Plans
6 MB Posted
- Attached to
- COPY PAPER BID
- Solicitation number
- 22-041
- Issued by
- Georgia
About this file
This is a plan set document for the Veterans Park Interim Phase 2 Improvements project in Sandy Springs, Fulton County, Georgia, prepared by the City of Sandy Springs in coordination with design professional Barge Design Solutions. The project involves demolition, grading, erosion and sediment control, and site improvements on approximately 0.80 acres of disturbed area. The scope of work includes removal of existing concrete, asphalt, building pads, walls, footings, fencing, and vegetation; site grading and fill operations; installation of silt fence and sediment control measures; construction exit stabilization; and sodding of disturbed areas with certified Cynodon dactylon 'Tifway 419' sod on a minimum of 6 inches of prepared topsoil. The project requires compliance with erosion and sediment control standards, including sediment storage calculations requiring 54 cubic yards of storage capacity provided through silt fence (775 linear feet), inlet sediment traps, and continued maintenance throughout construction. A non-mandatory pre-bid site visit is scheduled for March 1, 2022 at 10:00 a.m. at City Hall, with questions due by March 7, 2022 at 5:00 p.m., and bids due March 17, 2022 at 2:00 p.m. via the Bonfire Portal. The plans note that all disturbed areas must be stabilized with permanent vegetation and that the contractor is responsible for soil testing, compliance with the soil management plan prepared by United Engineering, and remediation of any contamination prior to material import or removal, as this site is classified as a brownfield property.
Pricing terms are to be submitted on a unit price basis through the Bonfire Portal, with structural fill material haul-in costs excluded from the base bid and priced separately. The contractor must provide all labor, materials, equipment, and disposal at the contractor's expense in accordance with federal, state, and local laws and regulations. All existing utilities must be protected, and any damage caused by demolition or construction activities must be repaired at no cost to the owner. The contractor is responsible for obtaining all necessary permits, providing temporary security fencing and windscreen supplied by the City, and conducting a preconstruction meeting with Sandy Springs' Community Development Department prior to commencing demolition or erosion control activities. Award is anticipated within sixty days of bid opening.
Text of this file
PART 1 - INDEX OF DRAWINGSCONTACTS
SANDY SPRINGS, FULTON COUNTY, GEORGIA
VETERANS PARK, INTERIM PHASE 2 IMPROVEMENTS - PART 1 of 2
V E
T E
R A
N S
P
A R
K
I N
T E
R I M
H A
E
P R
O V
E M
E N
T
A R
T
S A
N D
Y
S
P R
I N
G S
F
U L
T O
N
C
O U
N T
Y
G
E O
R G
I A
C I T
Y
O
F
S
A N
D Y
R
I N
G S
C0.0
VICINITY MAP
NOT TO SCALE
DESCRIPTIONSHEET NO.
DESIGN PROFESSIONAL BARGE DESIGN SOLUTIONS
2839 PACES FERRY ROAD / SUITE 850
ATLANTA, GA 30339
770.628.7631
CONTACT: JOHN FISH
CITY OF SANDY SPRINGS
Know what'sbelow
Callbefore you dig.
www.call811.com
Know what'sbelow
Callbefore you dig.
www.call811.com
SITE
N
C0.0 COVER SHEET
C1.0 EXISTING CONDITIONS
C2.0 DEMOLITION PLAN
C3.0 EROSION & SEDIMENT CONTROL PLAN
L1.0 SITE IMPROVEMENTS PLAN
L2.0 SITE DETAILS
PROJECT No.
3801308
Copyright 2020, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
U S
E R
L E
L O
V E
F I L E
F
C
A D
L A
N D
I n t e r i m
I N
T E
R I M
P
H C
O V
R d w g
P L O
T T
E D
S A
V E
D
2839 Paces Ferry Road // Suite 850 // Atlanta, Georgia 30339
Phone (770) 628-7361 // Fax (770) 805-0903
OWNER CITY OF SANDY SPRINGS
1 GALAMBOS WAY
SANDY SPRINGS, GA 30328
770.730.5600
CONTACT: RICHARD COLLINS
January 13, 2022
Date: 02/15/2022
These plans were NOT reviewed with respect to any building codes or structural design.
Code compliance and structural integrity are the responsibility of the owner and builder.
The building permit is subject to all City of Sandy Springs ordinances and Georgia State laws.
PERMIT # __________________
Permitted
Pool20-00123
LD
P
-0
M ou nt V er no n H w y
W W W
C1.0
I N
T E
R
A
V
E T
E R
A N
S
P
A R
K
C I T
Y
O
F
S
A N
R
I N
G S
S A
N D
Y
S
P R
I N
G S
F
U L T
O
C
U
N T
Y
G
E O
R G
I A
PROJ. NO.
C H
K
D R
D
A T
E D
E S
C R
I P
T I O
N R
E V
Copyright 2020, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
P a c e s
F e r r y
R o a d
S u i t e
A t l a n t a
G
A
P H
O N
E
F
X
U S
E R
L E
L O
V E
F I L E
F
C
A D
L A
N D
I n t e r
I N
T E
R I M
P
H
I M
P R
O V
E M
E N
T S d w g
P L O
T T
E D
S A
V E
D
Know what'sbelow
Callbefore you dig.
www.call811.com
Know what'sbelow
Callbefore you dig.
www.call811.com
: 3801308
C R
L D
P L E
L
E X
I S
T I N
G
C
O N
D I T
I O
N S
20' 40'
SCALE: 1 INCH = 20 FEET
10'20' 0'
ESTIMATED SOIL REMEDIATION LIMITS;
SEE SOIL REMEDIATION PLAN
1. ORIGINAL SURVEY INFORMATION PROVIDED
BY SANDY SPRINGS / JACOBS ENGINEERING.
2. THE PROPOSED GRADING ON THE WEST SIDE
OF THE PROJECT SITE IS PER DESIGN
DRAWINGS & NOT CONFIRMED AS-BUILT
SURVEYED INFORMATION.
