 13 days. Permanent may not be at final grade but will remain applied within seven days to denuded areas that of the site. Temporary soil stabilization shall be days after final grade is reached on any portion shall be applied to denuded areas within seven
1. Permanent or temporary soil stabilization transferred off-site.
on-site and borrow areas or soil intentionally stabilization shall be applied to all soil stockpiles
Temporary protection and permanent or protected with sediment trapping measures.
stockpiles and borrow areas shall be stabilized
2. During construction of the project, soil enough to survive and will inhibit erosion.
ground cover is achieved that is uniform, mature shall not be considered established until a permanently stabilized. Permanent vegetation established on denuded areas not otherwise
3. Permanent vegetative cover shall be takes place.
made functional before upslope land disturbance step in any land-disturbing activity and shall be to trap sediment shall be constructed as a first sediment barriers and other measures intended
4. Sediment basins and traps, perimeter dikes, other diversions immediately after installation.
earthen structures such as dams, dikes and
5. Stabilization measures shall be applied to
24 hours.
integrity of the basin during a 25-year storm of shall at a minimum maintain the structural yards/acre of drainage area. The outfall system minimum storage capacity of 134 cubic drainage areas less than three acres with
Sediment traps shall be constructed to control drainage area to be served by the trap or basin.
designed and constructed based upon the total
6. Sediment traps and sediment basins shall be corrected.
slope stabilization measures until the problem is stabilization shall be provided with additional excessively within on year of permanent erosion. Slopes that are found to be eroding constructed in a manner that will minimize
7. Cut and fill slopes shall be designed and flume or slope drain structures.
adequate temporary or permanent channel, or fill slopes unless contained within an
8. Concentrated runoff shall not flow down cut
14 days.
remain dormant for longer than denuded areas which will temporary stabilization to all temporary seeding or other
1. Contractor must apply
2. Not Applicable project site without approval.
soil can be brought into the all denuded areas. No foreign mix, approved by the CO, to topsoil and permanent seed
3. Contractor must apply any land disturbing activity.
perimeter controls prior to
4. Contractor must establish
5. Not Applicable
6. Not Applicable
7. Not Applicable remain sheet flow.
8. Not Applicable. All flow must provided adequate drainage or other protection shall be
9. Whenever water seeps from a slope face, otherwise treated to remove sediment.
conveyance system without first being filtered or so that sediment-laden water cannot enter the operable during construction shall be protected
10. All storm sewer inlets that are made channel and receiving channel.
shall be installed in both the conveyance required temporary or permanent channel lining operational, adequate outlet protection and any conveyance channels or pipes are made
11. Before newly constructed stormwater armored by non-erodible cover materials.
Earthen fill may be used for these structures if construction of causeways and cofferdams.
Non-erodible material shall be used for the greatest extent possible during construction.
transport and stabilize the work area to the minimize encroachment, control sediment performed, precautions shall be taken to
12. When work in a live watercourse is shall be provided.
crossing constructed of non-erodible material month period, a temporary vehicular stream construction vehicles more than twice in any six-
13. When a live watercourse must be crossed by live watercourses shall be met.
regulations pertaining to working in or crossing
14. All applicable federal, state, and local watercourse is completed.
stabilized immediately after work in the
15. The bed and banks of a watercourse shall be addition to other applicable criteria:
accordance with the following standards in
16. Underground utility lines shall be installed in
9. Not anticipated.
10. Not Applicable.
11. Not Applicable.
channel impacts.
measures to minimize in-stream protection
12. Contractor must install
13. Not Applicable.
and local regulations.
all applicable federal, state,
14. Contractor must follow construction.
areas subject to in-stream immediately restabilize the
15. Contractor must and promote stabilization.
properly compacted in order to minimize erosion
D. Material used for backfilling trenches shall be accordance with these regulations.
E. Re-stabilization shall be accomplished in complied with.
F. Applicable safety regulations shall be sedimentation.
stabilized to prevent further erosion and temporary measures shall be permanently soil areas resulting from the deposition of authority. Trapped sediment and the disturbed otherwise authorized by the local program measures are no longer needed, unless final site stabilization or after the temporary measures shall be removed within 30 days after
18. All temporary erosion and sediment control performed.
outfall of the pipe or pipe system shall be sites, downstream stability analyses at the channel, pipe, or storm sewer system. For those into adequate natural or man-made receiving development site shall be discharged directly
Concentrated stormwater runoff leaving a the following standards and criteria.
storm of 24-hour duration in accordance with of stormwater runoff for the stated frequency increases in volume, velocity and peak flow rate sediment deposition, erosion and damage due to development sites shall be protected from the
19. Properties and waterways downstream from
D. Not Applicable.
achieved.