SURVEY NOTES:
Date: 02/15/2022
These plans were NOT reviewed with respect to any building codes or structural design.
Code compliance and structural integrity are the responsibility of the owner and builder.
The building permit is subject to all City of Sandy Springs ordinances and Georgia State laws.
PERMIT # __________________
Permitted
LDP21-00100
LD
P
-0
M ou nt V er no n H
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
LOD
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L O
D
L O
D
L O
D
LEGEND
REMOVE ALL EXISTING CONCRETE,
ASPHALT, BUILDING PADS, WALLS &
FOOTINGS, FENCING, EXISTING
VEGETATION & DEBRIS
DEMOLITION KEYNOTES
SAWCUT ASPHALT PAVEMENT / CONCRETE
SAWCUT ASPHALT / CONCRETE @ BACK OF
CURB
C2.0
I N
T E
R
A
V
E T
E R
A N
S
P
A R
K
C I T
Y
O
F
S
A N
R
I N
G S
S A
N D
Y
S
P R
I N
G S
F
U L T
U
N T
Y
G
E O
R G
I A
PROJ. NO.
C H
K
D R
D
A T
E D
E S
C R
I P
T I O
N R
E V
Copyright 2020, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
P a c e s
F e r r y
R o a d
S u i t e
A t l a n t a
G
A
P H
O N
E
F
U S
E R
L E
L O
V E
F I L E
F
C
A D
L A
N D
I n t e r
I N
T E
R I M
P
H
I M
P R
O V
E M
E N
T S d w g
P L O
T T
E D
S A
V E
D
Know what'sbelow
Callbefore you dig.
www.call811.com
Know what'sbelow
Callbefore you dig.
www.call811.com
: 3801308
C R
L D
P L E
L
D E
M O
L I T
I O
N
P
L A
N
20' 40'
SCALE: 1 INCH = 20 FEET
10'20' 0'
DEMO NOTES:
CONTRACTOR SHALL PROTECT AND RESTORE ALL
PROPERTY TO REMAIN TO A CONDITION SIMILAR OR EQUAL
TO THAT EXISTING AT THE COMMENCEMENT OF
CONSTRUCTION EXCEPT AS NOTED.
SAWCUT PERIMETER OF AREA TO BE DEMOLISHED &
REMOVE A SUFFICIENT AREA TO INSTALL SILT FENCE PRIOR
TO REMOVING FURTHER PAVEMENT OR CONCRETE.
DEMOLITION DEBRIS AND ANY SURPLUS MATERIAL NOT
REQUIRED FOR SITE CONSTRUCTION SHALL BE DISPOSED
OF BY THE CONTRACTOR AT THE CONTRACTOR'S EXPENSE,
IN ACCORDANCE WITH ALL FEDERAL, STATE, AND LOCAL
LAWS AND REGULATIONS.
ALL DEPRESSIONS/EXCAVATIONS CREATED BY
CONTRACTOR'S ACTIVITIES, INCLUDING DEMOLITION SHALL
BE FILLED AND COMPACTED TO MATCH PROPOSED OR
EXISTING GRADES. IF ANY FILL MATERIAL IS REQUIRED, IT
SHALL BE FURNISHED AT THE CONTRACTOR'S EXPENSE.
GRADE SITE TO DRAIN, LEAVE NO STANDING WATER AREAS.
HAUL-IN OF STRUCTURAL FILL MATERIAL USED TO MEET
PROPOSED GRADES SHALL BE DONE ON A UNIT PRICE BASIS
AND SHALL NOT BE INCLUDED IN THE BASE BID (SEE BID
FORM).
PROVIDE SUITABLE SOIL AS FILL MATERIAL. SATISFACTORY
SOILS SHALL INCLUDE NATIVE NORTH GEORGIA SOILS FREE
OF ROCK OR GRAVEL LARGER THAN 3" IN ANY DIMENSION,
DEBRIS, VEGETATION, STICKS, LOGS, CONSTRUCTION
WASTE MATERIALS, FROZEN OR OTHER DELETERIOUS
MATTER. PLACE SOIL IN 6" LIFTS AND COMPACT SOIL TO 98%
STD PROCTOR.
THE CONTRACTOR SHALL PROTECT ALL EXISTING UTILITIES
TO REMAIN IN SERVICE. THE CONTRACTOR SHALL NOTIFY
THE APPROPRIATE GOVERNING AUTHORITY AND ENGINEER
PRIOR TO OR WITHIN 2 HOURS OF ANY DISRUPTION IN
SERVICE. THE CONTRACTOR SHALL MAKE ANY REPAIRS
NECESSARY TO RESTORE SERVICE AT THE CONTRACTOR'S
EXPENSE.
ALL EXISTING STORM DRAINAGE AND SANITARY SEWER
APPURTENANCES, STRUCTURES AND PIPES SHALL REMAIN
UNLESS DESIGNATED OTHERWISE.
CONTRACTOR SHALL COMPLY WITH ALL FEDERAL, STATE,
AND LOCAL LAWS, REGULATIONS AND ORDINANCES.
IN THE EVENT OF DISCREPANCIES AND/OR ERRORS FOUND
IN THE DRAWINGS, OR IF PROBLEMS ARE ENCOUNTERED
DURING CONSTRUCTION, THE CONTRACTOR IS REQUIRED
TO NOTIFY THE ENGINEER BEFORE PROCEEDING WITH THE
WORK. IF ENGINEER IS NOT NOTIFIED, THE CONTRACTOR
SHALL TAKE FULL RESPONSIBILITY FOR THE COST OF ANY
REVISIONS HE MAY INCUR.
CONTRACTOR SHALL GIVE ALL NECESSARY NOTICES AND
OBTAIN ALL PERMITS.
IT IS THE INTENT TO REMOVE AND HAUL-OFF ALL
DESIGNATED BUILDING FOUNDATIONS, SIDEWALKS,
PARKING LOTS, ROADWAYS, CURBS AND UTILITIES AS
SHOWN ON THE DRAWINGS.
ALL BUILDING FOUNDATIONS AND APPURTENANCES SHALL
BE REMOVED COMPLETELY. ANY BELOW GRADE WALLS,
FOUNDATIONS, VAULTS, PITS, SLABS OR ANY OTHER BELOW
GRADE EQUIPMENT, STRUCTURES OR STRUCTURAL
COMPONENTS SHALL BE BROKEN UP, REMOVED, AND
PROPERLY DISPOSED OF.
SIDEWALKS, CURBS, CURB & GUTTERS, AND PAVEMENTS TO
BE REMOVED ALONG WITH BASE STONE.
CATCH BASINS, DRAINAGE STRUCTURES AND PIPES TO
REMAIN IN PLACE AND BE PROTECTED DURING DEMOLITION
ACTIVITIES. CONTRACTOR SHALL REPAIR ANY DAMAGE
CAUSED BY DEMOLITION AT NO COST TO THE OWNER.
INITIAL EROSION AND SEDIMENT CONTROL MEASURES TO BE
IN PLACE PRIOR TO DEMOLITION ACTIVITIES. SEE SHEET
C2.0.
UPON COMPLETION OF DEMOLITION AND REMOVAL OF
EQUIPMENT, MATERIAL, AND DEBRIS, ALL REMAINING HOLES,
OPEN PITS AND OTHER HAZARDOUS EXCAVATIONS SHALL
BE FILLED TO PROPOSED GRADE WITH SUITABLE FILL
APPROVED BY THE ENGINEER. PLACE SOIL IN 6" LIFTS AND
COMPACT SOIL TO 98% STD PROCTOR.
CONTRACTOR SHALL PROTECT & STORE ALL CONCRETE
WHEEL STOPS FOUND WITHIN DEMO AREAS FOR FUTURE
USE ON SITE. SEE SHEET L1.0 FOR FUTURE USE
INSTRUCTION.
CONTRACTOR SHALL PLACE CITY-OWNED CONSRUCTION
FENCE WHERE NEEDED DURING CONSTRUCTION.
CONTRACTOR SHALL DELIVER THE FENCE TO THE CITY
WAREHOUSE ONCE THE PROJECT IS COMPLETE AND THE
FENCE IS NO LONGER NEEDED.,
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
B.O.C.
PROTECT ALL UTILITIES
WITHIN DASHED ZONE;
LEAVE AREA UNDISTURBED
PROTECT ALL UTILITIES
WITHIN DASHED ZONE;
LEAVE AREA UNDISTURBED
PROTECT ALL UTILITIES
WITHIN DASHED ZONE;
LEAVE THIS AREA
UNDISTURBED
ENSURE SMOOTH / FLUSH GRADE &
MATERIAL TRANSITION BETWEEN
PHASE 1 & PHASE 2 WORK
ENSURE SMOOTH / FLUSH GRADE &
MATERIAL TRANSITION BETWEEN
PHASE 1 & PHASE 2 WORK
B.O.C.
B.O.C.
B.O.C.
B.O.C.
Date: 02/15/2022
These plans were NOT reviewed with respect to any building codes or structural design.
Code compliance and structural integrity are the responsibility of the owner and builder.
The building permit is subject to all City of Sandy Springs ordinances and Georgia State laws.
PERMIT # __________________
Permitted
Pool20-00123
LD
P
-0
M ou nt V er no n H
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
LOD
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L O
D
L O
D
L O
D
Sd2-P
Sd2-G
LAT: 33.9243
LONG: -84.3784
Co
Sd1-S
Sd1-S
FS: 1087.66
FS: 1087.60
DuDu
ALL DISTURBED AREAS
Ds1Ds1
C3.0
I N
T E
R
A
V
E T
E R
A N
S
P
A R
K
C I T
Y
O
F
S
A N
R
I N
G S
S A
N D
Y
S
P R
I N
G S
F
U L T
U
N T
Y
G
E O
R G
I A
PROJ. NO.
C H
K
D R
D
A T
E D
E S
C R
I P
T I O
N R
E V
Copyright 2020, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
P a c e s
F e r r y
R o a d
S u i t e
A t l a n t a
G
A
P H
O N
E
F
U S
E R
L E
L O
V E
F I L E
F
C
A D
L A
N D
I n t e r
I N
T E
R I M
P
H
I M
P R
O V
E M
E N
T S d w g
P L O
T T
E D
S A
V E
D
Know what'sbelow
Callbefore you dig.
www.call811.com
Know what'sbelow
Callbefore you dig.
www.call811.com
: 3801308
C R
L D
P L E
L
E R
O S
I O
D
I M
E N
T
C
O N
T R
O L
P
L A
N
20' 40'
SCALE: 1 INCH = 20 FEET
10'20' 0'
Co
NOTE:
1. ALL PERVIOUS AREAS WILL BE SODDED OR
PLANTED AFTER FINE GRADING IS COMPLETE
2. SILT SOX MAY BE NEEDED TEMPORARILY
UNTIL FULL INSTALLATION OF SILT FENCE CAN
BE ACCOMPLISHED
LEGEND
EXISTING CONTOURS
LIMITS OF DISTURBANCE
LOD
LOD
DISTURBED AREA - 0.80 ACRES
SEDIMENT STORAGE CALCULATIONS
REQUIRED STORAGE = 67 CY PER ACRE DISTURBED
REQUIRED STORAGE = 0.80 ACRES DISTURBED X 67 CY/ACRE = 54 CY
STORAGE PROVIDED BY SILT FENCE = 775 LF X 1.5 SF = 1,163 CF OR 43 CY
STORAGE PROVIDED BY INLET SEDIMENT TRAP = 0.53' DEPTH (ELEV. 1088
TO ELEV. 1087.43) X 721.5 SF ((1,389 + 54) / 2) AREA = 382 CF OR 14 CY
57 CY TOTAL STORAGE PROVIDED
57 CY PROVIDED = 54 CY REQUIRED
**THIS PROJECT DISTURBS LESS THAN ONE ACRE AND DUE TO THE
LIMITED AVAILABLE SPACE A SEDIMENT BASIN IS INFEASIBLE. SEDIMENT
STORAGE WILL BE PROVIDED BY UTILIZING THE PROPOSED SILT FENCE,
PROPOSED INLET SEDIMENT TRAP AND ENSURING CONTINUED
MAINTENANCE OF THE FENCE THROUGHOUT CONSTRUCTION.