permanent stabilization is any disturbed area until
E. Contractor must re-stabilize applicable safety regulations.
F. Contractor to adhere to all within the project area.
streets and allay dust daily
17. Contractor to sweep out.
and prior to project close following final stabilization temporary filter barriers
18. Contractor must remove up-sized culverts.
protection downstream from provide adequacy of channel unless otherwise directed and directly to the open space treated or filtered runoff
19. Contractor must discharge be opened at one time.
A. No more than 500 linear feet of trench may uphill side of trenches.
B. Excavated material shall be placed on the streams on off-site property.
manner that does not adversely affect flowing trapping device, or both, and discharged in a filtered or passed through an approved sediment
C. Effluent from dewatering operations shall be
A. Not applicable
B. Not applicable device prior to discharge.
maintain sediment trapping
Contractor shall install and runoff or groundwater.
discharge sediment-laden
C. Contractor must not land disturbing activities.
individual development lots as well as to larger in this manner. This provision shall apply to shall be allowed only after sediment is removed sediment control disposal area. Street washing shoveling or sweeping and transported to a
Sediment shall be removed from the roads by cleaned thoroughly at the end of the day.
public road surface, the road surface shall be
Where sediment is transported onto a paved or by vehicular tracking onto the paved surface.
be made to minimize the transport of sediment intersect paved or public roads, provisions shall
17. Where construction vehicles access routes
U.S. DEPARTMENT OF TRANSPORTATION COLONIAL NATIONAL HISTORICAL PARK
Sheet 2 of 2
:2
J a n u a r y
D e f a
P R
O J E
C T
S \c o lo
\1 c d e
\H
W Y
D
E S
\C A
D D
\M
-M
-N P
C O
L O
C
D
E
E
S C
N a rr a ti v e .d g n
CONTROL NARRATIVE
EROSION AND SEDIMENT
PROJECT
M02
(Typ.)
for pile encapsulation
Limits of disturbance
See Detail E157-11
Install floating turbidity curtain
(Typ.)
for pile encapsulation
Limits of disturbance
See Detail E157-02
Silt fence
WORK ON LAND WORK IN WATER
U.S. DEPARTMENT OF TRANSPORTATION COLONIAL NATIONAL HISTORICAL PARK
NO SCALE
:0 e c e m b e r
D e f a
P R
O J E
C T
S \c o lo
\1 c d e \H
W Y
D
E S
\C A
D D
\M C
O L
O
B
C
D
P
E P
.D G
N
CONTROL PLAN
EROSION AND SEDIMENT
PROJECT
M03
GENERAL NOTES
TRAFFIC CONTROL, PHASE I (SCHEDULE A)
TRAFFIC CONTROL, PHASE II (SCHEDULES B AND C)
in the plans, or directed by the CO.
The following general notes apply at all times for the duration of the construction project, except when otherwise noted undesired overlapping of devices. Modifications may include: moving, supplementing, covering, or removing devices.
the CO. Changes may be required when physical dimensions in the plans are not attainable, or result in duplicate or
Adapt the traffic control plans to meet field conditions and provide safe and efficient traffic movement, as approved by of the day. Properly secure the steel plates if traffic is allowed to run over them.
3. Use steel plates to cover trenches in the roadway which cannot be backfilled to the pavement grade by the end
2. Cover or remove all conflicting signs and remove all conflicting striping for each stage, as approved by the CO.
1. Obtain approval from the CO for final locations and spacing of all traffic control devices.
Finish phase I construction before moving to phase II.
Close the Pitch and Tar Bridge, Blacks Point Bridge, and Long Bridge as shown in the Traffic Control Plan sheet.
Remove all traffic control devices from Powhatan Creek Bridge construction and close partial lane width using Temporary Traffic Control Part Lane Width and Shoulder Closure Layout Detail ET 635-11A to work on Isthmus Bridge.
Finish Powhatan Creek Bridge construction before moving to work on Isthmus Bridge.
Remove all traffic control devices from MIll Creek Bridge construction and close partial lane width using Temporary Traffic Control Part Lane Width and Shoulder Closure Layout Detail ET 635-11A to work on Powhatan Creek Bridge.
Finish MIll Creek Bridge construction before moving to work on Powhatan Creek Bridge.
Remove all traffic control devices from College Creek Bridge construction and close partial lane width using Temporary Traffic Control Part Lane Width and Shoulder Closure Layout Detail ET 635-11A to work on MIll Creek Bridge.
Finish College Creek Bridge construction before moving to work on Mill Creek Bridge.
Remove all traffic control devices from phase I construction and close partial lane width using Temporary Traffic Control Part Lane Width and Shoulder Closure Layout Detail ET 635-11A to work on College Creek Bridge.
NO. DATE BY REVISIONS
OFFICE OF FEDERAL LANDS HIGHWAY
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION COLONIAL NATIONAL HISTORICAL PARK
:1 e c e m b e r
N
S H
E E
P R
O J E
C T
S \c o lo
\1 c d e \H
W Y
D
E S
\C A
D D
\N N
P C
O L
O
C D
E
T
C P
.d g n
TRAFFIC CONTROL NARRATIVE
PROJECT
NUMBER
SHEET
NP COLO 1C14, 1D48, 1E15VA N01
Sign R11-2 (Mod.)
Sign R5-10b2
Sign R11-3a
Mount signs on type 3 barricades.
NOTE:
OR BICYCLES
PEDESTRIANS
NO
LOCAL TRAFFIC ONLY
ROAD CLOSED
1 MILE AHEAD
BRIDGE OUT
Sign R11-24
ROAD
CLOSED
U.S. DEPARTMENT OF TRANSPORTATION
SCHEDULE A, PHASE I
COLONIAL NATIONAL HISTORICAL PARK
:5 e c e m b e r
D e f a
H W
Y
D E
S \V
A N
P C
O L
O
C
D
E
\1
P
S
E \C
A D
D \N
N
P C
O L
O
C
D
E tt c .d g n
TRAFFIC CONTROL PLAN
PROJECT
NUMBER
SHEET
NP COLO 1C14, 1D48, 1E15VA N02
(Structure No.4290-031P)
Long Bridge
(Structure No.4290-029P)
Blacks Point Bridge
(Structure No.4290-02BP)
Pitch and Tar Bridge
R02
/2
/2
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
SCOPE OF WORK
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
SCOPE OF WORK:
N/A
R C
O L
O
B
C
D
S C
O P
E .D
G N
A C
T U
A L
F
IL
E
PEDESTRIAN BRIDGE
AND JAMESTOWN VISITOR CENTER
BLACKS POINT BRIDGE, LONG BRIDGE,
ISTHMUS BRIDGE, PITCH AND TAR BRIDGE,
MILL CREEK BRIDGE, POWHATAN CREEK BRIDGE,
REHABILITATION OF COLLEGE CREEK BRIDGE,
- Clean and paint steel superstructure.
Structure Number 4290-026P - Isthmus Bridge
- Clean and paint steel superstructure.
Structure Number 4290-024P - Mill Creek Bridge
- Clean and paint steel superstructure.
Structure Number 4290-023P - College Creek Bridge
Schedule C
028P, 029P, 031P
4290-023P, 024P, 025P, 026P,
- Patch approach asphalt.
Remove vegetation growth along structure.-
- Replace missing anchor bolt nut.
- Repair utility conduits.
- Clean and seal concrete deck.
- Remove existing joint seal and install new pre-compressed hybrid seal.
underside, and curbs.
- Locate and repair all deteriorated concrete at abutments, railings, deck
Structure Number 4290-026P - Isthmus Bridge
- Remove and replace rigid concrete pavement section.
"CONCRETE PILE ENCAPSULATION" sheet.
(FRP) pile jackets on piles according to fiber-reinforced polymer- Place
Unclog weep holes at abutments.-
Remove vegetation growth along structure.-
- Remove existing joint seal and install new pre-compressed hybrid seal.
underside, and abutments.
Locate and repair all deteriorated concrete at the bents, deck -
Structure Number 4290-025P - Powhatan Creek Bridge
Remove vegetation growth along structure.-
- Clean and seal concrete deck.
- Remove existing joint seal and install new pre-compressed hybrid seal.
curbs.
- Locate and repair all deteriorated concrete at abutments, railings, and
Structure Number 4290-024P - Mill Creek Bridge
Remove vegetation growth along structure.-
- Place lean concrete backfill in areas of undermining near wingwalls.
- Clean and seal concrete deck.
- Remove existing joint seal and install new pre-compressed hybrid seal.
curbs.
- Locate and repair all deteriorated concrete at abutments, railings, and
Structure Number 4290-023P - College Creek Bridge
Schedule B
- Replace damaged railing in-kind.
- Patch approach asphalt.
- Repair damages to Bent #36.
- Drive in uplifted deck spikes and install new spike near damaged spikes.
"TIMBER PILE ENCAPSULATION" sheet.
- Place fiber-reinforced polymer (FRP) pile jackets on piles according to washers.
- Clean and apply galvanizing spray to exterior beam bolts, nuts, and
- Tighten loose bolts and replace missing or damaged bolts/nuts.