NOTES:
A. Prior to any other construction, a stabilized construction entrance shall be constructed at each entry to or exit from the SITE
B. The construction exits shall be maintained in a condition which will prevent tracking or flow of mud on to public right-of-way. This may require periodic top dressing with stone, as conditions demands, and repair and/or clean-out of any structures used to trap sediment. All materials spilled, dropped, washed, or tracked from vehicle onto public roadway or into storm drain must be removed.
C. Prior to commencing land disturbance activity the limits of land disturbance shall be clearly and accurately demarcated with stakes, ribbons, or other appropriate means. The location and extent of all authorized land disturbance shall occur within the approved limits indicated on the approved plans.
D. Immediately after the establishment of construction entrances/exits, all perimeter erosion control devices and storm water management devices shall be installed prior to any other construction.
E. The contractor shall furnish and maintain all necessary barricades while roadway frontage improvements are being made. Any necessary traffic control measures, including temporary land closures, shall be permitted by and coordinated with the City of Sandy Springs.
F. The construction of the site will initiate with the installation of erosion control measures sufficient to control sediment deposits and erosion. All sediment control will be maintained until all up stream ground within the construction area has been completely stabilized with permanent vegetation and all roads/driveways have been paved.
G.Failure to install, operate or maintain all erosion control measures will result in all construction being stopped on the job site until such measures are corrected back to
City of Sandy Springs Standards.
H. A copy of the approved land disturbance plan and permit shall be present on the site whenever land disturbance activity is in progress.
I. During construction the Contractor shall install and maintain all necessary pedestrian and vehicular signage as required by The City. Including "Sidewalk Closed" signs, warning barrels and barricade structures.
J. Contractor shall utilize temporary security fencing and windscreen as provided by The City. Contractor shall relocate fencing and anchor fencing as necessary for security and construction activity. Contractor shall deliver the fence and windscreen to the City warehouse once the project is complete and the fence is no longer needed onsite.
K. Prior to commencing any demolition or erosion control activity the contractor shall conduct a preconstruction meeting on-site with the Sandy Springs' Community
Development Department.
A crushed stone pad located at the construction site exit to provide a place for removing mud from tires thereby protecting public streets.
CONSTRUCTION
EXIT
CoCo
(LABEL)
A barrier to prevent sediment from leaving the construction site. It may be sandbags, bales of straw or hay, brush, logs and poles, gravel, or a silt fence.
SEDIMENT
BARRIER
Sd1-S
Establishing a temporary vegetative cover with fast growing seedings on disturbed areas.
Establishing temporary protection for disturbed areas where seedlings may not have a suitable growing season to produce an erosion retarding cover.
Ds1
DISTURBED AREA
STABILIZATION
(WITH MULCHING
ONLY)
DISTURBED AREA
STABILIZATION
(WITH TEMP
SEEDING)
Ds2Ds2
Ds1Ds1Ds1
Ds2Ds2
Controlling surface and air movement of dust on construction site, roadways and similar sites.
DUST CONTROL ON
DISTURBED AREAS
DuDuDuDu
An impounding area created by excavating around a storm drain drop inlet. The excavated area will be filled and stabilized on completion of construction activities.
INLET
SEDIMENT
TRAP
Sd2
PROPOSED CONTOURS
C I T
Y
C
O M
M E
N T
S
C R
L E
L
Date: 02/15/2022
These plans were NOT reviewed with respect to any building codes or structural design.
Code compliance and structural integrity are the responsibility of the owner and builder.
The building permit is subject to all City of Sandy Springs ordinances and Georgia State laws.
PERMIT # __________________
Permitted
LDP21-00100
LD
P
-0
M ou nt V er no n H
L
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
LOD
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L
O
D
L O
D
L O
D
L O
D
FS: 1087.66
FS: 1087.60
L1.0
I N
T E
R
A
V
E T
E R
A N
S
P
A R
K
C I T
Y
O
F
S
A N
R
I N
G S
S A
N D
Y
S
P R
I N
G S
F
U L T
U
N T
Y
G
E O
R G
I A
PROJ. NO.
C H
K
D R
D
A T
E D
E S
C R
I P
T I O
N R
E V
Copyright 2020, Barge Design Solutions, Inc. ALL RIGHTS RESERVED
P a c e s
F e r r y
R o a d
S u i t e
A t l a n t a
G
A
P H
O N
E
F
U S
E R
L E
L O
V E
F I L E
F
C
A D
L A
N D
I n t e r
I N
T E
R I M
P
H
I M
P R
O V
E M
E N
T S d w g
P L O
T T
E D
S A
V E
D
Know what'sbelow
Callbefore you dig.
www.call811.com
Know what'sbelow
Callbefore you dig.
www.call811.com
: 3801308
C R
L D
P L E
L
S I T
E
I M
P R
O V
E M
E N
L
20' 40'
SCALE: 1 INCH = 20 FEET
10'20' 0'
LEGEND
AGGREGATE LAYDOWN YARD (APPROX.