- Remove and replace 15 glulam deck panels in-kind.
Structure Number 4290-031P - Long Bridge
- Replace damaged railing in-kind.
- Patch approach asphalt.
- Remove leaning trees near west abutments.
- Drive in uplifted deck spikes and install new spike near damaged spikes.
"TIMBER PILE ENCAPSULATION" sheet.
- Place fiber-reinforced polymer (FRP) pile jackets on piles according to
- Reattach loose superstructure bridging.
- Remove and replace pile bent cross bracing at Bents #15 and #16.
washers.
- Clean and apply galvanizing spray to exterior beam bolts, nuts, and
- Tighten loose bolts and replace missing or damaged bolts/nuts.
- Remove and replace 12 glulam deck panels in-kind.
Structure Number 4290-029P - Blacks Point Bridge
- Patch approach asphalt.
washers.
- Clean and apply galvanizing spray to exterior beam bolts, nuts, and
- Tighten loose bolts and replace missing or damaged bolts/nuts.
- Remove and replace gulam deck in-kind.
- Remove and replace timber railing.
Structure Number 4290-028P - Pitch and Tar Bridge
Schedule A
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
168 1/1656 10/1662 6/1613
168 1/1653 12/1653 12/1612
168 1/1652 4/1651 3/1611
168 1/1652 4/1651 3/1610
168 1/1651 9/1655 4/169
168 1/1654 7/1652 13/168
168 1/1650 13/1654 13/167
168 1/1651 12/1653 14/166
168 1/1650 11/1653 9/165
168 1/1652 9/1651 14/164
168 1/1650 13/1655 2/163
168 1/1656 9/1660 9/162
168 1/1648 1/1648 1/161
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
203 7/16211 12/166
199 5/16201 8/165
198 10/16204 12/164
202 1/16204 2/163
200 9/16198 7/162
206 7/16212 3/161
(in.)
Dim 'Y'
(in.)
Dim 'X'
No.
Span
Span Dimensions
R04
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
(STRUCTURE 4290-028P)
DECK PANEL LAYOUT
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
Notes:
layout.
3. See "TYPICAL DECK PANEL SPIKE LAYOUT" sheet for spike
Place panel with Dim "A" on the west side of bridge.2.
Verify span dimensions before fabricating panels.1.
Not to Scale
N
: 4290-028P
2 1 1 3 4 1 1 5 6 1 1 7 8 1 1 9 10 1 1 11 12 1 1 13
C Abutment #2L
C Bent #5L C Bent #4L
C Bent #3L C Bent #2L C Bent #1L C Abutment #1L
Tour Road
C Jamestown IsleL
See Detail A
DECK PANEL PLAN
DETAIL A
6 1 1 7
C Bent #4L
C Bent #3L
End Bridge
Begin Bridge
PITCH AND TAR BRIDGE
SCHEDULE A
R
C
O L
O
B
C
D
D e c k
P a n e l
L a y o u t_
P .D
G N
A C
T U
A L
F
IL
E
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
Dim "X" (West side)
Dim "A"
Dim "Y" (East side)
Dim "B"
°90°
90°
° 9
°9
° 9
D im
R05
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
(STRUCTURE 4290-029P)
PLAN AND ELEVATION
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
R
C
O L
O
B
C
D
P
E
P
.D G
N A
C T
U A
L F
IL
E
Notes:
No Scale
4 glued laminated panel
(Typ.)
Elev. 328.61'
Begin Bridge
Elev. 327.52'
End Bridge
Isle Tour Road
L Jamestown C
Direction of Traffic
51 41 31 21 11 01 9
1PLAN
ELEVATION
R
A p p r o x
.o N nap S
0.268%
Existing ground
Abutment 2 Bent 23 Bent 22 Bent 21 Bent 20 Bent 19 Bent 18 Bent 17 Bent 16 Bent 15 Bent 14 Bent 13 Bent 12 Bent 11 Bent 10 Bent 9 Bent 8 Bent 7 Bent 6 Bent 5 Bent 4 Bent 3 Bent 2 Bent 1 Abutment 1
: 4290-029P
(See Note 7) bent cross bracing in-kind
Remove and replace pile
BLACKS POINT BRIDGE
SCHEDULE A
N
DETAIL A
(Typ.)
for Pile encapsulation
Limits of disturbance
See Detail A
(See Note 6)
FRP jackets
Retrofit piles with
)yawdaor fo L gnola derusaem( "4-'404 C
CL E
nd ben t
End of dec k p ane l
L End bent
End of deck panel
C in superstructure (Typ.)
Reattach loose bridging in-kind (See Note 2)
Replace damaged railing near damaged spikes spikes and install new spike
Drive in uplifted deck
)dleif eht ni demrifnoc eb ot egdirb fo htgneL( width)
(10' long x full roadway pavement patch, type 2
Asphalt concrete width)
(10' long x full roadway pavement patch, type 2
Asphalt concrete
MLW
in-kind (See Note 1) damaged glulam deck panels
Remove and replace 12
#15 and #16.
7. Remove and replace existing pile bent cross bracing at bents or below the MLW elevation sheet for details. Portions of the FRP jackets will be installed at center piles at bent #16. See "TIMBER PILE ENCAPSULATION"
Install Fiber-Reinforced Polymer (FRP) jackets on north and 6.
layout.
5. See "TYPICAL DECK PANEL SPIKE LAYOUT" sheet for spike recommendations.
washers according to Section 555 and manufacturer's
Clean and apply galvanizing spray to beam bolts, nuts, and 4.
Tighten loose bolts and replace missing or damaged bolts/nuts. 3.
replacement of gulam deck panels.
2. Replace in-kind any railing sections damaged during locations, and submit to the CO for approval.
Before replacing deck panels, identify damaged areas and 1.
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
24 Spans @ 16'-10" (approx.) = 405'-4"
9'-0"
R06
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
: 4290-029P
BLACKS POINT BRIDGE
SCHEDULE A
Not to Scale
CL Abutment #2
End Bridge
CL Bent #23
CL Bent #22
CL Bent #21
CL Bent #20
CL Bent #19 CL Bent #18
CL Bent #17 CL Bent #16 CL Bent #15 CL Bent #14 CL Bent #13
CL Bent #12
CL Bent #11
Match line
CL Bent #11
CL Bent #10
CL Bent #9 CL Bent #8
CL Bent #7
CL Bent #6 CL Bent #5
CL Bent #4 CL Bent #3
CL Bent #2 CL Bent #1
C
Match line
Begin Bridge
L Abutment #1
L of Jamestown Isle Tour Road
Direction of traffic
N
1 4 5 1 1 2 6 1 1 7 8 1 1 9 1 1 11 12 1 1 13 14 1 1 15 16 1 1 17 18 1 1 19 20 1 1 21 22 1 1 23 24 1 1
26 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1
1 1
27 28 29 30
31 32 33 34 35 36 37 38 39 40 41 42
43 44 45 46
DECK PANEL PLAN
(Stringer lines, not shown)
See Detail "A"
(STRUCTURE 4290-029P)
DECK PANEL LAYOUT - 1
Notes:
CL Bent #6
36 36 1 1 37 38
DETAIL A
C
R C
O L
O
B
C
D
D e c k P a n e l
L a y o u t_
P
.D G
N A
C T
U A
L F
IL
E dimensions.
4. See "DECK PANEL LAYOUT-2" sheet for panel and span layout.
3. See "TYPICAL DECK PANEL SPIKE LAYOUT" sheet for spike
Place panel with Dim "A" on the north side of bridge.2.
Verify span dimensions before fabricating panels.1.
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
Dim. "X" (North side)
Dim. "A"
Dim. "Y" (South side)
Dim. "B"
D im
168 1/1650 6/1651 15/1613
168 1/1649 10/1653 1/1612
168 1/1652 10/1654 10/1611
168 1/1651 15/1656 10
168 1/1652 9/1652 9/169
168 1/1651 10/1654 8
168 1/1651 7/1652 9/167
168 1/1649 10/1654 12/166
168 1/1651 14/1654 15/165
168 1/1652 7/1653 7/164
168 1/1650 10/1655 4/163
168 1/1653 10/1653 10/162
168 1/1648 1/1648 1/161
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1652 13/1655 8/1626
168 1/1650 1/1652 7/1625
168 1/1653 3/1650 4/1624
168 1/1650 14/1655 8/1623
168 1/1650 15/1654 10/1622
168 1/1651 14/1652 6/1621
168 1/1651 3/1653 9/1620
168 1/1652 6/1654 7/1619
168 1/1652 54 10/1618
168 1/1649 7/1651 9/1617
168 1/1650 9/1650 9/1616
168 1/1653 1/1656 5/1615
168 1/1652 6/1657 3/1614
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1651 9/1651 9/1639
168 1/1651 7/1653 7/1638
168 1/1651 54 2/1637
168 1/1649 14/1654 14/1636
168 1/1654 2/1655 7/1635
168 1/1654 8/1656 10/1634
168 1/1650 13/1652 13/1633
168 1/1650 3/1653 1/1632
168 1/1653 54 12/1631
168 1/1653 54 8/1630
168 1/1650 13/1653 9/1629
168 1/1650 13/1653 4/1628
168 1/1653 15/1654 15/1627
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1659 8/1659 8/1648
168 1/1659 13/1657 6/1647
168 1/1647 7/1656 10/1646
168 1/1653 10/1655 9/1645
168 1/1654 13/1654 13/1644
168 1/1650 11/1652 9/1643
168 1/1651 10/1651 12/1642
168 1/1650 4/1653 11/1641
168 1/1649 1/1654 10/1640
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
197 15/16206 3/1613
199 5/16198 12/1612
202 13/16206 8/1611
197 10/16202 14/1610
202 1/16205 5/169
197 1/16201 15/168
204 11/16208 1/167
196 15/16205 1/166
199 201 5
195 6/16204 6/164
198 7/16200 6/163
204 8/16206 7/162
203 6/16210 2/161
(in.)