11,000 SF); SEE DETAIL 1/L1.0 (THIS
SHEET)
SOD - INSTALL SOD TO THE EXTENTS OF
DEMO AREAS. ALL SOD SHALL BE
INSTALLED ON 6" MIN. OF PLANTING / TOP
SOIL. SOD TYPE: CYNODON DACTYLON
`TIFWAY 419`, CERTIFIED PURE, WEED
FREE ; SEE DETAIL 2/L1.0 & SODDING
NOTES (THIS SHEET)
GRADING NOTES:
1. ALL AREAS OF DEMOLITION THAT ARE TO RECEIVE
SOD INSTALLATION SHALL BE CLEANED & GRADED
SMOOTH. FINISH GRADES SHALL TAPER TO MEET
SURROUNDING EXISTING, GRADES.
EXISTING CONTOURS
PROPOSED CONTOURS
1. SOD ALL AREAS AS INDICATED ON THE PLANS. SOD IS TO BE SAND
BASED SOD. CONTRACTOR TO SUBMIT SOD VARIETY TO LANDSCAPE
ARCHITECT FOR REVIEW. ALL SLOPES GREATER THAN 3:1 SHALL BE
PEGGED TO HOLD SOD IN PLACE. ALL DRAINAGE SWALES ARE TO
RECEIVE A 6' WIDE BAND OF SOD. PROVIDE A 3' WIDE BAND OF SOD
AROUND ALL DRAINAGE INLETS.
2. 6" OF TOPSOIL SHALL BE PROVIDED ON ALL AREAS TO BE SODDED,
INSTALLED AND STABILIZED PRIOR TO SOD.
3. SOD BED PREPARATION: LOOSEN SUBGRADE OF LAWN AREAS TO
A MINIMUM DEPTH OF 6 INCHES. REMOVE STONES MEASURING OVER
1 INCH IN ANY DIMENSION. REMOVE STICKS, ROOTS, RUBBISH, AND
OTHER EXTRANEOUS MATTER. ADD SOIL AMENDMENTS IN
ACCORDANCE WITH SOIL TEST REQUIREMENTS AND MIX
THOROUGHLY INTO UPPER 6 INCHES OF SOIL.
4. FINE GRADE LAWN AREAS TO SMOOTH, EVEN SURFACE WITH
LOOSE, UNIFORMLY FINE TEXTURE. ROLL, RAKE, AND DRAG LAWN
AREAS, REMOVE RIDGES AND FILL DEPRESSIONS, AS REQUIRED TO
MEET FINISH GRADES.
5. FERTILIZER: CONTRACTOR SHALL PERFORM A SOIL TEST PRIOR
TO SEEDING AND APPLICATION OF ANY SOIL AMENDMENTS, AND
SUBMIT RESULTS OF SOIL TESTS TO LANDSCAPE ARCHITECT FOR
APPROVAL. APPLY ALL AMENDMENTS PER SOIL TEST
RECOMMENDATIONS. SPREAD LIME AND FERTILIZER UNIFORMLY
OVER ALL AREAS IMMEDIATELY BEFORE FINAL LAND PREPARATION
AND MIX THOROUGHLY WITH THE SOIL.
6. SOD IS TO BE ROLLED AND WATERED WITHIN 5 DAYS OF
INSTALLATION.
7. AFTER TWO WEEKS, TOPDRESS AND THOROUGHLY WATER.
TOPDRESS SHALL CONSIST OF .5 TO 1 POUND: 38% UREA
FORMALDEHYDE PER 1,000 S.F. AND 20 POUNDS OF 6-12-12
FERTILIZER.
8. TOP DRESS SODDED AREAS WITH CLEAN, WEED FREE BUILDER'S
SAND MAY BE REQUIRED IF DEEMED NECESSARY BY THE LANDSCAPE
ARCHITECT TO FILL ANY DEPRESSIONS OR IRREGULARITIES IN THE
SOD.
9. SOD IS TO BE LAID AS SOON AS IT IS DELIVERED TO PLANTING
AREAS. ONLY HEALTHY, MOIST, AND GREEN SOD IS TO BE LAID. ANY
SOD WHICH IS BROWN AND UNDER STRESS IS UNACCEPTABLE. ANY
SOD WHICH IS NOT LAID WITHIN 24 HOURS OF DELIVERY IS
UNACCEPTABLE UNLESS APPROVED BY THE LANDSCAPE ARCHITECT.
10. REPAIR AND RESOD ALL ERODED OR DISTRUBED SOD AREAS
WHERE DESIRED VEGETATIVE COVER HAS NOT BEEN ESTABLISHED,
OR WHERE NOXIOUS WEEDS EMERGE.
11. CONTRACTOR IS RESPONSIBLE FOR WATERING AND
MAINTENANCE OF SODDED AREAS UNTIL AREAS EXHIBIT HEALTHY
AND VIGOROUS GROWTH AS DETERMINED BY LANDSCAPE
ARCHITECT.
SODDING NOTES
UNDISTURBED SUBGRADE / EXISTING SOIL
NOTE:
SOD PIECES ARE TO BE BUTTED UP
AGAINST EACH OTHER WITH NO GAPS.
IF THERE ARE GAPS THEY SHOULD BE
FILLED WITH SOD OR SAND.
PAVEMENT
SOD AS
SPECIFIED
PREPARED
SOIL
1/2" EDGER TO BE SMOOTH
CLEAN & PARALLEL TO
PAVEMENT
6" SOD SOIL MIX
SOIL & ROOT LAYER TO BE LEVEL
WITH TOP OF PAVEMENT
ROLL SOD & WATER THOROUGHLY
COMPACTED SUBGRADE,
95% PROCTOR
57 STONE, WASHED CLEAN
89 STONE, WASHED CLEAN
AGGREGATE LAYDOWN SPACE
NTS
L1.0
SOD PLANTING
NTS
L1.0
1. PRIOR TO THE START OF WORK, THE LANDSCAPE CONTRACTOR SHALL ASCERTAIN THE LOCATION
OF ALL SURFACE AND UNDERGROUND UTILITIES, ETC., AND SHALL TAKE PROPER PRECAUTIONS TO
PREVENT DAMAGE TO SUCH IMPROVEMENTS. IN THE EVENT ANY UTILITIES ARE UNCOVERED, THE
LANDSCAPE CONTRACTOR SHALL PROMPTLY NOTIFY THE LANDSCAPE ARCHITECT. THE LANDSCAPE
CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING ALL UTILITIES FROM DAMAGE DURING
CONSTRUCTION AND TO REPAIR ANY DAMAGE WHICH SHOULD OCCUR TO THE SATISFACTION OF
THE OWNER.