Dim 'Y'
(in.)
Dim 'X'
No.
Span
Span Dimensions
209 3/16209 3/1624
199 2/16204 12/1623
201 9/16204 10/1622
197 2/16203 6/1621
200 4/16202 10/1620
200 10/16206 11/1619
196 1/16201 18
201 7/16209 9/1617
196 1/16198 4/1616
200 8/16205 2/1615
199 2/16201 15/1614
(in.)
Dim 'Y'
(in.)
Dim 'X'
No.
Span
Span Dimensions
R07
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
(STRUCTURE 4290-029P)
DECK PANEL LAYOUT - 2
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
N/A
: 4290-029P
BLACK POINT BRIDGE
SCHEDULE A
R C
O L
O
B
C
D
D e c k P a n e l
L a y o u t_
P
.D G
N A
C T
U A
L F
IL
E
Notes:
1. See "DECK PANEL LAYOUT-1" sheet for deck panel plan.
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
R09
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
: 4290-031P
LONG BRIDGE
SCHEDULE A
Not to Scale
CL Abutment #2
End Bridge
CL Bent #40
Begin Bridge
N
DECK PANEL PLAN
(Stringer lines, not shown)
(STRUCTURE-031P)
DECK PANEL LAYOUT - 1
R
-B
C O
L O
B
C
D
D
E C
K -P
A N
E L
-L A
Y O
U T
.D
G N
A C
T U
A L
F
IL
E
CL Bent #39
CL Bent #38 CL Bent #37
CL Bent #36 CL Bent #35 CL Bent #34 CL Bent #33 CL Bent #32 CL Bent #31
CL Bent #31
39 38 37 36 35 34 33
CL Bent #30 CL Bent #29
CL Bent #28 CL Bent #27 CL Bent #26 CL Bent #25 CL Bent #24 CL Bent #23 CL Bent #22 CL Bent #21
CL Bent #21 CL Bent #20
CL Bent #19 CL Bent #18 CL Bent #17 CL Bent #16 CL Bent #15 CL Bent #14 CL Bent #13 CL Bent #12 CL Bent #11
CL Bent #11 CL Bent #10
CL Bent #9 CL Bent #8 C CL Bent #6 CL Bent #5 CL Bent #4 CL Bent #3 CL Bent #2 CL Bent #1
L Bent #7
CL Abutment #1
Isle Tour Road
L Jamestown C
2 1 1 3 4 1 1 5 6 1 1 7 8 1 1 8 9 1 1 10 11 1 1 12 13 1 1 13 14 1 1 14 15 1 1 16 17 1 1 17
118 1 19 20 1 1 21 22 1 1 23 24 1 1 25 26 1 1 27 28 1 1 29 30 1 1 31 32 1 1 33 34 1 1 35 36 1 1 37
31 30 29 28 27 26 25 24 23 22
38 1 1 39 40 1 1 41 42 1 1 43 44 1 1 45 46 1 1 47 48 1 1 49 50 1 1 51 52 1 1 52 53 1 1 54 55 1 1 56
21 20 19 18 17 16 15 14 13 12
11 10 9 8 7 6 5 4 3 2 1
57 1 1 58 59 1 1 60 61 1 1 62 63 1 1 63 64 1 1 65 66 1 1 67 68 1 1 69 70 1 1 71 72 1 1 73 74 1 1 75 76 1 1 77
Span No.