2. DAMAGE BY CONTRACTOR TO UNDISTURBED AREAS OUTSIDE THE LIMITS OF CONSTRUCTION
SHALL BE REPAIRED BY CONTRACTOR TO THE SATISFACTION OF THE OWNER.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL LANDSCAPE QUANTITY CALCULATIONS AND
THE LIABILITY WHICH PERTAINS TO THOSE QUANTITIES AND ANY RELATED CONTRACT DOCUMENTS
AND/OR PRICE QUOTATIONS. LANDSCAPE CONTRACTOR IS RESPONSIBLE FOR PROVIDING PLANT
QUANTITIES REQUIRED TO COVER SPECIFIED AREAS AT THE DESIGNATED SPACING.
4. CONTRACTOR IS RESPONSIBLE FOR CONDUCTING SITE INSPECTION PRIOR TO BIDDING WORK, TO
DETERMINE SITE CONDITIONS AND AREAS TO BE PLANTED. SUBMISSION OF BID INDICATES
CONTRACTOR HAS VERIFIED SITE CONDITIONS AND PLANT MATERIAL QUANTITIES.
5. SUBSTANTIAL COMPLETION: WILL BE PROVIDED AFTER THE CONTRACTOR HAS SATISFACTORILY
COMPLETED WORK REQUIREMENTS AS SPECIFIED. THE LANDSCAPE ARCHITECT WILL CONDUCT A
SUBSTANTIAL COMPLETION INSPECTION AND PROVIDE A PUNCH LIST OF OBSERVED DEFICIENCIES.
6. FINAL ACCEPTANCE: THE LANDSCAPE ARCHITECT WILL PROVIDE THE FINAL INSPECTION AFTER
THE CONTRACTOR HAS SATISFACTORILY CORRECTED THE DEFICIENCIES ON THE SUBSTANTIAL
COMPLETION PUNCH LIST. SHOULD THE LANDSCAPE ARCHITECT INSPECTION FIND WORK
INCOMPLETE, THE CONTRACTOR SHALL REMEDY THE DEFICIENCIES.
7. DURING LANDSCAPE INSTALLATION KEEP PAVEMENTS CLEAN AND WORK AREA IN ORDERLY
CONDITION.
8. CONTRACTOR TO REPAIR ANY PAVEMENTS, CURBS, DRAINAGE AND OTHER IMPROVEMENTS
DAMAGED AS A RESULT OF LANDSCAPE INSTALLATION ACTIVITIES.
GENERAL NOTES
9. THE CONTRACTOR SHALL NOT CHANGE OR SUBSTITUTE PLANT VARIETIES OR
SPECIES WITHOUT THE WRITTEN PERMISSION OF THE LANDSCAPE ARCHITECT.
10. THE CONTRACTOR IS RESPONSIBLE FOR COMPLYING WITH ALL LOCAL, STATE,
AND FEDERAL CONSTRUCTION CODES AND SECURING ALL NECESSARY PERMITS.
11. FINAL CLEAN ALL ROADWAYS AND SURROUNDING AREAS OUTSIDE THE LIMITS
OF DISTURBANCE OF MUD, STONE AND OTHER DEBRIS.
12. THE CONTRACTOR IS RESPONSIBLE FOR COMPLIANCE WITH THE SOIL
MANAGEMENT PLAN PREPARED BY UNITED ENGINEERING. THIS SITE IS A
BROWNFIELD SITE AND AS SUCH ALL SOILS ENTERING THE SITE OR REMOVED
FROM THE SITE SHALL BE TESTED FOR ORGANIC CONTAMINATION PRIOR TO
INSTALLATION OR REMOVAL FROM THE SITE. ALL TESTING SHALL BE CONDUCTED
AND PAID FOR BY THE CITY OF SANDY SPRINGS.
13. DO NOT SCALE FROM DRAWING.
N
P
R
ENSURE SMOOTH / FLUSH GRADE &
MATERIAL TRANSITION BETWEEN
PHASE 1 & PHASE 2 WORK
ENSURE SMOOTH / FLUSH GRADE &
MATERIAL TRANSITION BETWEEN
PHASE 1 & PHASE 2 WORK
B.O.C.
B.O.C.
B.O.C.
B.O.C.
B.O.C.
T.O.C.
ELEV. 1087.75±
T.O.C.
ELEV. 1087.75±
EXISTING UTILITIES, TYP.
PROTECT EXISTING
INLET GRATE
RIM: 1087.47
OE: 1085.17
BEGIN VEHICULAR BARRIER FENCE; MATCH &
CONNECT TO PHASE 1 VEHICULAR BARRIER;
SEE IMAGE 1 THIS SHEET FOR REFERENCE
BEGIN VEHICULAR BARRIER FENCE; MATCH &
CONNECT TO PHASE 1 VEHICULAR BARRIER;
SEE IMAGE 1 THIS SHEET FOR REFERENCE
END VEHICULAR BARRIER FENCE;
MATCH PHASE 1 VEHICULAR
BARRIER; SEE IMAGE 1 THIS
SHEET FOR REFERENCE
END VEHICULAR BARRIER FENCE; MATCH
PHASE 1 VEHICULAR BARRIER; SEE
IMAGE 1 THIS SHEET FOR REFERENCE
EX. DWBC
RIM: 1087.85
IE: 1084.54
OE: 1083.93
CONTRACTOR TO ENSURE STORMWATER FROM
DISTURBED SITE DOES NOT ENTER MOUNT VERNON
HIGHWAY. ENSURE DISTURBED AREA IS GRADED
TO DRAIN TO EXISTING GRATE INLET ON SITE.
C I T
Y
C
O M
M E
N T
S
C R
L E
L
Image 1
LD
P
-0
M ou nt V er no n H w y
Date: 02/15/2022
These plans were NOT reviewed with respect to any building codes or structural design.
Code compliance and structural integrity are the responsibility of the owner and builder.
The building permit is subject to all City of Sandy Springs ordinances and Georgia State laws.
PERMIT # __________________
Permitted
Pool20-00123
L2.0
N
T E
R
A
V
E T
E R
A N
S
P
A R
K
C I T
Y
O
F
S
A N
R
I N
G S
S A
N D
Y
S
P R
I N
G S
F
U L
T O
N
C
O U
N T
Y
G
E O
R G
I A
PROJ. NO.
C H
K
D R
D
A T
E D
E S
C R
I P
T I O
N R
E V
Copyright 2020, Barge Design Solutions, Inc. ALL RIGHTS RESERVED a c e s
F e r r y
R o a d
S u i t e
A t l a n t a
G
A
P H
O N
E
F
U S
E R
L E
L O
V E
F I L E
F
C
A D
L A
N D
I n t e r
I N
T E
R I M
P
H D
E T
A I L S d w g
P L O
T T
E D
S A
V E
D
Know what'sbelow
Callbefore you dig.
www.call811.com
Know what'sbelow
Callbefore you dig.
www.call811.com
: 3801308
C R
L D
P L E
L
S I T
E
D
E T
A I L S
1' MIN. 2' MAX.
BLOCK AND GRAVEL SECTION
BLOCK AND GRAVEL PERSPECTIVE
BLOCK AND GRAVEL SECTION
1' MIN. 2' MAX.
WIRE SCREEN
CONCRETE BLOCK
DEWATERING
DROP INLET GRATE
GRAVEL FILTER SHOULD
HAVE SLOPE OF 2:1
NOTE:
1. HARDWARE CLOTH OR COMPARABLE WIRE MESH WITH
INCH OPENINGS SHALL BE FITTED OVER ALL
BLOCK OPENINGS TO HOLD GRAVEL IN PLACE.
2. THE FOUNDATION SHOULD BE EXCAVATED AT LEAST 2 INCHES BELOW THE CREST OF THE STORM
DRAIN. THE FIRST ROW OF BLOCKS WILL BE PLACED HERE FOR LATERAL SUPPORT.
3. ONE BLOCK (AS SHOWN) IS TO BE PLACED ON EACH SIDE OF THE STRUCTURE ON ITS SIDE IN THE
BOTTOM ROW TO ALLOW FOR POOL DRAINAGE.
FOUNDATION SET 2" BELOW
CREST OF STORM DRAIN
DROP INLET
W/ GRATE
SEDIMENT
RUNOFF WATER
WITH SEDIMENT
DEWATERING
WIRE SCREEN
GRAVEL
TEMPORARY
SEDIMENT POOL
NOTE:
1. HARDWARE CLOTH OR COMPARABLE WIRE MESH WITH
INCH OPENINGS SHALL BE FITTED OVER ALL
BLOCK OPENINGS TO HOLD GRAVEL IN PLACE.
2. THE FOUNDATION SHOULD BE EXCAVATED AT LEAST 2 INCHES BELOW THE CREST OF THE STORM
DRAIN. THE FIRST ROW OF BLOCKS WILL BE PLACED HERE FOR LATERAL SUPPORT.
3. ONE BLOCK (AS SHOWN) IS TO BE PLACED ON EACH SIDE OF THE STRUCTURE ON ITS SIDE IN THE
BOTTOM ROW TO ALLOW FOR POOL DRAINAGE.
FOUNDATION SET 2" BELOW
CREST OF STORM DRAIN
SEDIMENT
DROP INLET
W/ GRATE
TEMPORARY
SEDIMENT POOL
GRAVEL
DEWATERING
RUNOFF WATER
WITH SEDIMENT
WIRE SCREEN
Sd2-G
Sd1-S
EXIT DIAGRAM
CONSTRUCTION EXIT NOTES:
1. AVOID LOCATING ON STEEP SLOPES OR AT CURVES ON PUBLIC ROADS.
2. REMOVE ALL VEGETATION AND OTHER UNSUITABLE MATERIAL FROM THE FOUNDATION AREA, GRADE, AND CROWN FOR POSITIVE DRAINAGE.
3. AGGREGATE SIZE SHALL BE IN ACCORDANCE WITH NATIONAL STONE ASSOCIATION R-2 (1.5"-3.5"
STONE).
4. GRAVEL PAD SHALL HAVE A MINIMUM THICKNESS OF 6".
5. PAD WIDTH SHALL BE EQUAL FULL WIDTH AT ALL POINTS OF VEHICULAR EGRESS, BUT NO LESS THAN
20'.
6. A DIVERSION RIDGE SHOULD BE CONSTRUCTED WHEN GRADE TOWARD PAVED AREA IS GREATER
THAN 2%..
7. INSTALL PIPE UNDER THE ENTRANCE IF NEEDED TO MAINTAIN DRAINAGE DITCHES.
8. WHEN WASHING IS REQUIRED, IT SHOULD BE DONE ON AN AREA STABILIZED WITH CRUSHED STONE
THAT DRAINS INTO AN APPROVED SEDIMENT TRAP OR SEDIMENT BASIN (DIVERT ALL SURFACE
RUNOFF AND DRAINAGE FROM THE ENTRANCE TO A SEDIMENT CONTROL DEVICE).
9. WASH RACKS AND/OR TIRE WASHERS MAY BE REQUIRED DEPENDING ON SCALE AND CIRCUMSTANCE.
IF NECESSARY, WASH RACK DESIGN MAY CONSIST OF ANY MATERIAL SUITABLE FOR TRUCK TRAFFIC
THAT REMOVE MUD AND DIRT.