See Detail "A"
N
N
N
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
168 1/1653 4/1657 11/1639
168 1/1656 15/1654 6/1638
168 1/1651 13/1653 7/1637
168 1/1653 52 3/1636
168 1/1653 3/1655 11/1635
168 1/1652 1/1656 11/1634
168 1/1654 12/1651 10/1633
168 1/1651 9/1654 1/1632
168 1/1655 4/1651 13/1631
168 1/1653 12/1654 2/1630
168 1/1650 14/1651 15/1629
168 1/1650 12/1652 11/1628
168 1/1654 12/1653 11/1627
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1661 7/1659 11/1677
168 1/1652 3/1656 11/1676
168 1/1653 11/1650 75
168 1/1651 15/1651 15/1674
168 1/1652 8/1656 8/1673
168 1/1656 15/1652 2/1672
168 1/1653 6/1656 9/1671
168 1/1653 56 9/1670
168 1/1656 15/1654 15/1669
168 1/1654 8/1657 10/1668
168 1/1652 10/1650 12/1667
168 1/1652 5/1652 5/1666
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1650 3/1658 26
168 1/1655 13/1651 8/1625
168 1/1656 4/1651 3/1624
168 1/1652 5/1655 7/1623
168 1/1655 12/1652 1/1622
168 1/1652 10/1660 21
168 1/1654 9/1657 1/1620
168 1/1655 6/1651 2/1619
168 1/1653 6/1653 14/1618
168 1/1651 12/1653 9/1617
168 1/1654 14/1653 12/1616
168 1/1652 15/1655 9/1615
168 1/1654 12/1653 14
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1652 11/1653 1/1665
168 1/1652 52 15/1664
168 1/1652 13/1653 9/1663
168 1/1655 12/1656 11/1662
168 1/1656 54 13/1661
168 1/1651 6/1652 10/1660
168 1/1653 7/1650 14/1659
168 1/1651 2/1654 5/1658
168 1/1652 53 2/1657
168 1/1654 12/1656 4/1656
168 1/1654 7/1655 15/1655
168 1/1652 10/1650 9/1654
168 1/1650 3/1653 6/1653
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1654 53 6/1613
168 1/1652 2/1652 13/1612
168 1/1651 4/1654 5/1611
168 1/1652 11/1654 6/1610
168 1/1652 15/1654 9
168 1/1650 9/1652 15/168
168 1/1650 15/1655 2/167
168 1/1652 1/1654 2/166
168 1/1652 5/1652 13/165
168 1/1650 55 3/164
168 1/1653 12/1654 12/163
168 1/1660 4/1660 1/162
168 1/1648 1/1648 1/161
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
168 1/1658 2/1654 15/1652
168 1/1648 6/1652 14/1651
168 1/1650 10/1650 4/1650
168 1/1656 7/1656 49
168 1/1656 56 10/1648
168 1/1653 1/1654 5/1647
168 1/1655 5/1652 6/1646
168 1/1652 1/1657 2/1645
168 1/1655 1/1654 44
168 1/1653 4/1653 12/1643
168 1/1654 12/1652 4/1642
168 1/1651 2/1654 8/1641
168 1/1653 4/1652 4/1640
(in.)
Dim 'C'
(in.)
Dim 'B'
(in.)
Dim 'A'
Mark
Panel
Panel Dimensions
198 13/16200 13
205 3/16208 4/1612
199 3/16203 9/1611
200 14/16199 10/1610
207 13/16207 9/169
201 10/16203 4/168
200 12/16201 12/167
201 199 2/166
207 8/16208 10/165
202 6/16209 3/164
205 8/16204 11/163
201 11/16198 1/162
209 11/16212 7/161
(in.)
Dim 'Y'
(in.)
Dim 'X'
No.
Span
Span Dimensions
197 11/16200 11/1626
205 1/16201 15/1625
202 6/16201 12/1624
201 5/16208 7/1623
200 14/16201 10/1622
206 4/16208 2/1621
200 6/16202 13/1620
204 202 1/1619
203 4/16207 3/1618
204 7/16202 12/1617
208 7/16208 11/1616
195 1/16199 3/1615
212 5/16205 14/1614
(in.)
Dim 'Y'
(in.)
Dim 'X'
No.
Span
Span Dimensions
199 2/16205 5/1639
197 3/16201 14/1638
201 11/16204 7/1637
199 7/16203 4/1636
204 2/16202 13/1635
205 8/16202 1/1634
203 14/16205 6/1633
199 10/16203 4/1632
204 13/16201 1/1631
203 4/16213 2/1630
204 2/16203 9/1629
208 2/16198 12/1628
200 15/16207 11/1627
(in.)
Dim 'Y'
(in.)
Dim 'X'
No.
Span
Span Dimensions
210 1/16210 14/1641
198 6/16204 1/1640
(in.)
Dim 'Y'
(in.)
Dim 'X'
No.