10. MAINTAIN AREA IN A WAY THAT PREVENTS TRACKING AND/OR FLOW OF MUD ONTO PUBLIC
RIGHTS-OF-WAYS. THIS MAY REQUIRE TOP DRESSING, REPAIR AND/OR CLEAN OUT OF ANY
MEASURES USED TO TRAP SEDIMENT.
FLOW
FLOW
ENTRANCE ELEVATION
Co
CULVERT UNDER
ENTRANCE (IF NEEDED)
DIVERSION RIDGE
(SEE NOTE 6)
N.S.A. R-2 (1.5"-3.5")
COARSE AGGREGATE
TIRE WASHRACK AREA/
TIRE WASHER
SUPPLY WATER TO WASH
WHEELS IF NECESSARY
HARD SURFACE PUBLIC ROAD
SEDIMENT TRAP
(SEE NOTE 8)
GEOTEXTILE UNDERLINER
GEOTEXTILE
UNDERLINER
COARSE AGGREGATE
(N.S.A. R-2)
ORIGINAL
GRADE
Du
18" MIN.
28"
TRENCH
NOTES:
1. USE STEEL OR WOOD POSTS OR AS SPECIFIED BY THE EROSION, SEDIMENTATION,
AND POLLUTION CONTROL PLAN.
FRONT VIEW
28"
30" MIN.
18" MIN.
6"
FABRIC
(WOVEN WIRE
FENCE BACKING)
4' MAX. O.C.
2"
6"
30" MIN.
FLOW
SIDE VIEW
SILT FENCE - TYPE SENSITIVE
Sd2-P
PAVEMENT
CURB APRON (GUTTER)
PAVEMENT
8" CONCRETE
BLOCK WRAPPED
IN FILTER FABRIC
CATCH BASIN
SECTION B-B
4"
CURB INLET FILTER "PIGS IN BLANKET"
8" CONCRETE BLOCK
WRAPPED IN FILTER FABRIC
CURBING
CATCH BASIN
B
PAVEMENT
4"
PLAN
B
PLAN
4"
PAVEMENT
FLOW
B
CATCH BASIN
CURBING
8" CONCRETE BLOCK
WRAPPED IN FILTER FABRIC
GUTTER
CURB INLET FILTER "PIGS IN BLANKET"
4"
FLOW
SECTION B-B
GUTTER
CATCH BASIN
8" CONCRETE
BLOCK WRAPPED
IN FILTER FABRIC
PAVEMENT
CURB
CURB APRON (GUTTER)
PAVEMENT
CATCH BASIN
8" CONCRETE BLOCKS
WRAPPED IN FILTER FABRIC
NOTES:
1. INSTALL FILTER AFTER ANY
ASPHALT PAVEMENT INSTALLATION.
2. WRAP 8" CONCRETE BLOCKS IN
FILTER FABRIC AND SPAN ACROSS
CATCH BASIN INLET.
3. FACE OPENINGS IN BLOCKS
OUTWARD.
4. LEAVE A GAP OF APPROXIMATELY
4 INCHES BETWEEN THE CURB
AND THE FILTERS TO ALLOW FOR
OVERFLOW TO PREVENT
HAZARDOUS PONDING.
5. INSTALL OUTLET PROTECTION
BELOW STORM DRAIN OUTLETS.
NOTES:
1. INSTALL FILTER AFTER ANY
ASPHALT PAVEMENT INSTALLATION.
2. WRAP 8" CONCRETE BLOCKS IN
FILTER FABRIC AND SPAN ACROSS
CATCH BASIN INLET.
3. FACE OPENINGS IN BLOCKS
OUTWARD.
4. LEAVE A GAP OF APPROXIMATELY
4 INCHES BETWEEN THE CURB
AND THE FILTERS TO ALLOW FOR
OVERFLOW TO PREVENT
HAZARDOUS PONDING.
5. INSTALL OUTLET PROTECTION
BELOW STORM DRAIN OUTLETS.
8" CONCRETE BLOCKS
WRAPPED IN FILTER FABRIC
CATCH BASIN
CURB
GUTTER
FLOW
GUTTER
FLOW
B
BLOCK AND GRAVEL
DROP INLET PROTECTION
EROSION AND SEDIMENT CONTROL
COMPOST FILTER SOCK
DISTURBED (WORK) AREA
FLOW
DISTURBED
(WORK) AREA
30" MIN.
18" MIN.
AREA TO BE PROTECTED
FLOW
AREA TO BE PROTECTED
CROSS-SECTION
PLAN
NOTE: FILTER SOCK SIZED TO SUIT
CONDITIONS (SEE APPROVED LIST)
NOTE: FILTER SOCK SIZED TO SUIT
CONDITIONS (SEE APPROVED LIST)
PLAN
CROSS-SECTION
AREA TO BE PROTECTED
FLOW
AREA TO BE PROTECTED
18" MIN.
30" MIN.
DISTURBED
(WORK) AREA
FLOW
DISTURBED (WORK) AREA
COMPOST FILTER SOCK
EROSION AND SEDIMENT CONTROL
Ds1
Date: 02/15/2022
These plans were NOT reviewed with respect to any building codes or structural design.
Code compliance and structural integrity are the responsibility of the owner and builder.
The building permit is subject to all City of Sandy Springs ordinances and Georgia State laws.
PERMIT # __________________
Permitted
LDP21-00100
LD
P
-0
M ou nt V er no n H
| Sheets and Views |
| C0.00_24x36 |
Other files
| File | Type | Posted |
|---|---|---|
| 22-041 RESPONSE FORM | — | |
| Award Information | — | |
| 22-041 COPY PAPER BID | — | |
| Award Information | — | |
| ITB | — | |
| Award Information | — |
On GovTribe
Work with this file