Span
Span Dimensions
R10
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
(STRUCTURE 4290-031P)
DECK PANEL LAYOUT - 2
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
Not to Scale
R C
O L
O
B
C
D
P
E
P
.D G
N A
C T
U A
L F
IL
E
: 4290-031P
LONG BRIDGE
SCHEDULE A
CL Bent #38
7 8 1 1 8 9
DETAIL A
CL Bent #37
Notes:
layout.
3. See "TYPICAL DECK PANEL SPIKE LAYOUT" sheet for spike
Place panel with Dim "A" on the north side of bridge.2.
Verify span dimensions before fabricating panels.1.
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
Dim. "X" (North side)
Dim. "A"
Dim. "Y" (South side)
Dim. "B"
R11
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
TYPICAL SECTION
TIMBER BRIDGE
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
Not to Scale
TYPICAL SECTION AT BENTS
"8
: 4290-028P, 4290-029P, 4290-031P bolt
" dia.4 fastened with 1
" Cross bracing8
3" x 7
AND LONG BRIDGE
BLACKS POINT BRIDGE,
PITCH AND TAR BRIDGE,
SCHEDULE A
panel deck
Glued laminated
" x 14'8
Key:
# Pile number
1 2 3
(Looking in the Direction of Traffic)
Pile cap
1'-0" x 1'-0"
10" x 1'-0" or
See Detail A
CL Structure
Notes:
the CO.
according to manufacturer's recommendations, as approved by ties over all bents with the deck being replaced. Attach
3. Attach timber stringer to pile cap with stainless steel hurricane
2. All dimensions are to be verified in the field.
See "CURB DETAILS" sheet for Detail A.1.
"8
TYPICAL SECTION AT MIDSPAN
CL Structure panel deck
Glued laminated
" x 14'8 each end
2 - 6" Spikes @
@ span ctrs.
2" x 4" Bridging
"8
7"8
(Typ.)
(See Note 3)
Hurricane TieR
C
O L
O
B
C
D
T
IM
B E
R T
Y P
-S E
C T
.D G
N A
C T
U A
L F
IL
E
Splice block
Stringer (Typ.)
Pile (Typ.)
Stringer (Typ.)
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
14'-0"
"4
12'-8
1'-0"
1'-9"5'-3"5'-3"1'-9"
14'-0"
"4
12'-8
R12
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
BENT REPAIR DETAILS
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
Not to Scale
TYPICAL SECTION AT BENTS
: 4290-031P
LONG BRIDGE
SCHEDULE A
Sister bent cap
CL Structure
Notes:
the CO.
according to manufacturer's recommendations, as approved by ties over all bents with the deck being replaced. Attach
3. Attach timber stringer to pile cap with stainless steel hurricane
725.22.
Furnish and install polypropylene shim conforming to Section 2.
1. All dimensions are to be verified in the field.
A A
SECTION A-A
3" 18"
(Typ.)
(Typ.)
(See Note 3)
Hurricane Tie
R C
O L
O
B
C
D
B E
N T
R E
P A
IR
D
E T
A
IL
S .D
G N
A C
T U
A L
F
IL
E : (See Note 2)
Bents #35 and #36
Shim beam #6 at
Pile
Sister bent cap (Typ.)
Pile cap
Splice block Curb
Splice block
Pile (Typ.)
Cross bracing (Typ.)
Stringer (Typ.)
Stringer
NPS
NO.NO.
PMIS STATE PROJECT
NUMBER
SHEET
180254 VA
1D48, 1E15
VA NP COLO 1C14,
222622, 222643, 222642
222636, 222632, 323954, 222594
PROJECT TEAM LEADERSCALECHECKED BYDESIGNED BY
KDN KDN DL
DRAWN BY
Christopher Negley of
DATE BRP NO.BRIDGE PLAN SHEET
November 2023 BRP-131246
COLONIAL NATIONAL HISTORICAL PARK
Structure Number
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
14'-0"
8"8"
R13
M
P R
O J E
C T
S \c o lo
\1 c d e
\B ri d g e \M ic ro s ta ti o n \B ri d g e D e s ig n F il e s \0
P R
O J E
C T
S
.d g n
CURB DETAILS
REVISIONSNO. DATE BYNO. DATE BY REVISIONS
/2
/2
Not to Scale
R C
O L
O
B
C
D
S E
C T
P
.D G
N A
C T
U A
L F
IL
E
: 4290-028P, 4290-029P, 4290-031P
DETAIL A
CURB ELEVATION
(Exterior Span)
Glued laminated panel deck
" x 14'-0"8 guard wheel
Glulam head bolt
1" Dia. dome block scupper
Glulam spike (Typ.)
head drive
" dome12 head bolt (Typ.)
1" Dia. dome
C…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .